Civil Engineering (CE) Exam  >  Civil Engineering (CE) Tests  >  Mock test series of SSC JE Civil Engineering 2025  >  Test: Estimation & Valuation- 1 - Civil Engineering (CE) MCQ

Test: Estimation & Valuation- 1 - Civil Engineering (CE) MCQ


Test Description

20 Questions MCQ Test Mock test series of SSC JE Civil Engineering 2025 - Test: Estimation & Valuation- 1

Test: Estimation & Valuation- 1 for Civil Engineering (CE) 2024 is part of Mock test series of SSC JE Civil Engineering 2025 preparation. The Test: Estimation & Valuation- 1 questions and answers have been prepared according to the Civil Engineering (CE) exam syllabus.The Test: Estimation & Valuation- 1 MCQs are made for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Estimation & Valuation- 1 below.
Solutions of Test: Estimation & Valuation- 1 questions in English are available as part of our Mock test series of SSC JE Civil Engineering 2025 for Civil Engineering (CE) & Test: Estimation & Valuation- 1 solutions in Hindi for Mock test series of SSC JE Civil Engineering 2025 course. Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free. Attempt Test: Estimation & Valuation- 1 | 20 questions in 12 minutes | Mock test for Civil Engineering (CE) preparation | Free important questions MCQ to study Mock test series of SSC JE Civil Engineering 2025 for Civil Engineering (CE) Exam | Download free PDF with solutions
Test: Estimation & Valuation- 1 - Question 1

Which of the following does not have unit as square meters?

Detailed Solution for Test: Estimation & Valuation- 1 - Question 1

R.C. Chajja is measured in mwhile D.P.C, Form works and Concrete Jaffries is measured in m.

Test: Estimation & Valuation- 1 - Question 2

Mastic asphalt is generally used for:

Detailed Solution for Test: Estimation & Valuation- 1 - Question 2

Mastic asphalt is a mixture of a bitumen binder, stone filler and mineral powder heated and mixed in the hot state. Mastic asphalt has wet consistency as it contains a larger quantity of the binder compared to the common contractible asphalt.

The characteristic features of the mastic road asphalt mix are the following properties:

1. High frost resistance

2. resistant to salt water (salt) and chemicals

3. increased strength, abrasion resistance and heat resistance

4. waterproof (does not absorb moisture and does not swell out due to lack of pores)

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Estimation & Valuation- 1 - Question 3

The estimated value of a built-up property at the end of its useful life without being dismantled is its:

Detailed Solution for Test: Estimation & Valuation- 1 - Question 3

Scrap Value: Scrap Value is the sell value of dismantled materials of an asset at the end of it’s useful life. Scrap Value is counted in the calculation of depreciation of a property, generally @10% of the cost of the Structure.

Salvage value: Salvage Value is the Estimated Value of an asset without dismantling it at the end of it’s useful life.

Book Value: Book value is the amount shown in the account book after allowing necessary depreciations. The book value of a property at a particular year is the original cost minus the amount of depreciation allowed per year and will be gradually reduced year to year and at the end of the utility period of the property, the book value will be only scrap value.

Market Value: The market value of a property is the amount which can be obtained at any particular time from the open market if the property is put for sale. The market value will differ from time to time according to demand and supply.

Test: Estimation & Valuation- 1 - Question 4

The measurement of longitudinal section survey is done on which basis?

Detailed Solution for Test: Estimation & Valuation- 1 - Question 4

The longitudinal section survey is done linearly in Surveying, While Transverse section survey is done on the basis of area.

Test: Estimation & Valuation- 1 - Question 5

In general, while computing volume of earthwork, the volume computed by the prismoidal formula will be compared to that calculated by trapezoidal formula.

Detailed Solution for Test: Estimation & Valuation- 1 - Question 5



By comparing the both it is clear that volume calculated by prismoidal is greater than by trapezoidal formula for same cross section.

Test: Estimation & Valuation- 1 - Question 6

Pick up the correct statement from the following:

Detailed Solution for Test: Estimation & Valuation- 1 - Question 6

There are four main stages in the project for a work, namely,

1. Administrative approval

2. Expenditure sanction

3. Technical sanction

4. Appropriation or re-appropriation of funds

For every work (excluding repairs) initiated by, or connected with, the requirements of another department, it is first necessary to obtain the concurrence of the department concerned to the proposals. The formal acceptance by the department concern is termed “administrative approval” of the work. Expenditure sanction means the concurrence of the Government to the expenditure proposed in cases where this is necessary. Appropriation or re-appropriation represents the allotment of a particular sum of money to meet expenditure on a specified object.

The estimated value of the work excluding the amount for contingencies, work charged establishment, tool and plants, is called Work value. The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost.

Test: Estimation & Valuation- 1 - Question 7

The Brick work is not measured in min case of

Detailed Solution for Test: Estimation & Valuation- 1 - Question 7

Brickwork generally measured in munless specified. Brickwork one brick thick (20 cm) or less shall be measured in separately in m2. While Brick work in arches, Reinforced brick work is measured in m3.

Test: Estimation & Valuation- 1 - Question 8

Berms are provided in canals if these are

Detailed Solution for Test: Estimation & Valuation- 1 - Question 8

Berm is the horizontal distance left at ground level between the toe of the bank and the top edge of cutting. The purpose of providing Berm to help the channel to attain regime conditions, they protect the banks from erosion due to wave action. Berms are to be provided in all cuttings when the depth of cutting is more than 3 meters.

Test: Estimation & Valuation- 1 - Question 9

The standard width of asbestos cement corrugated sheet is

Detailed Solution for Test: Estimation & Valuation- 1 - Question 9

According to IS 13008 : 1990, The overall width of asbestos cement corrugated sheet is 1.015 meter (-5 to + 10 mm tolerance).

Test: Estimation & Valuation- 1 - Question 10

The useful part of liveable area of a building is known as

Detailed Solution for Test: Estimation & Valuation- 1 - Question 10

Carpet area the covered area of the usable spaces of rooms at any floor. It is measured between walls to walls within the building and is the sum of the actual areas of the rooms where you can carpet. Carpet area means the area of the property where you can lay your carpet, measured wall to wall. This is the actual area which you can call your personal space and you should be really concerned about while buying a property.

Circulation area is the floor area of verandah, passages, staircase, balconies etc. which are used for movement of persons using the building.

Plinth area is the covered built-up area measured at the floor level of any storey or at the floor level of the basement. Plinth area is also called as built-up area and is the entire area occupied by the building including internal and external walls. Plinth area is generally 10-20% more than carpet area.

Test: Estimation & Valuation- 1 - Question 11

What is the unit of measuring cornice?

Detailed Solution for Test: Estimation & Valuation- 1 - Question 11

The methods and units of measurements for civil construction works are mainly categorised for their nature, shape and size and for making payments to the contractor. The principle of units of measurements normally consists the following:

1. Single units work like doors, windows, trusses etc., are expressed in numbers.

2. Works consists linear measurements involve length like cornice, fencing, hand rail, bands of specified width etc., are expressed in running metres (RM)

3. Works consists areal surface measurements involve area like plastering, white washing, partitions of specified thickness etc., and are expressed in square meters (m2)

Test: Estimation & Valuation- 1 - Question 12

The cross-section areas of three sections of an embankment at an interval of 40 m are 10 square metres, 15 square metres and 35 square metres. Calculate the quantity of earthwork for the embankment. Use prismoidal method.

Detailed Solution for Test: Estimation & Valuation- 1 - Question 12

Prismoidal formula is given by:

V =  h/3[a+a+ 4[a+ a+…. an-2] +2[a+ a+…. an-1]

Calculation:

h = 40 m

a= 10 m2

a3 = 35 m2

a2 = 15 m2

V = 1400 m3

Test: Estimation & Valuation- 1 - Question 13

When the width is 10 sq.m in plan area and excavation exceeding 1.5 m with depth not exceeding 30 cm, it is termed as?

Detailed Solution for Test: Estimation & Valuation- 1 - Question 13

Surface excavation is required to be done when the width is 10 m2 in plan area and excavation exceed 1.5 m with depth not exceeding 30 cm.

As width is very large compared to depth, so surface excavation is done.

Test: Estimation & Valuation- 1 - Question 14

The slope of the outlet of P-trap below the horizontal is kept.

Detailed Solution for Test: Estimation & Valuation- 1 - Question 14

In most homes, there is a P-trap installed under the sinks in the bathroom and kitchens. A P-trap is a plumbing fixture that has several purposes. It traps debris that has drained from the sink and prevents it from forming a clog deep within the plumbing system and to stops sewer gases from passing in to the home. The slope of the outlet of “P trap” below the horizontal is kept at 14°.

Test: Estimation & Valuation- 1 - Question 15

The above figure represents plan and section of an excavation layout. The volume of earthwork in excavation of foundation trench is

Detailed Solution for Test: Estimation & Valuation- 1 - Question 15

Volume of excavation= perimeter × area

Perimeter = 4 + 4 + 2(6 - 2 × 0.8) = 16.8 m

Area = 0.8 × 0.6 = 0.48 m2; Hence volume = 16.8 × 0.48 = 8.064 m3.

Test: Estimation & Valuation- 1 - Question 16

The following document contains detailed description of all items of work excluding their quantities, along with the current rates:

Detailed Solution for Test: Estimation & Valuation- 1 - Question 16

Tender is an offer to execute some specified work or to supply some specified article at certain rates. While inviting tender the bill of quantities, detailed specifications, conditions of contract and plans and drawings are supplied.

Schedule of rates is a list of rates of various items of works to facilitate the preparation of estimates and to serve as a guide in setting rates in connection with contract agreement. 

Test: Estimation & Valuation- 1 - Question 17

If ‘i' is the rate of interest expressed in decimal and ‘n’ is the number of years, then coefficient of annual sinking find, Ic is

Detailed Solution for Test: Estimation & Valuation- 1 - Question 17

Co-efficient of annual sinking is

Test: Estimation & Valuation- 1 - Question 18

Modular bricks are of nominal size 20 cm × 10 cm × 10 cm and 30% of the volume is lost in mortar between joints. Then what is the required number of modular bricks per cubic meter of brickwork?

Detailed Solution for Test: Estimation & Valuation- 1 - Question 18

Nominal size (Modular brick) = 20 cm × 10 cm × 10 cm

Actual size (Modular brick) = 19 cm × 9 cm × 9 cm

Mortar required for 1 m3 brickwork =

= 0.2305 m3

Volume of Mortar lost b/w joints = 30%

 

Volume (set Mortar) 

Actual volume of brickwork = 1 – 0.29655 = 0.70035 m3

No. of modular bricks

Test: Estimation & Valuation- 1 - Question 19

Which of the following tax generally not applicable to residential building is:

Test: Estimation & Valuation- 1 - Question 20

Plywood is obtained by gluing wooden sheets at a pressure of:

Detailed Solution for Test: Estimation & Valuation- 1 - Question 20

Correct Answer :- a

Explanation : Plywood is obtained by gluing wooden sheets at a pressure of 100 to 150 N/cm^2.

Plywood is formed through the bonding of three or more layers of wood using an adhesive. The layers are very thin and the bonding is done at a temperature of 100 to 130 °C. Each layer has grains on it that are perpendicular to the layer below it. This lessens the extent to which the plywood shrinks and also increases the strength of the final product.

1 videos|1 docs|64 tests
Information about Test: Estimation & Valuation- 1 Page
In this test you can find the Exam questions for Test: Estimation & Valuation- 1 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Estimation & Valuation- 1, EduRev gives you an ample number of Online tests for practice

Top Courses for Civil Engineering (CE)

Download as PDF

Top Courses for Civil Engineering (CE)