The expected time (te) of a PERT activity in term s of optimistic time (to), pessimistic time (tp) and most likely time (tm) is given by
In PERT the span of time between the optimistic and pessimistic time estimates of an activity is
Activity-on-Arrow (AOA) diagram is preferred over Activity-on-Node (AON) diagram because
The variance of the completion time for a project is the sum of variance of