Test: Material Requirement Planning - Mechanical Engineering MCQ


Test Description

10 Questions MCQ Test Topicwise Question Bank for Mechanical Engineering - Test: Material Requirement Planning

Test: Material Requirement Planning for Mechanical Engineering 2024 is part of Topicwise Question Bank for Mechanical Engineering preparation. The Test: Material Requirement Planning questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: Material Requirement Planning MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Material Requirement Planning below.
Solutions of Test: Material Requirement Planning questions in English are available as part of our Topicwise Question Bank for Mechanical Engineering for Mechanical Engineering & Test: Material Requirement Planning solutions in Hindi for Topicwise Question Bank for Mechanical Engineering course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Test: Material Requirement Planning | 10 questions in 30 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study Topicwise Question Bank for Mechanical Engineering for Mechanical Engineering Exam | Download free PDF with solutions
Test: Material Requirement Planning - Question 1

Which of the following input data are needed for MRP?
1. Master production schedule
2. Inventory status
3. Bill of materials
4. Machine capacity

Select the correct answer from above:

Test: Material Requirement Planning - Question 2

In an MRP system, component demand is

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Material Requirement Planning - Question 3

Demand for a given item is said to be dependent if

Test: Material Requirement Planning - Question 4

A master production schedule specifies

Test: Material Requirement Planning - Question 5

A master production schedule specifies

Test: Material Requirement Planning - Question 6

The input to MRP which lists the assemblies, subassemblies, parts and raw materials needed to produce one unit of finished product is known as

Test: Material Requirement Planning - Question 7

One way to facilitate production scheduling and production in firms making a large number of different final products is to use

Test: Material Requirement Planning - Question 8

Which of the following statements best compares modular bills and phantom bills?

Test: Material Requirement Planning - Question 9

If the demand for product A is 50 units, what will be the gross requirement for component E?

Detailed Solution for Test: Material Requirement Planning - Question 9

As per given dependent demand figure, Requirement of B = 50 x 2 = 100 Requirement of C = 50 x 3 = 150 Requirement of D = 150 x 1 = 150 Requirement of E= 150 x 2 = 300

Test: Material Requirement Planning - Question 10

The minimum record accuracy required for successful MRP is approximately

45 videos|314 tests
Information about Test: Material Requirement Planning Page
In this test you can find the Exam questions for Test: Material Requirement Planning solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Material Requirement Planning, EduRev gives you an ample number of Online tests for practice

Top Courses for Mechanical Engineering

Download as PDF

Top Courses for Mechanical Engineering