Material Requirement Planning


10 Questions MCQ Test Manufacturing and Industrial Engineering | Material Requirement Planning


Description
This mock test of Material Requirement Planning for Mechanical Engineering helps you for every Mechanical Engineering entrance exam. This contains 10 Multiple Choice Questions for Mechanical Engineering Material Requirement Planning (mcq) to study with solutions a complete question bank. The solved questions answers in this Material Requirement Planning quiz give you a good mix of easy questions and tough questions. Mechanical Engineering students definitely take this Material Requirement Planning exercise for a better result in the exam. You can find other Material Requirement Planning extra questions, long questions & short questions for Mechanical Engineering on EduRev as well by searching above.
QUESTION: 1

Which of the following input data are needed for MRP?
1. Master production schedule
2. Inventory status
3. Bill of materials
4. Machine capacity

Select the correct answer from above:

Solution:
QUESTION: 2

In an MRP system, component demand is

Solution:
QUESTION: 3

Demand for a given item is said to be dependent if

Solution:
QUESTION: 4

A master production schedule specifies

Solution:
QUESTION: 5

A master production schedule specifies

Solution:
QUESTION: 6

The input to MRP which lists the assemblies, subassemblies, parts and raw materials needed to produce one unit of finished product is known as

Solution:
QUESTION: 7

One way to facilitate production scheduling and production in firms making a large number of different final products is to use

Solution:
QUESTION: 8

Which of the following statements best compares modular bills and phantom bills?

Solution:
QUESTION: 9

If the demand for product A is 50 units, what will be the gross requirement for component E?

Solution:

As per given dependent demand figure, Requirement of B = 50 x 2 = 100 Requirement of C = 50 x 3 = 150 Requirement of D = 150 x 1 = 150 Requirement of E= 150 x 2 = 300

QUESTION: 10

The minimum record accuracy required for successful MRP is approximately

Solution: