Arun Sharma Test: Pie Chart- 2 for UPSC 2024 is part of CSAT Preparation preparation. The Arun Sharma Test: Pie Chart- 2 questions and answers have been prepared according to the UPSC exam syllabus.The Arun Sharma Test: Pie Chart- 2 MCQs are made for UPSC 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Arun Sharma Test: Pie Chart- 2 below.
Solutions of Arun Sharma Test: Pie Chart- 2 questions in English are available as part of our CSAT Preparation for UPSC & Arun Sharma Test: Pie Chart- 2 solutions in Hindi for CSAT Preparation course. Download more important topics, notes, lectures and mock test series for UPSC Exam by signing up for free. Attempt Arun Sharma Test: Pie Chart- 2 | 5 questions in 10 minutes | Mock test for UPSC preparation | Free important questions MCQ to study CSAT Preparation for UPSC Exam | Download free PDF with solutions
Arun Sharma Test: Pie Chart- 2 - Question 1

Practice Quiz or MCQ (Multiple Choice Questions) with solutions are available for Practice, which would help you prepare for "Pie Chart" under LR and DI. You can practice these practice quizzes as per your speed and improvise the topic. The same topic is covered under various competitive examinations like - CAT, GMAT, Bank PO, SSC and other competitive examinations.

The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answers the question that follow.

Q. Near about 20% of the funds are to be arranged through:

Detailed Solution for Arun Sharma Test: Pie Chart- 2 - Question 1

 

20% of the total funds to be arranged= Rs. (20% of 57600) crores
= Rs. 11520 crores
~= Rs. 11486 crores.

Rs. 11486 crores is the amount of funds to be arranged through External Assistance.

Arun Sharma Test: Pie Chart- 2 - Question 2

The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answers the question that follow.

If NHAI could receive a total of Rs. 9695 crores as External Assistance, by what percent (approximately) should it increase the Market Borrowing to arrange for the shortage of funds?

Detailed Solution for Arun Sharma Test: Pie Chart- 2 - Question 2

1 Crore+ students have signed up on EduRev. Have you? Download the App
Arun Sharma Test: Pie Chart- 2 - Question 3

The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answers the question that follow.

If the toll is to be collected through an outsourced agency by allowing a maximum 10% commission, how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4910 crores?

Detailed Solution for Arun Sharma Test: Pie Chart- 2 - Question 3

Arun Sharma Test: Pie Chart- 2 - Question 4

The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answers the question that follow.

The central angle corresponding to Market Borrowing is

Detailed Solution for Arun Sharma Test: Pie Chart- 2 - Question 4

Arun Sharma Test: Pie Chart- 2 - Question 5

The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answers the question that follow.

The approximate ratio of the funds to be arranged through Toll and that through Market Borrowing is

Detailed Solution for Arun Sharma Test: Pie Chart- 2 - Question 5

218 videos|139 docs|151 tests
Information about Arun Sharma Test: Pie Chart- 2 Page
In this test you can find the Exam questions for Arun Sharma Test: Pie Chart- 2 solved & explained in the simplest way possible. Besides giving Questions and answers for Arun Sharma Test: Pie Chart- 2, EduRev gives you an ample number of Online tests for practice

Top Courses for UPSC

218 videos|139 docs|151 tests
Download as PDF

Top Courses for UPSC