Test: Time And Work- 1


10 Questions MCQ Test IBPS PO Mains - Study Material, Online Tests, Previous Year | Test: Time And Work- 1


Description
This mock test of Test: Time And Work- 1 for Quant helps you for every Quant entrance exam. This contains 10 Multiple Choice Questions for Quant Test: Time And Work- 1 (mcq) to study with solutions a complete question bank. The solved questions answers in this Test: Time And Work- 1 quiz give you a good mix of easy questions and tough questions. Quant students definitely take this Test: Time And Work- 1 exercise for a better result in the exam. You can find other Test: Time And Work- 1 extra questions, long questions & short questions for Quant on EduRev as well by searching above.
QUESTION: 1

P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in

Solution:
Work done by P and Q in 1 day = 1/10
Work done by R in 1 day = 1/50
Work done by P, Q and R in 1 day = 1/10 + 1/50 = 6/50
But Work done by P in 1 day = Work done by Q and R in 1 day . Hence the above equation can be written as
Work done by P in 1 day * 2 = 6/50
=> Work done by P in 1 day = 3/50
=> Work done by Q and R in 1 day = 3/50
Hence work done by Q in 1 day = 3/50 – 1/50 = 2/50 = 1/25
So Q alone can do the work in 25 days
QUESTION: 2

P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they completes the job in 4 days. How much days does it take for R alone to complete the work?

Solution:

Amount of work P can do in 1 day = 1/16

Amount of work Q can do in 1 day = 1/12 

Amount of work P, Q and R can together do in 1 day = 1/4

Amount of work R can do in 1 day = 1/4 - (1/16 + 1/12) = 3/16 – 1/12 = 5/48

=> Hence R can do the job on 48/5 days = 9 (3/5) days

QUESTION: 3

Machine P can print one lakh books in 8 hours. Machine Q can print the same number of books in 10 hours while machine R can print the same in 12 hours. All the machines started printing at 9 A.M. Machine P is stopped at 11 A.M. and the remaining two machines complete work. Approximately at what time will the printing of one lakh books be completed?

Solution:
QUESTION: 4

A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

Solution:

QUESTION: 5
6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.
Solution:
Let work done by 1 man in 1 day = m and work done by 1 woman in 1 day = b 
Work done by 6 men and 8 women in 1 day = 1/10 
=> 6m + 8b = 1/10
=> 60m + 80b = 1    (1)
Work done by 26 men and 48 women in 1 day = 1/2 
=> 26m + 48b =1/2
=> 52m + 96b = 1    (2)
Solving equation 1 and equation 2. We get m = 1/100 and b = 1/200
Work done by 15 men and 20 women in 1 day 
= 15/100 + 20/200 =1/4
=> Time taken by 15 men and 20 women in doing the work = 4 days
QUESTION: 6

P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?

Solution:

Work done by P in 1 day = 1/18
Work done by Q in 1 day = 1/15
Work done by Q in 10 days = 10/15 = 2/3
Remaining work = 1 – 2/3 = 1/3
Number of days in which P can finish the remaining work = (1/3) / (1/18) = 6

QUESTION: 7

A can do a particular work in 6 days . B can do the same work in 8 days. A and B signed to do it for Rs. 3200. They completed the work in 3 days with the help of C. How much is to be paid to C?

Solution:

QUESTION: 8
P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the work and he is assisted by Q and R on every third day?
Solution:
Amount of work P can do in 1 day = 1/20
Amount of work Q can do in 1 day = 1/30
Amount of work R can do in 1 day = 1/60
P is working alone and every third day Q and R is helping him
Work completed in every three days = 2 * (1/20) + (1/20 + 1/30 + 1/60) = 1/5
So work completed in 15 days = 5 * 1/5 = 1
Ie, the work will be done in 15 days
QUESTION: 9

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

Solution:
We have,
B = 3/2*A
→ 
A = 2/3*B
One day's work, (A+B) = 1/18
(2/3*B+B) = 1/18
5/3*B = 1/18
One day's work of B = 3/90
B alone can complete the work in,
= 90/3
= 30 days.
QUESTION: 10

P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?

Solution:

Amount of work P can do in 1 day = 1/15

 

Amount of work Q can do in 1 day = 1/20

 

Amount of work P and Q can do in 1 day = 1/15 + 1/20 = 7/60

 

Amount of work P and Q can together do in 4 days = 4 x (7/60) = 7/15

 

Fraction of work left = 1 – 7/15= 8/15

Similar Content

Related tests