If P and Q work together, they will complete a job in 7.5 days. However, if P works alone and completes half the job and then Q takes over and completes the remaining half alone, they will be able to complete the job in 20 days. How long will Q alone take to do the job if P is more efficient than Q?
A and B undertake to complete a piece of work for Rupees 1200. A can do it in 8 days, B can do it in 12 days and with the help of C they complete the work in 4 days. Find the share of C?
1 Crore+ students have signed up on EduRev. Have you? Download the App |
Among four persons Anuj, Bhim, Carl and Dinesh. Anuj takes thrice as much time as Bhim to complete a piece of work. Bhim takes thrice as much time as Carl and Carl takes thrice as much time as Dinesh to complete the same work. If all together they take 3 days to complete the work. Find the time taken by Bhim alone to complete the work alone.
A and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after some days and B completed the remaining work in 12 days. Number of days after which A left the job
A factory produces nuts and bolts. A machine in it produces only nuts while another produces only bolts. The machine producing only nuts produces 500 nuts per minute and need to be cleared for 10 minutes after production of 2000 nuts. The machine producing only bolts produces 600 bolts per minute and needs to be cleared for 15 minutes after production of 3000 bolts. Find the minimum time required to produce 6000 pairs of bolts and nuts if both machines are operated simultaneously.
Three professors P, Q, R are evaluating answer script of a subject. P is 40 more efficient than Q, who is 20 more efficient than R. P takes 10 days less than Q to complete the evaluation work. P starts the evaluation work and works for 10 days and then Q takes over. Q evaluates for next 15 days and then stops. In how many days, R can complete the remaining evaluation work?
A piece of work has to be completed in 50 days, a number of men are employed but it is found that only half of the work is done in 30 days, then an additional 20 men were joined to complete the work on time. How many men initially put to work?
P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?
A and B together can do a piece of work in 24 days, which B and C together can do it in 32 days. After A has been working at it for 10 days and B for 14 days, C finishes it in 26 days. In how many days C alone will do the work?
50 men could complete a work in 200 days. They worked together for 150 days, after that due to bad weather the work is stopped for 25 days. How many more workers should be employed so as to complete the work in time?
A and B can do a piece of work in 24 and 30 days respectively. Both started the work and worked for 6 days. Then B leaves the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C alone can do the work
P and Q can do a piece of work in 10 days and 20 days respectively. Both of them start the work but P leaves the work 5 days before its completion. Find the time in which work is completed
Ram and shyam can do a piece of work in 5 and 7 days respectively. They start working alternatively starting from shyam, then in how many days the work is completed
A group of 24 women is supposed to do a work in 40 days. After 20 days 4 more women is employed and the work is completed in 2 days before the scheduled time. How many days it have been delayed if 4 more women were not employed?
P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?
If P can do 1/3 of the work in 5 days and Q can do 1/4 of the work in 6 days, then how much money will Q get if they were paid a total of 390 rupee?
A piece of work has to be completed in 50 days, a number of men are employed but it is found that only half of the work is done in 30 days, then an additional 20 men were joined to complete the work on time. How many men initially put to work?
A does half as much work as B in one third of the time taken by B. If together they take 20 days to finish the work then what will be the share of A if 1000 rupees is given for the whole work?
A does half as much work as B does in one sixth of the time. If together they take 20 days to complete the work, then what is the time taken by A to complete the work independently.
P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?