Civil Engineering (CE) Exam  >  Civil Engineering (CE) Tests  >  GATE Civil Engineering (CE) 2025 Mock Test Series  >  Test: Resource Allocation & CPM Updating - Civil Engineering (CE) MCQ

Test: Resource Allocation & CPM Updating - Civil Engineering (CE) MCQ


Test Description

10 Questions MCQ Test GATE Civil Engineering (CE) 2025 Mock Test Series - Test: Resource Allocation & CPM Updating

Test: Resource Allocation & CPM Updating for Civil Engineering (CE) 2024 is part of GATE Civil Engineering (CE) 2025 Mock Test Series preparation. The Test: Resource Allocation & CPM Updating questions and answers have been prepared according to the Civil Engineering (CE) exam syllabus.The Test: Resource Allocation & CPM Updating MCQs are made for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Resource Allocation & CPM Updating below.
Solutions of Test: Resource Allocation & CPM Updating questions in English are available as part of our GATE Civil Engineering (CE) 2025 Mock Test Series for Civil Engineering (CE) & Test: Resource Allocation & CPM Updating solutions in Hindi for GATE Civil Engineering (CE) 2025 Mock Test Series course. Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free. Attempt Test: Resource Allocation & CPM Updating | 10 questions in 30 minutes | Mock test for Civil Engineering (CE) preparation | Free important questions MCQ to study GATE Civil Engineering (CE) 2025 Mock Test Series for Civil Engineering (CE) Exam | Download free PDF with solutions
Test: Resource Allocation & CPM Updating - Question 1

When a CPM network is to be updated one considers

Test: Resource Allocation & CPM Updating - Question 2

Which one of the following is the base for resource levelling?

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Resource Allocation & CPM Updating - Question 3

The activity duration (days) and resource requirements (units) are shown in the figure below. What is the maximum resource required in a day?

Detailed Solution for Test: Resource Allocation & CPM Updating - Question 3


Test: Resource Allocation & CPM Updating - Question 4

What is the process of incorporating changes and rescheduling or replanning called?

Test: Resource Allocation & CPM Updating - Question 5

Activities A and B can be started independently. Activity C follows activity A, and activity D follows activities B and C. Activity E follows activity B and precedes activity F. The activities D and F merge at the objective event. Which one of the following is the correct network of the project?

Test: Resource Allocation & CPM Updating - Question 6

Which of the following are the possible changes during the updating of the project network?
1. Change in the duration of an activity.
2. Addition or deletion of an activity.
3. Change in the logical relationship.
Select the correct answer using the codes given below:

Test: Resource Allocation & CPM Updating - Question 7

The constraints in case of resource smoothing operation would be

Detailed Solution for Test: Resource Allocation & CPM Updating - Question 7

(i) Resource Smoothing The total project duration is not changed, but some of the activity start times are shifted by their available floats so that a uniform demand for the resources is generated. The resources are considered to be unlimited.
(ii) Resource levelling The activity start time are so rescheduled that the peak demand for a particular resource does not cross the available limit of the resources. Thus the resources are considered to be limited.

Test: Resource Allocation & CPM Updating - Question 8

The resources in a construction project are made up of

Test: Resource Allocation & CPM Updating - Question 9

The following table contains data on four activities, A B, C and D:

The maximum total resource load in any week will be

Detailed Solution for Test: Resource Allocation & CPM Updating - Question 9


Maximum = 3 + 4 + 6 + 7 = 20

Test: Resource Allocation & CPM Updating - Question 10

Updating may result in

31 docs|280 tests
Information about Test: Resource Allocation & CPM Updating Page
In this test you can find the Exam questions for Test: Resource Allocation & CPM Updating solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Resource Allocation & CPM Updating, EduRev gives you an ample number of Online tests for practice

Up next

Download as PDF

Up next