CAT Exam  >  CAT Tests  >  Daily Test for CAT Preparation  >  CAT Previous Year Questions: Time & Work (July 1) - CAT MCQ

CAT Previous Year Questions: Time & Work (July 1) - CAT MCQ


Test Description

10 Questions MCQ Test Daily Test for CAT Preparation - CAT Previous Year Questions: Time & Work (July 1)

CAT Previous Year Questions: Time & Work (July 1) for CAT 2024 is part of Daily Test for CAT Preparation preparation. The CAT Previous Year Questions: Time & Work (July 1) questions and answers have been prepared according to the CAT exam syllabus.The CAT Previous Year Questions: Time & Work (July 1) MCQs are made for CAT 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for CAT Previous Year Questions: Time & Work (July 1) below.
Solutions of CAT Previous Year Questions: Time & Work (July 1) questions in English are available as part of our Daily Test for CAT Preparation for CAT & CAT Previous Year Questions: Time & Work (July 1) solutions in Hindi for Daily Test for CAT Preparation course. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free. Attempt CAT Previous Year Questions: Time & Work (July 1) | 10 questions in 20 minutes | Mock test for CAT preparation | Free important questions MCQ to study Daily Test for CAT Preparation for CAT Exam | Download free PDF with solutions
*Answer can only contain numeric values
CAT Previous Year Questions: Time & Work (July 1) - Question 1

Bob can finish a job in 40 days, if he works alone. Alex is twice as fast as Bob and thrice as fast as Cole in the same job. Suppose Alex and Bob work together on the first day, Bob and Cole work together on the second day, Cole and Alex work together on the third day, and then, they continue the work by repeating this three - day roster, with Alex and Bob working together on the fourth day, and so on. Then, the total number of days Alex would have worked when the job gets finished, is

[2022]


Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 1

Let the efficiency of Bob be 3 units/day. So, Alex's efficiency will be 6 units/day, and Cole's will be 2 units/day.

Since Bob can finish the job in 40 days, the total work will be 40*3 = 120 units.

Since Alex and Bob work on the first day, the total work done = 3 + 6 = 9 units.

Similarly, for days 2 and 3, it will be 5 and 8 units, respectively.

Thus, in the first 3 days, the total work done = 9 + 5 + 8 = 22 units.

The work done in the first 15 days = 22*5 = 110 units.

Thus, the work will be finished on the 17th day(since 9 + 5 = 14 units are greater than the remaining work).

Since Alex works on two days of every 3 days, he will work for 10 days out of the first 15 days.

Then he will also work on the 16th day.

The total number of days = 11.

*Answer can only contain numeric values
CAT Previous Year Questions: Time & Work (July 1) - Question 2

Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is

[2022]


Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 2

Let the time taken by Anu, Tanu and Manu be 5x, 8x and 10x hours.

Total work = LCM(5x, 8x, 10x) = 40x

Anu can complete 8 units in one hour

Tanu can complete 5 units in one hour

Manu can complete 4 units in one hour

It is given, three of them together can complete in 32 hours.

32(8 + 5 + 4) = 40x

X = 68/5

It is given,

Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day, i.e. 36 + 4 = 40 hours

40(8 + 5) + y(4) = 40x

4y = 24

y = 6

Manu alone will complete the remaining work in 6 hours.

1 Crore+ students have signed up on EduRev. Have you? Download the App
CAT Previous Year Questions: Time & Work (July 1) - Question 3

Rahul, Rakshita and Gurmeet, working together, would have taken more than 7 days to finish a job. On the other hand, Rahul and Gurmeet, working together would have taken less than 15 days to finish the job. However, they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job. If Rakshita had worked alone on the job then the number of days she would have taken to finish the job, cannot be

[2023]

Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 3

Let the work done by Rahul, Rakshita, and Gurmeet be a, b, and c units per day, respectively, and the total units of work are W.

Hence, we can say that 7(a + b + c) < W ( Rahul, Rakshita, and Gurmeet, working together, would have taken more than 7 days to finish a job).

Similarly, we can say that 15(a + c) > W ( Rahul and Gurmeet, working together would have taken less than 15 days to finish the job)

Now, comparing these two inequalities, we get: 7(a + b + c) < W < 15(a + c)

It is also known that they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job.
Therefore, the total units of work done is: W = 6(a + b + c) + 3b

Hence, we can say that 7(a + b + c) < 6(a + b + c) + 3b < 15(a + c)

Therefore, (a + b + c) < 3b ⇒ a + c < 2b, and 9b < 9(a + c) => b < a + c

⇒ a + b + c < 3b => 7(a + b + c) < 21b , and 15b < 15(a + c)

Hence, The number of days required for b must be in between 15 and 21 (both exclusive).

Hence, the correct option is D

*Answer can only contain numeric values
CAT Previous Year Questions: Time & Work (July 1) - Question 4

The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number of days Sunil will take to finish the job working alone, is

[2023]


Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 4

“The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression.” This implies that the amount of time taken individually by Amal, Sunil and Kamal to finish a job are in A.P.
“Kamal takes twice as much time as Amal to do the same amount of job.” Since the amount of time taken individually by Amal, Sunil and Kamal to finish a job are in A.P, this simply means that Sunil Should take 1.5 times the time as Amal to do the same amount of job.
So, to do the same amount of job individually, the times taken by Amal, Sunil and Kamal will be in the ratio, 1 : 1.5 : 2 or 2 : 3 : 4
Amal, Sunil and Kamal worked for 4, 9 and 16 days respectively to finish the job.
Sunil does in 3 days what Amal does in 2 days.
Therefore, Sunil does in 6 days what Amal does in 4 days.
Sunil does in 3 days what Kamal does in 4 days.
Therefore, Sunil does in 12 days what Kamal does in 16 days.
So, to finish the entire job on his own, Sunil would require, 6 + 9 + 12 = 27 days.

*Answer can only contain numeric values
CAT Previous Year Questions: Time & Work (July 1) - Question 5

Anil can paint a house in 12 days while Barun can paint it in 16 days. Anil, Barun, and Chandu undertake to paint the house for ₹ 24000 and the three of them together complete the painting in 6 days. If Chandu is paid in proportion to the work done by him, then the amount in INR received by him is   [2021]


Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 5

Now Anil Paints in 12 Days
Barun paints in 16 Days
Now together Arun , Barun and Chandu painted in 6 Days
Now let total work be W
Now each worked for 6 days
So Anil's work = 0.5W
Barun's work = 6W / 16 = 3W/8
Therefore Charu's work =W/2 - 3W/8 = W/8
Therefore proportion of charu = 24000/8 = 3,000

CAT Previous Year Questions: Time & Work (July 1) - Question 6

One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is    [2021]

Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 6

Let Rahul work at a units/hr and Gautam at b units/hour
Now as per the condition :
8a + 6b =7.5a + 7.5b
so we get 0.5a = 1.5b
or a = 3b
Therefore total work = 8a + 6b = 8a + 2a = 10a
Now Rahul alone takes 10a/10 = 10 hours.

CAT Previous Year Questions: Time & Work (July 1) - Question 7

Anil can paint a house in 60 days while Bimal can paint it in 84 days. Anil starts painting and after 10 days, Bimal and Charu join him. Together, they complete the painting in 14 more days. If they are paid a total of ₹ 21000 for the job, then the share of Charu, in INR, proportionate to the work done by him, is   
                                                                                                                                                                                            [2021]

Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 7

Let Entire work be W
Now Anil worked for 24 days ( 10 days alone and 14 days with bimal and charu both )
Bimal worked for 14 days and Charu worked for 14 days .
Now Anil Completes W in 60 days
so in 24 days he completed 0.4W
Bimal completes W in 84 Days
So in 14 Days Bimal completes = W/6
Therefore work done by charu = 
Therefore proportion of Charu = 13/30 x 21000 = 9100

CAT Previous Year Questions: Time & Work (July 1) - Question 8

Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is    [2021]

Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 8

Let the total amount of work be 60 units.
Then Anu, Vinu, and Manu do 4, 5, and 3 units of work per day respectively.
On the 1st day, Anu and Vinu work. Work done on the 1st day = 9 units
On the 2nd day, Manu and Vinu work. Work done on the 2nd day = 8 units
This cycle goes on. And in 6 days, the work completed is 9 + 8 + 9 + 8 + 9 + 8 = 51 units.
On the 7th day, again Anu and Vinu work and complete the remaining 9 units of work. Thus, the number of days taken is 7 days.

*Answer can only contain numeric values
CAT Previous Year Questions: Time & Work (July 1) - Question 9

Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is   
                                                                                                                                                                                             [2021]


Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 9

Let the total work be 48 units. Let Amar do 'm' work, Akbar do 'k' work, and Anthony do 'n' units of work in a month.
Amar and Akbar complete the project in 12 months. Hence, in a month they do 48/12 = 4 units of work.
m + k = 4.
Similarly, k+n = 3, and m+n = 2.
Solving the three equations, we get m = 3/2, k = 5/2, n = 1/2
Here, Amar works neither the fastest not the slowest, and he does 1.5 units of work in a month. Hence, to complete the work, he would take 48/1.5 = 32months.

CAT Previous Year Questions: Time & Work (July 1) - Question 10

At their usual efficiency levels, A and B together finish a task in 12 days. If A had worked half as efficiently as she usually does, and B had worked thrice as efficiently as he usually does, the task would have been completed in 9 days. How many days would A take to finish the task if she works alone at her usual efficiency?

[2019]

Detailed Solution for CAT Previous Year Questions: Time & Work (July 1) - Question 10

Let Total work be 108 days
At normal efficiency work is done in 12 days
Let A' s day work = A & B' s day work = B
      ► A + B = 9 & 
      ► A + B = 9…(1)
      ► A + 6B = 24…(2)
Solving (1) & (2), A = 6 B = 3
At usual efficiency A will do the work in 108 / 6 = 18 days.

152 docs|327 tests
Information about CAT Previous Year Questions: Time & Work (July 1) Page
In this test you can find the Exam questions for CAT Previous Year Questions: Time & Work (July 1) solved & explained in the simplest way possible. Besides giving Questions and answers for CAT Previous Year Questions: Time & Work (July 1), EduRev gives you an ample number of Online tests for practice

Top Courses for CAT

Download as PDF

Top Courses for CAT