A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?
  • a)
    225
  • b)
    250
  • c)
    275
  • d)
    300
  • e)
    350
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
A certain work plan for September requires that a work team, working e...
The work plan requires that the team produce an average of 200 items per day in September. Because the team has only produced an average of 150 items per day in the first half of September, it has a shortfall of 200 - 150 = 50 items per day for the first half of the month. The team must make up for this shortfall in tire second half of the month, which has an equal number of days as the first half of the month. The team must therefore produce in the second half of the month an average amount per day that is 50 items greater than the required average of 200 items per day for the entire month. This amount for the second half of September is 250 items per day.
The correct answer is B.
1 Crore+ students have signed up on EduRev. Have you?
1 Crore+ students have signed up on EduRev. Have you?

Learn this topic in detail

GMAT Mock Test - 1
79 Ques | 158 Mins
Start Test
More from Related Course
Quantitative for GMAT
View notes & videos
View courses related to this question
Explore GMAT courses

Similar GMAT Doubts

Quick links for GMAT exam

850+
Video Lectures
2500+
Revision Notes
600+
Online Tests
10,000+
Doubts Solved
A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer?
Question Description
A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer? for GMAT 2023 is part of GMAT preparation. The Question and answers have been prepared according to the GMAT exam syllabus. Information about A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for GMAT 2023 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer?.
Solutions for A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for GMAT. Download more important topics, notes, lectures and mock test series for GMAT Exam by signing up for free.
Here you can find the meaning of A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer?, a detailed solution for A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A certain work plan for September requires that a work team, working every day, produce an average of 200 items per day. For the first half of the month, the team produced an average of 150 items per day. How many items per day must the team average during the second half of the month ifitis to attain the average daily production rate required by the work plan?a)225b)250c)275d)300e)350Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice GMAT tests.

Download free EduRev App

Track your progress, build streaks, highlight & save important lessons and more!
(Scan QR code)