B Com Exam  >  B Com Questions  >  Which ledger contains the cost of materials, ... Start Learning for Free
Which ledger contains the cost of materials, wages, and overheads for each job undertaken?
  • a)
    Stores Ledger
  • b)
    Work-in-Progress Ledger
  • c)
    Finished Goods Ledger
  • d)
    Cost Ledger
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
Which ledger contains the cost of materials, wages, and overheads for ...
The Work-in-Progress Ledger contains the cost of materials, wages, and overheads for each job undertaken. It helps in tracking the cost of work in progress and specific jobs or processes.
Explore Courses for B Com exam

Similar B Com Doubts

Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer?
Question Description
Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer? for B Com 2024 is part of B Com preparation. The Question and answers have been prepared according to the B Com exam syllabus. Information about Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for B Com 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for B Com. Download more important topics, notes, lectures and mock test series for B Com Exam by signing up for free.
Here you can find the meaning of Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which ledger contains the cost of materials, wages, and overheads for each job undertaken?a)Stores Ledgerb)Work-in-Progress Ledgerc)Finished Goods Ledgerd)Cost LedgerCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice B Com tests.