The cross – section of a strip footing is shown below:
The quantity of 150 thick PCC (1 : 3 : 6) per metre length of footing is
  • a)
    0.0625 sq.m
  • b)
    0.0625 cu.m.
  • c)
    0.094 sq.m
  • d)
    0.094 cu. m/
Correct answer is option 'C'. Can you explain this answer?

Civil Engineering (CE) Question

Tirumal Kandula answered Jun 26, 2018
The correct answer is D. Because we are asked to determine for per metre length so it will be 0.094 cu.m/m.
The quantity is determined as 0.625 x 0.15 = 0.09375 cu.m/m.

This discussion on The cross section of a strip footing is shown below:The quantity of 150 thick PCC (1 : 3 : 6) per metre length of footing isa)0.0625 sq.mb)0.0625 cu.m.c)0.094 sq.md)0.094 cu. m/Correct answer is option 'C'. Can you explain this answer? is done on EduRev Study Group by Civil Engineering (CE) Students. The Questions and Answers of The cross section of a strip footing is shown below:The quantity of 150 thick PCC (1 : 3 : 6) per metre length of footing isa)0.0625 sq.mb)0.0625 cu.m.c)0.094 sq.md)0.094 cu. m/Correct answer is option 'C'. Can you explain this answer? are solved by group of students and teacher of Civil Engineering (CE), which is also the largest student community of Civil Engineering (CE). If the answer is not available please wait for a while and a community member will probably answer this soon. You can study other questions, MCQs, videos and tests for Civil Engineering (CE) on EduRev and even discuss your questions like The cross section of a strip footing is shown below:The quantity of 150 thick PCC (1 : 3 : 6) per metre length of footing isa)0.0625 sq.mb)0.0625 cu.m.c)0.094 sq.md)0.094 cu. m/Correct answer is option 'C'. Can you explain this answer? over here on EduRev! Apart from being the largest Civil Engineering (CE) community, EduRev has the largest solved Question bank for Civil Engineering (CE).