Time & Work MCQs for UPPSC (UP) Exam

It covers all Important Questions with answers on Time & Work for the UPPSC (UP) exam. The questions are based on important topics. Details about the questions:
  • Topic: Time & Work
  • Type of Questions: MCQs with solutions
  • Number of Questions: 36
  • You can attempt them on EduRev to score high in UPPSC (UP) exam.

P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in
  • a)
    30 days
  • b)
    25 days
  • c)
    20 days
  • d)
    15 days
Correct answer is option 'B'. Can you explain this answer?

Let distance between the two places = d km
Let total time taken by faster horse = t hr
⇒ Total time taken by slower horse = (t + 5) hr,
Therefore,
speed of the faster horse = d/t km/hr
speed of the slower horse = d/(t + 5) km/hr 
The two horses meet each other in 3 hour 20 min i.e. in 3(1/3) hr = 10/3 hr
In this time, total distance travelled by both the horses together is d. 
d/(t+5) * 10/3 + d/t * 10/3 = d
⇒ 10/(3(t+5)) + 10/3t = 1
⇒ 10t + 10(t+5) = 3t(t+5)
⇒ 20t + 50 = 3t+ 15t
⇒ 3t− 5t − 50 = 0
⇒ 3t+ 10t − 15t − 50 = 0
⇒ t(3t + 10) − 5(3t + 10) = 0
⇒ (3t + 10)(t − 5) = 0
t = 5 (ignoring -ve value) 
Thus, Total time taken by slower horse = 5 + 5 = 10 hr
So Option B is correct

Anup can dig a well in 10 days. but particularly in difficult time the work is such that due to fatigue every subsequent day efficiency of a worker falls by 10%.If Anup is given a task of digging one such well in the difficult time, then in how many days will he finish the work?
  • a)
    12th day
  • b)
    15 th day
  • c)
    11th day
  • d)
    Never
Correct answer is option 'D'. Can you explain this answer?

Wizius Careers answered
Correct Answer :- d
Explanation : The total no. of days in which Anoop can dig the well is 10 days.
Anoop's one day efficiency is 10%.
On day one Anoop performs 10% of his work efficiency, then the next day he won't be able to perform because as per the question the efficiency of a worker falls by 10%.
thus, 10%-10% = 0.

P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
  • a)
    8/15
  • b)
    7/15
  • c)
    11/15
  • d)
    2/11
Correct answer is option 'A'. Can you explain this answer?

Since P to R is double the distance of P to Q,
Therefore, it is evident that the time taken from P to R and back would be double the time taken from P to Q and back (i.e. double of 6.5 hours = 13 hours).
Since going from P to R takes 9 hours, coming back from R to P would take 4 hours i.e. 139 = 4
So Option A is correct

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
  • a)
    30 days
  • b)
    35 days
  • c)
    40 days
  • d)
    45 days
Correct answer is option 'A'. Can you explain this answer?

Rajesh Khatri answered
We have,
B = 3/2*A
→ 
A = 2/3*B
One day's work, (A+B) = 1/18
(2/3*B+B) = 1/18
5/3*B = 1/18
One day's work of B = 3/90
B alone can complete the work in,
= 90/3
= 30 days.

A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn, i.e., first day A does it alone, second day B does it alone and 3rd day C does it alone. After that the cycle is repeated till the work is finished. They get Rs 240 for this job. If the wages are divided in proportion to the work each had done. Find the amount A will get?
  • a)
    14
  • b)
    24
  • c)
    34
  • d)
    36
Correct answer is 'B'. Can you explain this answer?

Ishani Rane answered
Work done by A in 1 day = 1/90
Work done by B in 1 day = 1/40
Work done by C in 1 day = 1/12
Work done in 3 days = 1/90 + 1/40 + 1/12 = 43/360
in 8 * 3 = 24 days , work completed = 8 * 43/360 = 344/360
Remaining work = 1 - 344/360 = 16/360
in 25th day, A works and completes 1/90 work .
Remaining work = 16/360 - 1/90 = 12/360
in 26th day, B works and completes 1/40 work .
Remaining work = 12/360 - 1/40 = 1/120
in 27th day, C works and completes this entire 1/120 work
A worked 9 days by doing 1/90 work each day. Total work done by A = 9 * 1/90 = 1/10
B worked 9 days by doing 1/40 work each day. Total work done by B = 9 * 1/40 = 9/40
C worked 9 days by doing 1/12 work in the initial 8 days and 1/120 work in the 9th day.
Total work done by C = 8 * 1/12 + 1/120 = 81/120
Work done by A : Work done by B : Work done by C
= 1/10 : 9/40 : 81/120 
= 12 : 27 : 81
Total amount that they get = 240
Amount that A get = 240 * 12/(12+27+81) = Rs.24

P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
  • a)
    8
  • b)
    5
  • c)
    4
  • d)
    6
Correct answer is option 'D'. Can you explain this answer?

Initial distance = 25 dog leaps
Per-minute dog makes 5 dog leaps and cat makes 6 cat leaps = 3 dog leaps
⇒  Relative speed = 2 dog leaps / minutes
⇒  An initial distance of 25 dog leaps would get covered in 12.5 minutes.
So Option D is correct

In what time would a cistern be filled by three pipes of diameter of 1 cm, 2 cm and 3 cm if the largest pipe alone can fill the cistern in 49 minutes, the amount of water flowing through each pipe being proportional to the square of its diameter?
  • a)
    31.5 minutes
  • b)
    63 minutes
  • c)
    126 minutes
  • d)
    None of these
Correct answer is option 'A'. Can you explain this answer?

Naroj Boda answered
Since the amount of water flowing through each pipe is proportional to square of its diameter so if efficiency of longest pipe (3 cm) = 1/49
Then efficiency of pipe (2 cm) = 4/(49 x 9)
and efficiency of pipe (1 cm) = 1/ (49 x 9) 
Now let cistern is filled by all three pipes in x minutes.

Chetan is thrice as efficient as Mamta and together they can finish a piece of work in 60 days. Mamta will take how many days to finish this work alone?
  • a)
    80
  • b)
    160
  • c)
    240
  • d)
    320
Correct answer is option 'C'. Can you explain this answer?

  • Chetan is thrice as efficient as Mamta.
  • Let, Mamta takes 3x days and Chetan takes x days to complete the work.
  • ∴ 1/x + 1/3x = 1/60 ⇒ x = 80.
  • ∴ Mamta will take 80 × 3 = 240 days to complete the work.

6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.
  • a)
    4 days
  • b)
    6 days
  • c)
    2 days
  • d)
    8 days
Correct answer is option 'A'. Can you explain this answer?

Let work done by 1 man in 1 day = m and work done by 1 woman in 1 day = b 
Work done by 6 men and 8 women in 1 day = 1/10 
=> 6m + 8b = 1/10
=> 60m + 80b = 1    (1)
Work done by 26 men and 48 women in 1 day = 1/2 
=> 26m + 48b =1/2
=> 52m + 96b = 1    (2)
Solving equation 1 and equation 2. We get m = 1/100 and b = 1/200
Work done by 15 men and 20 women in 1 day 
= 15/100 + 20/200 =1/4
=> Time taken by 15 men and 20 women in doing the work = 4 days

Mayank can do 50% more work than Shishu in the same time. Shishu alone can do a piece of work in 30 hours. Shishu starts working and he had already worked for 12 hours when Mayank joins him. How many hours should Shishu and Mayank work together to complete the remaining work?
  • a)
    6
  • b)
    12
  • c)
    4.8
  • d)
    7.2
Correct answer is option 'D'. Can you explain this answer?

Ishani Rane answered
Shishu alone does the work in 30 hours 

So in 1 hour he does 1/30 of the work 

Mayank in 1 hour does 1/30 + 1/2*1/30= 1/30 +1/60 = 3/60 = 1/20 of the work 

Together in 1 hour they do 1/30 +1/20 = 5/60 = 1/12 of the work 

Together they can finish the work in 12 hours 

Shishu in 12 hours does 12/ 30 = 2/5 

Remaining work = 3/5 

3/5 X 12 = 36/5 = 7.2 hours

Read the passage below and solve the questions based on it.
The tank at a water supply station is filled with water by several pumps. At first three pumps of Ihe same capacity are turned on: 2.5 hours later, two more pumps (both the same) of a different capacity are set into operation. After 1 hour, the additional pumps were set into operation; the tank was almost filled to its capacity (15 m3 were still lacking): in another hour the tank was full. One of the two additional pumps could have filled the tank in 40 hours
Q. What is the volume of the tank?
  • a)
    60 m3
  • b)
    80 m3
  • c)
    75 m3
  • d)
    90 m3
Correct answer is option 'A'. Can you explain this answer?

Bhavya Saha answered
Let us assume that, first three pumps fills the tank in x hours .
so,
→ Efficiency of each pump = (1/x) m³ / hour .
then,
→ Efficiency of three pump = (3/x) m³ / hour .
 
now,
→ First three pumps works for = 2.5h + 1h + 1h = 4.5 hours.
 
so,
→ Water filled by 3 pumps in 4.5 hours = 4.5 * (3/x) = (13.5/x) m³ .
 
now, given that,
→ Time taken by additional pump to fill the tank = 40 hours.
so,
→ Efficiency of 2 additional tanks = 2 * (1/40) = (1/20) m³ / h .
 
and,
→ Additional pumps work for = 1 + 1 = 2 hours.
 
so,
→ Water filled by additional pumps in 2 hours = 2 * (1/20) = (1/10) m³ .
 
therefore,
→ (13.5/x) + (1/10) = 1
→ (13.5/x) = 1 - (1/10)
→ (13.5/x) = (9/10)
→ x = 135/9 = 15 hours.
 
since given that, in last 1 hour they filled 15 m³ .
 
hence,
→ 3 * (1/15) + (1/20) = 15 m³
→ (1/5) + (1/20) = 15
→ (4 + 1)/20 = 15
→ (5/20) = 15
→ (1/4) = 15
→ 1 = 60  (Ans.) (Option A)

Refer to the data below and answer the questions that follow.
Anoop was writing the reading comprehension sections in Lhe DOG entrance examinations, There were four passages of exactly equal length in terms of number of words and die four passages had 5, 8, 8 and 6 questions following each of them respectively. It is known that Anoop can answer exactly 12 questions in the time he takes to read any one of the four passages. Assume that his rate of reading and answering questions remains the same throughout the section.
Q.
By what per cent should Anoop increase his reading speed if he has to cut down on his total time spent on the section by 20%? Assume that the time spent on answering the questions is constant and as given in the directions.
  • a)
    36.36%
  • b)
    54.54%
  • c)
    50.50%
  • d)
    45.45%
Correct answer is option 'D'. Can you explain this answer?

Maulik Rane answered
To solve this problem, let's first find out the total time Anoop takes to read all four passages and answer all the questions.

Let the time he takes to read one passage be T. Since there are four passages, he takes 4T time to read all the passages. It is given that he can answer 12 questions in the time he takes to read one passage. So, the time he takes to answer one question is T/12.

There are a total of 5+8+8+6 = 27 questions. The time he takes to answer all the questions is 27 * (T/12) = 27T/12 = 9T/4.

Now, the total time spent on the section is the sum of the time spent on reading all the passages and answering all the questions: 4T + 9T/4 = 25T/4.

To cut down on his total time spent on the section by 20%, the new total time should be 80% of the original time, which is 0.8 * (25T/4) = 5T.

Since the time spent on answering the questions remains constant, the time spent on reading should reduce to 5T - 9T/4 = 11T/4. The new time he takes to read one passage is (11T/4) / 4 = 11T/16.

Now, let's find out the percentage increase in reading speed. The original time to read one passage is T, and the new time is 11T/16. Since speed is inversely proportional to time, the new speed will be 16/11 times the original speed.

The percentage increase in speed is [(16/11 - 1) * 100] = [(5/11) * 100] = 45.45%.

So, Anoop should increase his reading speed by 45.45% to cut down on his total time spent on the section by 20%.

Two pipes can separately fill a tank in 20 hours and 30 hours respectively. Both the pipes are opened to fill the tank but when the tank is 3/4th full, a leak develops in, through which one-fourth of water supplied by both the pipes goes out. What is the total time taken to fill the tank?
  • a)
    18 hours
  • b)
    14 hours
  • c)
    15 hours
  • d)
    13 hours
Correct answer is option 'D'. Can you explain this answer?

Tanvi nair answered
Understanding the problem:
- Pipe 1 can fill the tank in 20 hours.
- Pipe 2 can fill the tank in 30 hours.
- When the tank is 3/4th full, a leak develops and one-fourth of the water supplied by both pipes goes out.

Solution:
1. Let's calculate the filling rate of each pipe:
- Pipe 1 can fill 1/20 of the tank in 1 hour.
- Pipe 2 can fill 1/30 of the tank in 1 hour.
2. When the tank is 3/4th full, the total amount of water in the tank is 3/4 of the tank's capacity.
3. At this point, the leak starts and one-fourth of the water supplied by both pipes goes out. This means only 3/4 of the water supplied by both pipes remains in the tank.
4. Let the total time taken to fill the tank be x hours. In x hours, the combined filling rate of both pipes is 1/x of the tank's capacity.
5. The effective filling rate after the leak starts is (3/4) * (1/20 + 1/30) = (3/4) * (1/20 + 1/30) = (3/4) * (1/12) = 1/16 of the tank's capacity.
6. Equating the effective filling rate to the combined filling rate:
1/x = 1/16
x = 16 hours
Therefore, the total time taken to fill the tank is 16 hours, which corresponds to option 'D'.

Chapter doubts & questions for Time & Work - 6 Months Preparation Course for UPPSC 2026 is part of UPPSC (UP) exam preparation. The chapters have been prepared according to the UPPSC (UP) exam syllabus. The Chapter doubts & questions, notes, tests & MCQs are made for UPPSC (UP) 2026 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests here.

Chapter doubts & questions of Time & Work - 6 Months Preparation Course for UPPSC in English & Hindi are available as part of UPPSC (UP) exam. Download more important topics, notes, lectures and mock test series for UPPSC (UP) Exam by signing up for free.

Top Courses UPPSC (UP)