Engineering Economics 

Cash Flow

Cash flow is the sum of money recorded as receipts or disbursements in a project’s financial records.
A cash flow diagram presents the flow of cash as arrows on a time line scaled to the magnitude of the cash flow, where
expenses are down arrows and receipts are up arrows.
Year-end convention ~ expenses occurring during the year are assumed to occur at the end of the year.

Example (FEIM):

A mechanical device will cost $20,000 when purchased. Maintenance will cost $1000 per year. The device will generate
revenues of $5000 per year for 5 years.
The salvage value is $7000.

 

Engineering Economics---------------------------------------------------------------- Next Slide


Discount Factors and Equivalence

Present Worth (P): present amount at t = 0
Future Worth (F): equivalent future amount at t = n of any present amount at t = 0
Annual Amount (A): uniform amount that repeats at the end of each year for n years
Uniform Gradient Amount (G): uniform gradient amount that repeats at the end of each year, starting at the end of the second year and stopping at the end of year n.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Discount Factors and Equivalence

NOTE: To save time, use the calculated factor table provided in the NCEES FE Handbook.

Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

 

Engineering Economics---------------------------------------------------------------- Next Slide

Discount Factors and Equivalence

Example (FEIM):
How much should be put in an investment with a 10% effective annual rate today to have $10,000 in five years?
Using the formula in the factor conversion table,
P = F(1 + i) –n = ($10,000)(1 + 0.1) –5 = $6209
Or using the factor table for 10%,
P = F(P/F, i%, n) = ($10,000)(0.6209) = $6209

Engineering Economics---------------------------------------------------------------- Next Slide

 

Discount Factors and Equivalence

Example (FEIM):
What factor will convert a gradient cash flow ending at t = 8 to a future value? The effective interest rate is 10%.
The F/G conversion is not given in the factor table. However, there are different ways to get the factor using the factors that are in the table.

For example,
NOTE: The answers arrived at using the formula versus the factor table turn out to be slightly different. On economics problems, one should not worry about getting the exact answer.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Nonannual Compounding

Effective Annual Interest Rate
An interest rate that is compounded more than once in a year is converted from a compound nominal rate to an annual effective rate.

Effective Interest Rate Per Period

Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

Example (FEIM):
A savings and loan offers a 5.25% rate per annum compound daily over
365 days per year. What is the effective annual rate?

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Discount Factors for Continuous Compounding

The formulas for continuous compounding are the same formulas in the factor conversion table with the limit taken as the number of periods, n, goes to infinity.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Comparison of Alternatives

Present Worth

When alternatives do the same job and have the same lifetimes, compare them by converting each to its cash value today. The superior alternative will have the highest present worth.

Example (EIT8):

 

Engineering Economics---------------------------------------------------------------- Next Slide

Comparison of Alternatives

Capitalized Costs

Used for a project with infinite life that has repeating expenses every year.
Compare alternatives by calculating the capitalized costs (i.e., the amount of money needed to pay the start-up cost and to yield enough interest to pay the annual cost without touching the principal).

NOTE: The factor conversion for a project with no end is the limit of the P/A factor as the number of periods, n, goes to infinity.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Comparison of Alternatives

Annual Cost

When alternatives do the same job but have different lives, compare the cost per year of each alternative.
The alternatives are assumed to be replaced at the end of their lives by identical alternatives. The initial costs are assumed to be borrowed at the start and repaid evenly during the life of the alternative.

Engineering Economics---------------------------------------------------------------- Next Slide

Comparison of Alternatives

Cost-Benefit Analysis
Project is considered acceptable if B – C ≥ 0 or B/C ≥ 1.
Example (FEIM):
The initial cost of a proposed project is $40M, the capitalized perpetual
annual cost is $12M, the capitalized benefit is $49M, and the residual
value is $0. Should the project be undertaken?
B = $49M, C = $40M + $12M + $0
B – C = $49M – $52M = –$3M < 0

Engineering Economics---------------------------------------------------------------- Next Slide

 

Comparison of Alternatives

Rate of Return on an Investment (ROI)
The ROI must exceed the minimum attractive rate of return (MARR).
The rate of return is calculated by finding an interest rate that makes the present worth zero. Often this must be done by trial and error.
The project should not be undertaken.

Engineering Economics---------------------------------------------------------------- Next Slide

 

Depreciation

Straight Line Depreciation

The depreciation per year is the cost minus the salvage value divided by the years of life.

Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Depreciation

Accelerated Cost Recovery System (ACRS)
The depreciation per year is the cost times the ACRS factor (see the table in the NCEES Handbook). Salvage value is not considered.

 

Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

Engineering Economics---------------------------------------------------------------- Next Slide

 

Depreciation

Example (FEIM):
An asset is purchased that costs $9000. It has a 10-year life and a salvage value of $200. Find the straight-line depreciation and ACRS depreciation for 3 years.

Straight-line depreciation/year 

ACRS depreciation
First year ($9000)(0.1) = $ 900
Second year ($9000)(0.18) = $1620
Third year ($9000)(0.144) = $1296

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Depreciation

Book Value

The assumed value of the asset after j years. The book value (BVj) is the initial cost minus the sum of the depreciations out to the j th year.

Example (FEIM):
What is the book value of the asset in the previous example after 3 years using straight-line depreciation? Using ACRS depreciation?
Straight-line depreciation
$9000 – (3)($800) = $6360
ACRS depreciation
$9000 – $900 – $1620 – $1296 = $5184

Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Tax Considerations

Expenses and depreciation are deductible, revenues are taxed.

Example (EIT8):

Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

Engineering Economics---------------------------------------------------------------- Next Slide

 

Tax Considerations

Gain or loss on the sale of an asset:
If an asset has been depreciated and then is sold for more than the book value, the difference is taxed.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Bonds

Bond value is the present worth of payments over the life of the bond.
Bond yield is the equivalent interest rate of the bond compared to the bond cost.

Example (EIT8):

Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Break-Even Analysis
 

Calculating when revenue is equal to cost, or when one alternative is equal to another if both depend on some variable.

Example (FEIM):
How many kilometers must a car be driven per year for leasing and buying to cost the same? Use 10% interest and year-end cost.
Leasing: $0.15 per kilometer
Buying: $5000 purchase cost, 3-year life, salvage $1200,
$0.04 per kilometer for gas and oil, $500 per year for insurance
EUAC (leasing) = $0.15x, where x is kilometers driven
EUAC (buying) = $0.04x + $500 + ($5k)(A/P,10%,3) – ($1.2k)(A/F,10%,3)
= $0.04x + $500 + ($5k)(0.4021) – ($1.2k)(0.3021)
= $0.04x + $2148
Setting EUAC (leasing) = EUAC (buying) and solving for x
$0.15x = $0.04x + $2148
x = 19,527 km must be driven to break even

Engineering Economics---------------------------------------------------------------- Next Slide

Inflation

Inflation-Adjusted Interest Rate

Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

Engineering Economics---------------------------------------------------------------- Next Slide

Additional Examples

Example 1 (FEIM):
What is the uninflated present worth of $2000 in 2 years if the average inflation rate is 6% and i is 10%?
d = i + f + if = 0.06 + 0.10 + (0.06)(0.10) = 0.166
P = ($2000)(P/F,16.6%, 2) = ($2000)(1 + d)–n
= ($2000)(1 + 0.166)–2 = $1471

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

Example 2 (FEIM):
It costs $75 per year to maintain a cemetery plot. If the interest rate is 6.0%, how much must be set aside to pay for maintenance on each plot without touching the principal?
(A) $1150
(B) $1200
(C) $1250
(D) $1300
P = ($75)(P/A,6%,∞) = ($75)(1/0.06) = $1250
Therefore, (C) is correct.

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

Example 3 (FEIM):
It costs $1000 for hand tools and $1.50 labor per unit to manufacture a product. Another alternative is to manufacture the product by an automated process that costs $15,000, with a $0.50 per-unit cost. With an annual production rate of 5000 units, how long will it take to reach the break-even point?
(A) 2.0 yr
(B) 2.8 yr
(C) 3.6 yr
(D) never
Cumulative cost (hand tools) = $1000 + $1.50x, where x is the number of units.
Cumulative cost (automated) = $15,000 + $0.50x
Set cumulative costs equal and solve for x.
$1000 + $1.50x = $15,000 + $0.50x

$1x = $14,000
x = 14,000 units
tbreak-even = x/production rate = 14,000/5000 = 2.8 yr
Therefore, (B) is correct.

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

Example 4 (FEIM):
A loan of $10,000 is made today at an interest rate of 15%, and the first payment of $3000 is made 4 years later. The amount that is still due on the loan after the first payment is most nearly
(A) $7000
(B) $8050
(C) $8500
(D) $14,500
loan due = ($10k)(F/P,15%,4) – $3000
= ($10k)(1 + 0.15)4 – $3000
= ($10k)(1.7490) – $3000
= $14,490 ($14,500)
Therefore, (D) is correct.

 

Engineering Economics---------------------------------------------------------------- Next Slide

Additional Examples

Example 5 (FEIM):

A machine is purchased for $1000 and has a useful life of 12 years. At the end of 12 years, the salvage value is $130. By straight-line depreciation, what is the book value of the machine at the end of 8 years?
(A) $290
(B) $330
(C) $420
(D) $580
BV = $1000 – ($1000 – $130)(8/12) = $1000 – $580 = $420
Therefore, (C) is correct.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

Example 6 (FEIM):

The maintenance cost for an investment is $2000 per year for the first 10 years and $1000 per year thereafter. The investment has infinite life.
With a 10% interest rate, the present worth of the annual disbursement is most nearly
(A) $10,000
(B) $16,000
(C) $20,000
(D) $24,000
The costs or benefits for a cash flow that repeat should be broken into different benefits and costs that all start or finish at the time of interest.
Take the $2000 cost that repeats for 10 years and break it into two $1000 costs to have one $1000 cost that goes on infinitely and one $1000 cost that goes on for 10 years.
P = ($1000)(P/A,10%,10) + ($1000)(P/A,10%,∞)
= ($1000)(6.1446) + ($1000)(1/0.10)
= $6144.6 + $10,000 = $16,144.6 ($16,000)
Therefore, (B) is correct.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

Example 7 (FEIM):
With an interest rate of 8% compounded semiannually, the value of a $1000 investment after 5 years is most nearly
(A) $1400
(B) $1470
(C) $1480
(D) $1800
ie = (1 + r/m)m – 1= (1 + 0.08/2)2 – 1 = 0.0816
F = ($1000)(F/P,8.16%,5) = ($1000)(1 + 0.0816)5
= ($1000)(1.480) = $1480
Therefore, (C) is correct.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

Example 8 (FEIM):
The following data applies for example problems 8.1 through 8.3. A company is considering the purchase of either machine A or machine B.
machine A machine B
initial cost $80,000 $100,000
estimated life 20 years 25 years
salvage value $20,000 $25,000
other costs $18,000 per year $15,000 per year for the first 15 years
$20,000 per year for the next 10 years

Example 8.1 (FEIM):
The interest rate is 10%, and all cash flows may be treated as end-of-year cash flows. Assume that equivalent annual cost is the value of the constant annuity equal to the total cost of a project. The equivalent annual cost of machine B is most nearly
(A) $21,000
(B) $21,500
(C) $23,000
(D) $26,500

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

The $15,000 cost for 15 years and the $20,000 cost for the next 10 years can be broken into a $20,000 cost for the full 25 years and a $5000 benefit that is present for the first 15 years.
The present worth of $20k for 25 years is

P($20,25) = ($20k)(P/A,10%,25) = ($20k)(9.0770) = $181.54k
The present worth of $5k for 15 years is
P($5,15) = ($5k)(P/A,10%,15) = ($5k)(7.6061) = 38.03k
Pother costs = $181.54 k + $38.03k = $143.51k
Aother costs = Pother costs(A/P, 10%, 25) = ($143.51k)(0.1102) = $15,815
EUAC = ($100k)(A/P,10%,25) – ($25k)(A/F,10%,25) + $15,815
= ($100k)(0.1102) – ($25k)(0.0102) + $15,815
= $11,020 – $255 + $15,815 = $26,610 ($26,500)
Therefore, (D) is correct.

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

Example 8.2 (FEIM):

If funds equal to the present worth of the cost of purchasing and using machine A over 20 years were invested at 10% per annum, the value of the investment at the end of 20 years would be most nearly:
(A) $548,000
(B) $676,000
(C) $880,000
(D) $1,550,000
P(A) = $80k + ($20k)(P/F,10%,20) – ($18k)(P/A,10%,20)
= $80k + ($20k)(0.1486) – ($18k)(8.5136)
= $80k + $2.972k – $153.245k
= $230,273
F(A,10%,20) = ($230,273)(F/P,10%,20) = ($230,273)(6.7275)
= $1,549,162 ($1,550,000)
Therefore, (D) is correct.

 

Engineering Economics---------------------------------------------------------------- Next Slide

 

Additional Examples

Example 8.3 (FEIM):

How much money would have to be placed in a sinking fund each year to replace machine B at the end of 25 years if the fund yields 10% annual compound interest and if the first cost of the machine is assumed to increase at a 6% annual compound rate? (Assume the salvage value does not change.)
(A) $2030
(B) $2510
(C) $2540
(D) $4110
F = P(F/P,6%,25) – salvage value = ($100,000)(4.2919) – $25,000
= $404,190
A = F(A/F,10%,25) = ($404,190)(0.0102)
= $4123 ($4110)
Therefore, (D) is correct.

The document Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE) is a part of Electronics and Communication Engineering (ECE) category.
All you need of Electronics and Communication Engineering (ECE) at this link: Electronics and Communication Engineering (ECE)

Top Courses for Electronics and Communication Engineering (ECE)

FAQs on Chapter - Engineering Economics PPT, Economics, Semester, Engineering - Electronics and Communication Engineering (ECE)

1. What is engineering economics?
Ans. Engineering economics is a branch of economics that applies economic principles and techniques to analyze engineering projects and make decisions regarding the use of resources. It involves considering factors such as cost, revenue, time, and risk in order to determine the most efficient and profitable course of action for engineering projects.
2. How is engineering economics relevant to the field of Electronics and Communication Engineering (ECE)?
Ans. Engineering economics is highly relevant to the field of Electronics and Communication Engineering (ECE) as it helps engineers make informed decisions regarding the design, development, and implementation of electronic systems and communication networks. By considering economic factors, engineers can determine the feasibility, cost-effectiveness, and profitability of various projects and technologies in the ECE field.
3. What are the key principles of engineering economics?
Ans. The key principles of engineering economics include: 1. Time value of money: This principle recognizes that money has different values at different points in time. It involves analyzing and comparing cash flows at different time periods to determine their present or future worth. 2. Cost analysis: Engineers need to consider the various costs associated with a project, including initial investment, operating costs, maintenance costs, and salvage value. Cost analysis helps in assessing the economic viability of a project. 3. Benefit analysis: In addition to costs, engineers also need to assess the benefits of a project, such as increased revenue, cost savings, or improved efficiency. Benefit analysis helps in determining the economic value and profitability of a project. 4. Risk analysis: Engineering economics involves evaluating and managing risks associated with a project. This includes assessing uncertainties, potential losses, and contingency planning to minimize risks and maximize returns. 5. Decision-making: Engineering economics provides tools and techniques for making rational decisions by considering various alternatives and evaluating their economic implications.
4. How can engineering economics help in project evaluation and selection?
Ans. Engineering economics plays a crucial role in project evaluation and selection by providing a systematic approach to assess the economic feasibility and profitability of different projects or alternatives. It helps in comparing the costs, benefits, risks, and returns associated with each option and selecting the one that maximizes the net present value (NPV), internal rate of return (IRR), or other relevant economic indicators. By considering the time value of money and conducting thorough financial analysis, engineering economics helps engineers make informed decisions and allocate resources effectively.
5. What are some common applications of engineering economics in the field of ECE?
Ans. Some common applications of engineering economics in the field of ECE include: 1. Cost analysis for designing and manufacturing electronic devices or communication systems. 2. Evaluation of different technologies and components to determine the most cost-effective and efficient options. 3. Economic analysis of implementing new communication networks or upgrading existing ones. 4. Assessment of the financial viability of research and development projects in the ECE field. 5. Optimization of production processes and supply chains to minimize costs and maximize profits. By applying engineering economics principles, engineers in the ECE field can make data-driven decisions that consider both technical and economic aspects, leading to improved project outcomes and resource allocation.
Download as PDF
Explore Courses for Electronics and Communication Engineering (ECE) exam

Top Courses for Electronics and Communication Engineering (ECE)

Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

Semester

,

MCQs

,

Engineering - Electronics and Communication Engineering (ECE)

,

study material

,

video lectures

,

Engineering - Electronics and Communication Engineering (ECE)

,

Objective type Questions

,

Engineering - Electronics and Communication Engineering (ECE)

,

Previous Year Questions with Solutions

,

shortcuts and tricks

,

Exam

,

Chapter - Engineering Economics PPT

,

practice quizzes

,

Semester

,

Viva Questions

,

Extra Questions

,

Economics

,

Economics

,

mock tests for examination

,

past year papers

,

Chapter - Engineering Economics PPT

,

Chapter - Engineering Economics PPT

,

ppt

,

Free

,

Sample Paper

,

Summary

,

Important questions

,

Economics

,

Semester

,

pdf

,

Semester Notes

;