Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE) PDF Download

Chapter 2 

 

CROSS DRAINAGE WORKS

A cross drainage work is a structure which is constructed at the crossing of a canal and a natural drain, so as dispose of drainage water without interrupting the continuous canal supplies.

Type of Cross-drainage works The drainage water intercepting the canal can be disposed of in either of the following ways:

(1) By passing the canal over the drainage. this may be accomplished either through (i) an aqueduct,; or through a (ii) syphon- aqueduct.

(2) By passing the canal below the drainage. This may be accomplished either through (i) a super -passage; or through a (ii) canal syphon generally called a syphon.

(3) By passing the drain through the canal, so that the canal water and drainage water are allowed to intermingle with each other, This may be accomplished through (i) a level crossing; or through (ii) inlets and outlets.
All these different types of cross drainage works are described below in details.

1. SYPHON AQUEDUCT
When the HFL of the drain is sufficiently below the bottom of the canal, so that the drainage water flows freely under gravity, the structure is known as an aqueduct. However, if the  HFL of the drain is higher than the canal bed and the  water passes through the aqueduct barrels under syphonic action, the structure is known as Syphon Aqueduct .

 Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

2. SUPER PASSAGE
When the FSL of the canal is sufficiently below the bottom of the drain trough, so that the canal water flows freely under gravity, the  structure is known as a super passage.

 Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

However, in this type of cross-drainage works, the inspection road cannot be provided along the canal and a separate bridge is required for the roadway. For affecting economy, the canal may be flumed, but  the drainage trough is never flumed.

 Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

Level crossing:- In this type of cross -drainage work, the canal water and drain water are allowed to intermingle with each other, A level crossing is generally provided when a large canal and a huge drainage (such as a stream or a river) approach each other practically at the same level. A typical layout of a level crossing is shown figure .
The arrangement is practically the same as is provided on a canal headworks.

 Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

Inlets and outlets:- An inlet is a structure constructed in order to allow the drainage water to enter the canal and get mixed with the canal water and thus to help in augmenting canal supplies. may sometimes be constructed to escape out the additional discharge at a suitable site, a little downstream along the canal.

 Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

An inlet essentially consists of an open cut in a canal bank, suitably protected by pitching, to admit the upland drainage water into the canal.The aqueduct or super passage type of works are generally used when high flood drainage discharge is large and continues for a sufficient time. A level crossing is used when the high flood drainage discharge is large but short lived. Inlets and outlets are used when the high flood drainage discharge is small.

The document Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE) is a part of the Civil Engineering (CE) Course Civil Engineering SSC JE (Technical).
All you need of Civil Engineering (CE) at this link: Civil Engineering (CE)
2 videos|122 docs|55 tests

Top Courses for Civil Engineering (CE)

FAQs on Cross Drainage Work - Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

1. What is a cross drainage work?
Ans. A cross drainage work refers to a structure that is constructed to allow the passage of water from one side of a road, railway line, or canal to the other side, without obstructing the flow.
2. Why are cross drainage works important?
Ans. Cross drainage works are important because they help in maintaining the natural flow of water and preventing flooding or water accumulation on one side of a road, railway line, or canal. They ensure smooth passage of water and prevent any disruptions to transportation systems.
3. What are the different types of cross drainage works?
Ans. The different types of cross drainage works include bridges, culverts, syphons, aqueducts, and underpasses. These structures are designed based on the specific requirements of the location and the volume of water to be carried.
4. What factors are considered in the design of cross drainage works?
Ans. The design of cross drainage works takes into consideration factors such as the water flow rate, the height of the embankment or road, the type of soil, the availability of construction materials, and the expected lifespan of the structure. Engineers also consider environmental factors and the impact on local flora and fauna.
5. How are cross drainage works constructed?
Ans. Cross drainage works are constructed by first conducting a detailed survey and analysis of the site. The design is then prepared, considering various factors. Construction materials are procured, and the foundation is prepared. The superstructure is then constructed using reinforced concrete, steel, or other suitable materials. The structure is tested for stability and durability before being put into operation.
2 videos|122 docs|55 tests
Download as PDF
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

Sample Paper

,

Free

,

shortcuts and tricks

,

pdf

,

Summary

,

Extra Questions

,

Objective type Questions

,

past year papers

,

Important questions

,

Exam

,

study material

,

mock tests for examination

,

Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

,

MCQs

,

Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

,

ppt

,

Semester Notes

,

Cross Drainage Work | Civil Engineering SSC JE (Technical) - Civil Engineering (CE)

,

Previous Year Questions with Solutions

,

video lectures

,

practice quizzes

,

Viva Questions

;