Protection works
Just upstream and downstream of the solid floor of the spillway apron, the river bed is protected by certain methods like block protection, loose stone apron, etc. as may be seen from Figure 17 showing a typical section of spillway of a barrage. These protection works are discussed below:
FIGURE 17. Section through a typical barrage spillway
Upstream block protection
Just beyond the upstream impervious floor, pervious protection comprising of cement concrete blocks of adequate size laid over loose stone shall have to be provided. The cement concrete blocks of size around 1.5m x 1.5m x 0.9m are generally used for barrages in alluvial rivers. The length of the upstream block protection may be kept equal to a length D, that is, the design depth of scour below the floor level (Figure 18).
Figure 13. Upstream Block Protection
Downstream block protection
Pervious block protection is provided just beyond the down stream impervious floor. It comprises of cement concrete blocks of size 1.5m x 1.5m x 0.9m laid with gaps of 75mm width and packed with gravel. The downstream block protection is laid on a graded inverted filter designed to prevent the uplift of fine sand particles upwards due to seepage forces. The filter should roughly conform to the following design criteria.
1. d15 of filter / d15 of foundation ≥ 4 ≥ d15 of filter/d85of foundation
Where d15 and d85 represent grain sizes. dx is the size such that x% of the soil grains are smaller than that particle size. Where x may be 15 or 85 percent.
2. The filter may be provided in two or more layers. The grain size curves of the filter layers and the base material has to be nearly parallel.
The length of the downstream block protection has to be approximately equal to 1.5D, where D is the design depth of cover below the floor level. Where this length is substantial, the block protection with inverted filter may be provided in part of the length and block protection only with loose stone spawls in the remaining length as shown in Figure 19.
Figure 19. Downstream Bolck Protection
Loose stone protection
Beyond the block protection on the upstream and down streams of a barrage located on alluvial foundation, a layer of loose boulders or stones have to be laid, as shown in Figure 20(a). The boulder size should be at least 0.3m and should not weigh less than 40kg. This layer of boulders are expected to fall below at an angle , or launch , when the riverbed down stream starts getting scoured at the commencement of a heavy flood [Figure 20(b)]. The length of river bed that has to be protected with loose stone blocks shall be around 1.5D, where D is the depth of scour below average riverbed.
FIGURE 20. Section through downstream protection : (a) After initial laying ; (b) After scour of downstream nverbed due to passage of flood.
It may be mentioned that the loose stone protection shall have to be laid not only down stream of the barrage floor, but all along the base of guide bunds, flank walls, abutment walls, divide walls, under sluice tunnels, as may be observed from the typical layout of a barrage given in Figure 21.
Figure 21. Typical Layout of a Barrage and Its Appurtenant Structures
Once the basic dimensions are fixed for all the barrage component, they are designed structurally, considering the forces estimated from the hydraulic analysis, The Bureau of Indian Standards code IS: 11130- 1984 “Criteria for structural design of barrages and weirs” specifies the recommendations in this regard, the important ones of which have been discussed below.
As the major portion of the barrage structure including the raft floor, piers, divide walls, under sluice tunnels, etc. is constructed as reinforced concrete structures, accordingly the general principles specified in IS: 456- 2000 “Code of practice for plain and reinforced concrete” shall have to be followed. Since most of the construction is likely to remain underwater, the minimum cover may be kept at 50mm for safety. Some other items, notably sheet piles, gates, gate groves, etc. have to be made of structural steel made, conforming to relevant Bureau of Indian Standards specifications. The important components of a barrage are discussed below with the specific structural requirements.
Cut-off (Sheet-pile)
The upstream and downstream cut-offs of a diversion structure may be steel sheet-piles anchored to the barrage floor by means of R.C.C. caps, or may be built of masonry or reinforced concrete. The sheet pile cut-offs are to be designed as sheet pile retaining walls anchored at the top. They shall be designed to resist the worst combination of forces and movements considering possible scour on the outer side, earth pressure and surcharge due to floor loads on the inner side, differential hydrostatic pressure computed on the basis of the percentage of pressure of seepage below floor etc. In case the effect of cut-offs is taken into account for resistance against forward sliding of the structure, the cut-offs shall also be designed to withstand the passive pressures developed. The R.C.C. pile caps shall be designed to transmit the forces and moments acting on the steel sheet piles to the barrage floor.
Impervious floor (also called solid apron)
Generally there are two types of floors, the first being called the Gravity type and the second as the Raft type. In the former, the uplift pressure is balanced by the self weight of the floor only considering unit length of the floor, where as the latter considers the uplift pressure to be balanced not only by the floor but also the piers and other superimposed dead loads considering a span as a unit. Contemporary designs of barrages have also been of the raft- type, and hence this type of construction is recommended and discussed in this session.
The thickness of the impervious floor shall be adequate to counter balance the uplift pressure at the point under consideration. The thickness of the downstream floor (cistern) shall also have to be checked under hydraulic jump conditions, in which case the net vertical force on the floor is to be found out from the difference of the vertical uplift due to sub-surface flow and the weight of water column at any point from above due to the flowing water.
The design of the raft has to be done using the theory of beams on elastic foundations and the following forces, or their worst combination has to be taken:
Beyond the block protection on the upstream and down streams of a barrage located on alluvial foundation, a layer of loose boulders or stones have to be laid, as shown in Figure 20(a). The boulder size should be at least 0.3m and should not weigh less than 40kg. This layer of boulders are expected to fall below at an angle , or launch , when the riverbed down stream starts getting scoured at the commencement of a heavy flood [Figure 20(b)]. The length of river bed that has to be protected with loose stone blocks shall be around 1.5D, where D is the depth of scour below average riverbed.
Structural design of barrage components
A pier shall have to be designed as a reinforced concrete column and IS:456-2000 may be followed accordingly.
For the design of other components of a barrage project, like Divide walls, Abutments, Flank walls, Return walls, etc., IS: 11130-1984 may be followed.
Construction of concrete barrages
Barrages are nowadays made of reinforced concrete and designed as raft type structures which are light in weight compared to storage dams (designed as gravity-type structures). The design of barrages is done by accepting some calculated risks and hence it is important that the construction of such a structure is done with great care and there is no room for construction failure to occur. In this section, the important steps for a careful construction of barrage is explained and further details may be had from Bureau of Indian Standards Code IS:11150-1993 “Construction of concrete barrages – code of practice”.
Data required for construction activities
For planning and execution of construction activities, a number of data is required, most of which would be available from the design reports. These include:
Construction planning
The construction planning for any structure can be broadly classified under two heads: a) Infrastructure planning, and b) Procurement planning and is applicable to barrage construction also. It also includes the finalization of a programme of works and, intermediate review of the programme vis-à-vis the actual work going on in the field. These points are briefly explained below.
Infrastructure planning
This aspect of planning needs to ensure approach roads, power and water supply, workshop, stores, aggregate processing plant, concrete batching and mixing plants, camps and work sheds. It also requires the establishment of other amenities, such as market, schools, medical facilities, and other social and cultural needs of the field staff and workers. The planning should be carried out to the extent possible before the work starts, so that the uncertainties and delays in execution of work, and precise time estimates for the job planning could be evaluated.
Procurement planning
This requires the storage of various construction related materials, like explosives for blasting rocks, cement for construction, steel sheet piles, structural and reinforcement steel, aggregates, etc. The construction equipment necessary to execute the work have also to be procured along with adequate spare parts and accessories.
Programme of works
This should be prepared at the start of the construction activities and consist mainly of Bar Chart Programme for the project duration showing the quantities and monthly progress required for various major items of the project. Another master network plan based on PERT/CPM planning may have to be worked out for monitoring the project work. Based on these programmes, the planning for finance, manpower, equipment required for various activities in different seasons of work have to be prepared.
Review of programme and resources
This should be carried out from time to time as the construction work progresses and should compare items such as the budgeted programme of work and the actual programme of work reviewed at intervals of three or six months. Also, the actual performance of various machines have to be compared with the estimated performance and recommend necessary corrective measures that should be taken. Availability and procurement of essential materials like cement, reinforcement steel, sheet piles, etc. have to be reviewed as well as that for accessory and spare parts of plant and machinery in use and the availability of skilled and unskilled manpower.
Sequence of construction
This important activity has to be planned perfectly, since mistakes at this stage would be difficult to be rectified later. The major items under the sequence of construction are as follows:
Care and diversion of river
Since a barrage would be covering almost the entire width of the river, and it would take quite a few years to construct the whole structure, it would be necessary to construct only portions of the barrage at each construction season, when the flow in the river is relatively less. There may not possibly be any construction in the flood season. During the construction season, the river has to be diverted from the area enclosed for construction by suitable flow diversion works.
The programme of construction of river diversion work should mainly be determined by the availability of working period, likely time that would be required for construction of coffer dams, associated diversion works and construction capability.
The period available for construction of cofferdams is generally limited and depends upon the post-monsoon pattern of the river course and quantum of discharge and programme of work of various items of permanent nature. Cofferdam construction for the portions nearer to the river banks where velocities may not be high, may be of earthen type cofferdams and when the work advances into the river portion, composite type cofferdams consisting of single sheet piles backed with earthen embankments may be provided. Suitable protection on the river side has to be provided to avoid dislodging of sheet piles due to scour of soil backing. For details about the choice of coffer dam to be adopted, one may refer to the Bureau of Indian Standards Code IS:10084-1982 (part1) “Guidelines for choice of type of diversion works: cofferdams”.
1. What is the purpose of the main diversion structure in a barrage? |
2. What factors are considered in the design of the main diversion structure of a barrage? |
3. How does the main diversion structure of a barrage help in flood control? |
4. What are some common materials used for constructing the main diversion structure of a barrage? |
5. How does the design of the main diversion structure ensure efficient water distribution downstream? |
|
Explore Courses for Civil Engineering (CE) exam
|