CLAT PG Exam  >  CLAT PG Notes  >  Law of Contracts  >  Remedies and Damage under Indian Contract Act, 1872

Remedies and Damage under Indian Contract Act, 1872 | Law of Contracts - CLAT PG PDF Download

Remedies and Damages Under the Indian Contract Act, 1872 

Section 73: Compensation for Loss or Damage Due to Breach of Contract 

  • When a contract is broken, the party affected by the breach is entitled to receive compensation from the party who breached the contract. This compensation is for any loss or damage that naturally arises from the breach in the usual course of events or that both parties were aware of when making the contract as likely to result from the breach.
  • However, compensation is not awarded for any remote or indirect losses or damages that occur due to the breach.

In summary, Section 73 of the Indian Contract Act, 1872 governs the compensation for loss or damage caused by a breach of contract, ensuring that the affected party is fairly compensated for direct and foreseeable losses while excluding remote or indirect losses.

 Remoteness of Damage 

The term  'remoteness of damages'  refers to a legal test used to determine which types of losses resulting from a breach of contract can be compensated through an award of damages. It is distinct from the concept of  measure of damages  or quantification, which deals with the method of assessing the monetary compensation for a specific consequence or loss that has been deemed not too remote.

 Key Principles from Hadley v Baxendale 

  • The rules regarding remoteness of damage in contract law are derived from the Court of Exchequer's judgment in  Hadley v Baxendale  and its subsequent interpretations in later cases.
  • In the case of  Hadley v Baxendale  , the plaintiffs faced a disruption in their mill operations due to a broken crankshaft. The defendant carrier was responsible for delivering the broken crankshaft to the manufacturer but failed to do so within the agreed-upon timeframe, causing a delay in restarting the mill.
  • The plaintiffs sought to recover the profits they would have earned had the mill been operational without delay. However, the court rejected this claim on the grounds that the profits were not a direct consequence of the carrier's delay in delivering the broken shaft to the third party.
  • According to the principles established in  Hadley v Baxendale  , damages awarded to the aggrieved party for a breach of contract should either arise naturally and reasonably from the breach itself, or be reasonably deemed to have arisen within the contemplation of the parties at the time of contract formation.

Question for Remedies and Damage under Indian Contract Act, 1872
Try yourself:
What principle governs the compensation for loss or damage caused by a breach of contract under the Indian Contract Act, 1872?
View Solution

 Rule in Hadley v Baxendale 

  • The rule in Hadley v Baxendale consists of two key parts:
  •  Arising Naturally:  Damages that can be fairly and reasonably considered to arise naturally from the breach, according to the usual course of events.
  •  Contemplation of the Parties:  Damages that both parties could reasonably have contemplated at the time of entering into the contract.

 Damage Arising in the Usual Course of Things 

Under this branch of the rule, compensation can be claimed for any loss or damage that arose in the usual course of things from the breach of contract. If the loss is one which does not arise in the usual course of things but in special loss arising out of special circumstances, then the situation would be covered by the second branch of the rule.

 Usual Course of Things 

The first part of this section operates to affix liability on the person who has committed a breach of those matters as may fairly and reasonably be considered as arising naturally from the breach. Such matters would include the normal circumstances prevailing within the type of transaction in question. It is assumed for the purpose that a reasonable businessman must be taken to understand the ordinary business practices and exigencies of the other's trade or business without the need for any special discussion or communication.

 Delay in Carriage of Goods Meant for Sale 

If the carrier is responsible for delaying the delivery of goods to their destination, they may be held liable for the difference in prices between the agreed delivery date and the actual delivery date. This loss is considered a natural consequence of the breach, as it arises in the usual course of events. In the case of  Wilson v. Lancashire and Yorkshire Railway , the plaintiff, a cap manufacturer, entrusted the defendants with a consignment of cloth meant for cap production. Due to the defendants' delay in delivering the cloth, the plaintiff was unable to fulfill cap orders because the season for cap production had passed. The court ruled that the plaintiff could only claim the difference in value of the cloth between the agreed delivery date and the actual delivery date. However, the plaintiffs were not entitled to compensation for the loss of profits resulting from the inability to prepare or sell the caps.

 Compensation for Mental Anguish 

In the case of Ghaziabad Development Authority v. Union of India, the Ghaziabad Development Authority announced a scheme for the allotment of developed plots through advertisements. However, there was an unreasonable delay by the Authority in completing the scheme for plot development. As a result of this delay, the purchaser was entitled to claim the loss of profit that occurred due to the delay caused by the vendor of the plots.

However, the buyer of the plots could not claim any compensation for mental anguish caused by the delay in contract performance. The Supreme Court (SC) held that mental anguish cannot be considered a basis for damages in ordinary commercial disputes. Damages in such cases are typically limited to actual financial losses incurred as a result of the breach of contract.

 Breach of Promise to Marry

In cases of breach of promise to marry, the injured party may experience feelings of hurt and disappointment, which can lead to claims for exemplary damages. A notable case illustrating this is  Laxminarayan v. Sumitra  . In this case, after the engagement, the prospective husband continued to assure the girl of marriage and engaged in sexual relations with her, resulting in her pregnancy. However, he later reneged on his promise to marry her. The court ruled in favor of the girl, awarding her damages for various factors, including physical pain, emotional distress, loss of marriage prospects, and social stigma. The initial compensation of Rs. 30,000 awarded by the lower court was upheld by the M.P. High Court.

 Loss Arising from Special Circumstances

When a breach of contract leads to losses that do not occur naturally or in the usual course of events, but rather due to special circumstances, the party breaching the contract can be held liable for those losses. However, this is contingent upon the special circumstances being communicated to the breaching party at the time of contract formation. If the breaching party was unaware of the special circumstances that resulted in the specific loss, they cannot be held responsible. The extent of liability depends on the knowledge and acceptance of one party regarding the purpose and intention of the other when entering into the contract. The defendant's liability increases with the degree of knowledge they possess regarding the special circumstances.

Measure of Damages

  •  Introduction  to the measure of damages in contract law is crucial for understanding how compensation is determined when a contract is breached. When a breach occurs, and it is established that the consequences of the breach are proximate and not remote, the next step is to assess the compensation owed to the aggrieved party.
  •  Nature of Damages  : Damages in contract law are compensatory, meaning their purpose is to restore the injured party to the position they would have been in had the contract been fulfilled. This principle is evident in various cases, such as the one involving the State of Kerala v. K. Bhaskaran, where a contractor sought compensation for the loss of 10% profit due to a breach of contract.
  •  Measure of Damages in Specific Scenarios  : In contracts for the sale of goods, the measure of damages is determined by the difference between the contract price and the market price at the time of the breach. This principle applies whether the buyer or the seller breaches the contract. For instance, if the buyer breaches the contract, the seller can claim damages based on the market price on the breach date without needing to resell the goods on that date. Conversely, if the seller breaches the contract, the buyer can claim damages based on the market price on the breach date without needing to repurchase the goods.


The document Remedies and Damage under Indian Contract Act, 1872 | Law of Contracts - CLAT PG is a part of the CLAT PG Course Law of Contracts.
All you need of CLAT PG at this link: CLAT PG
56 docs

Top Courses for CLAT PG

FAQs on Remedies and Damage under Indian Contract Act, 1872 - Law of Contracts - CLAT PG

1. What are the different types of remedies available under the Indian Contract Act, 1872?
Ans. The Indian Contract Act, 1872 provides several remedies for breach of contract, primarily categorized into two types: specific performance and damages. Specific performance mandates the party in breach to fulfill their contractual obligations. Damages can be further divided into three types: 1. Liquidated damages, which are pre-determined amounts specified in the contract for breach. 2. General damages, which are awarded for losses that naturally arise from the breach. 3. Special damages, which are awarded for losses that are not typical but were communicated by the aggrieved party at the time of contract formation.
2. How does the Indian Contract Act, 1872 define 'damages' in relation to a breach of contract?
Ans. Under the Indian Contract Act, 1872, 'damages' are defined as a monetary compensation awarded to the party suffering from the breach of contract. The aim of damages is to restore the injured party to the position they would have been in had the breach not occurred. The Act recognizes that damages must be reasonable and not punitive, ensuring they reflect the actual loss suffered due to the breach.
3. Can a party claim both specific performance and damages for the same breach under the Indian Contract Act, 1872?
Ans. No, a party cannot claim both specific performance and damages for the same breach under the Indian Contract Act, 1872. The principle of election applies here, meaning the aggrieved party must choose one remedy. If they opt for specific performance, they cannot seek damages for the same breach, as the law does not allow dual remedies for a single breach.
4. What is the significance of 'reasonable foreseeability' in awarding damages under the Indian Contract Act, 1872?
Ans. 'Reasonable foreseeability' is a significant principle in determining the extent of damages awarded under the Indian Contract Act, 1872. It stipulates that only those damages which were foreseeable at the time of contract formation can be claimed. This means the breaching party should only be liable for losses that were within their contemplation when the contract was made, ensuring fairness and preventing excessive liability.
5. How does the Indian Contract Act, 1872 address the issue of mitigation of damages?
Ans. The Indian Contract Act, 1872 emphasizes the principle of mitigation of damages, which requires the aggrieved party to take reasonable steps to reduce their losses resulting from the breach. The party cannot claim damages for losses that could have been avoided with reasonable efforts. If it is determined that the aggrieved party failed to mitigate their damages, the amount of damages awarded may be reduced accordingly.
56 docs
Download as PDF
Explore Courses for CLAT PG exam

Top Courses for CLAT PG

Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

study material

,

past year papers

,

1872 | Law of Contracts - CLAT PG

,

Sample Paper

,

Exam

,

Viva Questions

,

Remedies and Damage under Indian Contract Act

,

video lectures

,

shortcuts and tricks

,

practice quizzes

,

Semester Notes

,

MCQs

,

Free

,

Extra Questions

,

mock tests for examination

,

Remedies and Damage under Indian Contract Act

,

Summary

,

Previous Year Questions with Solutions

,

pdf

,

Objective type Questions

,

1872 | Law of Contracts - CLAT PG

,

1872 | Law of Contracts - CLAT PG

,

Important questions

,

Remedies and Damage under Indian Contract Act

,

ppt

;