B Com Exam  >  B Com Notes  >  Cost Accounting  >  Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting

Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com PDF Download

STEPS FOR CALCULATION OF MACHINE HOUR RATE 

The following steps are required to be taken for the calculation of machine hour rate:  

(i) Each machine or group of machine should be treated as a cost centre.  

(ii) The estimated overhead expenses for the period should be determined for each machine or group of machines. 

(iii) Overheads relating to a machine are divided into two parts i.e. fixed or standing charges and variable or machine expenses.  

(iv) Standing charges are estimated for a period for every machine and the amount so estimated is divided by the total number of normal working hours of the machine during that period in order to calculate an hourly rate for fixed charges. For machine expenses, an hourly rate is calculated for each item of expenses separately by dividing the expenses by the normal working hours.  

(v) Total of standing charges and machine expenses rates will give the ordinary machine hour rate.

There are two ways of computing the machine hour rate. According to the first method, only indirect expenses directly or immediately connected with the operation of the machine are taken into account, e.g., power, depreciation, repairs and maintenance, insurance, etc. The rate is calculated by dividing the estimated total of these expenses for a period by the estimated number of operating hours of the machines during the period.

It will be obvious, however, that in addition to the expenses stated above there may still be other manufacturing expenses such as supervision charges, shop cleaning and lighting, consumable stores and shop supplies, shop general labour, rent and rates, etc., incurred for the department as a whole and, hence, not charged to any particular machine or group of machines. In order to see that such expenses are not left out of production costs, one should include a proportionate amount of such expenses, in the expenses of machines, before proceeding to compute the machine hour rate. Some people even prefer to add the wages paid to the machine operator in order to get a comprehensive rate for working a machine for one hour. But it is preferable to include the machine operator’s wages in direct wages.

Generally, all expenses are not allocated to machines; it will be, therefore, necessary to calculate another rate for charging the general departmental expenses to production. This second rate will be calculated on the basis of direct labour hours or wages. In effect, therefore, both the machine hour and the labour hour rates will be applied, though separately.

As regards the superiority of one method over the other, it may be considered that the recovery of the direct machine expenses without the proportion of the departmental expenses is likely to be more accurate than when these are made part thereof, because the general departmental expenses are not connected with the actual operation of the machines except remotely. Therefore, when merged with the direct machine expenses for the purpose of computing the machine hour rate, the resultant rate may not be as accurate or as it would be otherwise. But the second method has the advantage of simplifying the routine and procedure of applying manufacturing overheads in as much as only the machine hour rate has to be applied for charging the general departmental overhead. 

Advantages of Machine Hour Rate 

(1) Where machinery is the main factor in production, it is usually the best method of charging machine operating expenses to production.

(2) The under-absorption of machine overheads would indicate the extent the machines have been idle.

(3) It is particularly advantageous where one operator uses several machines (e.g., automatic screw manufacturing machines) or where several operators are engaged in one machine (e.g., the belt press used in making conveyor belts).

(4) It is a logical method and takes into consideration the time factor completely. 

Disadvantages of Machine Hour Rate 

(1) Additional data concerning the operating time of machines, not otherwise necessary, must be recorded and maintained. 

(2) As general data concerning rates for all the machines in a department may be suitable, the computation of a separate machine hour rate for each machine or group of machines would mean additional work.

(3) It gives inaccurate result if hand labour is equally important. If production is carried on in different departments having different degrees of mechanisation, the best method would be the machine hour rate. The machine may be treated as a small department or cost centre and the total cost for, say, a month may be divided by the effective hours for which the machine is usually used. Suppose the total cost of running a machine, including, expenses on rent, lighting, insurance, supervision, depreciation, power, etc. for a month is Rs.12,600 and the total number of hours is 200 including 20 for maintenance, the machine hour rate is Rs.70 i.e. 12,600/180. If the machine is used on job for 5 hours, the job should be charged with Rs.350 i.e. Rs.70 x 5 as production overheads.

[In small firms however, quite good results are obtained by working out the percentage of factory overheads to direct wages or by dividing the total factory overheads by the total number of direct labour hours (productive labour hour rate); production overheads may then be charged to jobs or products using one of these methods. Office expenses are usually charged as a percentage of works cost].

Illustration 4  

Following information is made available from the costing records of a factory: 

(i)

(i) The original cost of the machine           : Rs.1,00,000  

Estimated life                                             : 10 years  

Residual Value                                          : Rs.5,000  

Factory operates for 48 hours per week  : 52 weeks in a year  

Allow 15% towards machine maintenance down time.  

5% (of productive time assuming unproductive) may be allowed as setting up time.  

(ii) Electricity used by the machine is 10 units per hour at a cost of 50 paise per unit. 

(iii) Repair and maintenance cost is ` 500 per month.  

(iv) Two operators attend the machine during operations alongwith two other machines.  Their total wages including fringe benefits, amounting to Rs.5,000 per month is paid.

(v) Othe overheads attributable to the machine are Rs.10,431 per year. 

Using above data, calculate machine hour rate. 

Solution 

Computation of Machine Hour Rate: 

Particulars   

Per Year 

Rs.

Per Year 

Rs.

Standing Charges   
Wages for Operator (Rs.5,000 × 12)/3 20,000  
Other Overheads 10,431  
Standing charges per hour (30,431/2,015)  15.10 
Machine Exoences   
[(1,00,000 – 5,000)/10]/2015  4.71 
Repair and maintenance (5.00 × 12/2,015)   2.98 
Electricity (10 units @ 50 paise)  5.00
Machine Hour Rate  27.79 


Working Note: 

Calculation of effective machine hours:

Total working hours per year (4 × 52) 2,496 
Less: 15% maintenance time 375
 2,121 
Less: 5% for setting up time 108
Effective time 2,015
  


Illustration 5 

The following information has been collected from the cost records of a small company for the year ended 31st March, 2014: 

Direct Materials2,50,000 
Direct Labour2,00,000 
Direct Expenses20,000 
Works Overheads1,60,000 
Office Expenses94,500 


The total number of direct labour hours were 1,00,000 involving 40,000 machine hours. What should be the price quoted for a job involving 2,000 labour hours @ Rs.3 per hour, 1,000 machine hours and Rs.10,000 in direct materials if the profit desired is 20% on the selling price? 

Solution:  

It should be realised that three methods for apportioning production overheads are possible in the problem. These are: 

(i) Percentage on Direct Wages: 80%, i.e., Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

(ii) Productive Labour Hour Rate: Rs.1.60, i.e. Rs.1,60,000 ÷ 1,00,000 

(iii) Machine Hours Rate: Rs.4.00, i.e. Rs.1,60,000 ÷ 40,000. 

The total work cost comes to Rs.6,30,000; office expenses are Rs.94,500. The percentage of office expenses to works cost is 15%, i.e.,Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

Statement of Cost of Job No............. 

 Percentage on 
 Direct wages
 Rs.

Productive Labour
 Hour rate
 Rs.

Machine
 Hour rate 
 Rs.
Direct Materials 10,00010,00010,000 
Direct Labour 6,000 6,000 6,000
 16,00016,00016,000 
Works Overhead* 4,800  3,200 4,000
Works Cost20,80019,20020,000 
Office Expenses (15% of Works Cost)  3,120 2,880 3,000
 23,92022,08023,000 
Profit (25% on cost, or at 20% on selling price) 5,980 5,5205,750
Price29,90027,60028,750


One should note that by using a different method a different figure is obtained.

Illustration 6 

Calculate the machine hour rate from the following:

 Rs.
Cost of machine18,000 
Cost of installation2,000 
Scrap value after 10 years2,000 
Rates and rent for a quarter for the shop600 
General lighting200 p.m. 
Shop supervisor’s salaryRs.6,000 per quarter 
Insurance premium for a machine120 p.a.
Estimated repair200 p.a. 
Power 2 units per hour @ Rs.150 per 100 units  
Estimated working hours p.a. 2,000  


The machine occupies 1/4th of the total area of the shop. The supervisor is expected to devote 1/6th of his time for supervising the machine. General lighting expenses are to be apportioned on the basis of floor area. 

Solution: 

Computation of Machine Hour Rate 

Machine No.: 

  Per year
Rs.
Per hour
Rs.
Standing Charges:   
Rent and Rates - 1/4th 600  
General lighting as per floor area - (200x12)/4 600  
Supervisor’s Salary (6,000x4)/6 4,000  
Insurance premium   120 
Total yearly standing charges 5,320  
Hourly rate (5,320 ÷ 2,000)   2.66 
Machine Expenses:   
Depreciation Cost18,000   
Installation  2,000  
Total 20,000   
Less: Scrap value2,000  
Amount to be written off18,000  0.90 
Repairs etc. — Rs.200/2,000 hours   0.10 
Power 2 units @ Rs.1.5 per unit   3.00
Machine Hour Rate  6.66


Combined machine hour and direct labour hour rate 

Where the work is done partly by machines and partly by manual labour, a combination of Machine Hour and Direct Labour Hour Method is used for the purpose of absorbing works expenses. Such expenses as are inseparable from the running of the machine, are allocated on the basis of the Machine Hour Rate and the other expenses which are not directly attached to the machines are allocated on the basis of the direct labour hour basis. In fact, because of inconvenience, it may not be possible to cover all the items included in factory overheads while computing machine hour and direct labour hour rates. For example, it is likely that such overhead items as salary of the works manager or the factory clerical staff, stationery, etc. are left out. To cover such items also there will be need to apply the method of the percentage of wages to overhead (remaining items only). Suppose the various rates worked out are the following:  

Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

The total wages (direct) for a month come to  Rs.1,50,000 and the items of overheads   not  covered  while  computing  the  rates  mentioned  above  totalled Rs.22,500 per  month.  For a  job undertaken during  the month,  the  following information is available: 

Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

Total of direct wages Rs.600

The overheads to be applied to the job will be Rs.790 i.e.

Rs. 
Machine A   10 hours @ Rs.35350 
Machine B     5 hours @ Rs.45225 
Workers  
Category 1   25 hours @ Rs.3.0075 
Category 2   20 hours @ Rs.2.5050 
"Remaining" overheads (15% on Rs.600) 90
 790


Rate per unit of production 

This is also known as unit cost method. Under this method, actual or pre-determined overhead rate is calculated by dividing the overheads to be absorbed by number of units produced or expected to be produced. The rate is calculated as under: 

Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

This method is very simple. The main limitation of this method is that it is restricted to those concerns which produce only one item of product or a few sizes, quantities or grades of the same product. 

The document Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com is a part of the B Com Course Cost Accounting.
All you need of B Com at this link: B Com
106 videos|173 docs|18 tests

FAQs on Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting - Cost Accounting - B Com

1. What are the different methods of absorbing production overheads?
Ans. The different methods of absorbing production overheads include: 1. Absorption costing: This method allocates production overheads to individual units of output based on a predetermined overhead absorption rate. The rate is calculated by dividing the total estimated overheads by the estimated level of activity. 2. Direct labor hours rate: This method allocates overheads based on the number of direct labor hours required to produce a unit. The overhead rate is calculated by dividing the estimated overheads by the estimated total direct labor hours. 3. Machine hours rate: This method allocates overheads based on the number of machine hours used in the production process. The overhead rate is calculated by dividing the estimated overheads by the estimated total machine hours. 4. Percentage of direct labor cost: This method allocates overheads based on a percentage of the direct labor cost incurred in the production process. The percentage is calculated by dividing the estimated overheads by the estimated total direct labor cost. 5. Activity-based costing: This method allocates overheads based on the activities that drive the incurrence of overhead costs. It identifies cost drivers and allocates overheads to products or services based on the proportionate use of these cost drivers.
2. What is absorption costing?
Ans. Absorption costing is a method of allocating production overheads to individual units of output. It considers all the costs incurred in the production process, including both variable and fixed production overheads. These costs are allocated to units based on a predetermined overhead absorption rate, which is calculated by dividing the total estimated overheads by the estimated level of activity. Absorption costing is commonly used for external reporting purposes and for valuing inventory. It ensures that all costs, including fixed overheads, are allocated to products or services, providing a more accurate representation of the total cost of production. However, absorption costing may not reflect the actual cost behavior of overheads and can lead to over or under-absorption of overheads, especially if the estimated overheads or level of activity differ from the actual amounts.
3. How is the direct labor hours rate calculated?
Ans. The direct labor hours rate is calculated by dividing the estimated overheads by the estimated total direct labor hours. The formula for calculating the direct labor hours rate is as follows: Direct labor hours rate = Estimated overheads / Estimated total direct labor hours For example, if the estimated overheads for a production process are $10,000 and the estimated total direct labor hours are 2,000 hours, the direct labor hours rate would be $5 per hour ($10,000 / 2,000 hours). This rate is then used to allocate overheads to individual units of output based on the number of direct labor hours required for each unit.
4. What is activity-based costing?
Ans. Activity-based costing (ABC) is a method of allocating overheads based on the activities that drive the incurrence of overhead costs. It identifies cost drivers, which are the factors that cause costs to increase or decrease, and allocates overheads to products or services based on the proportionate use of these cost drivers. ABC recognizes that different products or services consume overhead resources to different extents, and therefore, should be allocated overheads accordingly. It provides a more accurate and detailed understanding of the costs associated with each product or service, enabling better decision-making. Unlike traditional costing methods, ABC takes into account both volume-related and non-volume-related cost drivers, providing a more comprehensive analysis of overhead costs.
5. What are the advantages of using absorption costing?
Ans. Some of the advantages of using absorption costing include: 1. Provides a more accurate representation of the total cost of production: Absorption costing considers all costs, including fixed overheads, ensuring that they are allocated to products or services. This provides a more accurate picture of the total cost of production. 2. Useful for external reporting purposes: Absorption costing is commonly used for external reporting, as it complies with generally accepted accounting principles. It allows businesses to value inventory and determine the cost of goods sold. 3. Helps in pricing decisions: Absorption costing provides a better understanding of the total cost of production, which can help businesses make informed pricing decisions. It ensures that all costs, including overheads, are considered when setting prices. 4. Provides a basis for performance evaluation: Absorption costing enables businesses to evaluate the performance of different products or services based on their total cost of production. It helps in identifying profitable and non-profitable products or services. However, it is important to note that absorption costing may not reflect the actual cost behavior of overheads and can lead to over or under-absorption of overheads. It also requires accurate estimation of overheads and the level of activity, which can be challenging in practice.
106 videos|173 docs|18 tests
Download as PDF
Explore Courses for B Com exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

Viva Questions

,

Exam

,

Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

,

study material

,

Sample Paper

,

practice quizzes

,

Semester Notes

,

Extra Questions

,

Free

,

video lectures

,

Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

,

ppt

,

MCQs

,

shortcuts and tricks

,

pdf

,

Methods of Absorbing Production Overheads (Part - 2) - Cost Accounting | Cost Accounting - B Com

,

Objective type Questions

,

past year papers

,

Summary

,

Previous Year Questions with Solutions

,

mock tests for examination

,

Important questions

;