PE Exam Exam  >  PE Exam Notes  >  Civil Engineering (PE Civil)  >  Practice Problems: Temporary Structures

Practice Problems: Temporary Structures

Question 1

A construction engineer is designing a temporary excavation support system for a 20-foot deep trench in sandy soil. The soil has a unit weight of 115 pcf and an angle of internal friction of 32°. Using Rankine's earth pressure theory, what is the total active lateral earth pressure per linear foot acting on the support system?
(a) 12,400 lb/ft
(b) 15,800 lb/ft
(c) 18,600 lb/ft
(d) 21,200 lb/ft

Question 2

A project manager must design a falsework support system for a concrete bridge deck. The deck area to be supported is 30 ft × 60 ft with a thickness of 18 inches. The concrete unit weight is 150 pcf, and live load during construction is 50 psf. What is the total load that the falsework system must support?
(a) 405,000 lb
(b) 495,000 lb
(c) 585,000 lb
(d) 675,000 lb

Question 3

A scaffolding system uses timber planks (Douglas Fir-Larch, Select Structural grade) as work platforms. Each plank is 2 inches × 10 inches in cross-section and spans 8 feet between supports. The allowable bending stress is 1,500 psi. Assuming a uniform load, what is the maximum allowable uniform load per linear foot the plank can support?
(a) 94 lb/ft
(b) 141 lb/ft
(c) 188 lb/ft
(d) 235 lb/ft

Question 4

A temporary steel sheet pile wall retains soil to a height of 5 meters. The soil has a unit weight of 18 kN/m³ and a coefficient of active earth pressure of 0.33. A uniform surcharge of 15 kPa is applied at the ground surface. What is the maximum lateral earth pressure at the base of the wall?
(a) 24.7 kPa
(b) 29.7 kPa
(c) 34.7 kPa
(d) 39.7 kPa

Question 5

A construction site requires a temporary access ramp for equipment. The ramp consists of steel plates supported by timber beams spaced at 4 feet on center. Each beam is 6 inches × 12 inches (actual dimensions) and spans 16 feet. If the allowable bending stress for the timber is 1,200 psi and the equipment creates a uniform load of 150 lb/ft² on the ramp, what is the maximum bending stress in the beams?
(a) 960 psi
(b) 1,080 psi
(c) 1,200 psi
(d) 1,320 psi

Question 6

A temporary trench box is being used in an excavation. The trench box has an inside width of 8 feet and must support lateral soil pressure from clay soil with a unit weight of 120 pcf. The vertical struts are spaced 6 feet apart vertically. If the apparent lateral pressure at a depth of 15 feet is 65 psf per foot of depth, what is the load on the middle strut at 9 feet depth?
(a) 21,060 lb
(b) 28,080 lb
(c) 31,590 lb
(d) 42,120 lb

Question 7

A shoring system uses hydraulic shores rated at 18,000 lb capacity each. The shores are placed horizontally across a 12-foot wide trench at 5-foot vertical spacing. The lateral earth pressure diagram shows a maximum pressure of 480 psf at the bottom of a 16-foot deep trench. How many shores are required at the location experiencing maximum load (assuming uniform pressure distribution across that level)?
(a) 1 shore
(b) 2 shores
(c) 3 shores
(d) 4 shores

Question 8

A formwork designer is calculating the pressure exerted by fresh concrete on vertical wall forms. The concrete will be placed at a rate of 8 feet per hour, has a unit weight of 150 pcf, and a temperature of 70°F. Using ACI 347 guidelines with the equation P = 150 + 9,000R/T (where R is rate in ft/hr and T is temperature in °F), what is the maximum lateral pressure on the forms?
(a) 1,029 psf
(b) 1,179 psf
(c) 1,329 psf
(d) 1,479 psf

Question 9

A construction engineer designs a soldier pile and lagging wall for an excavation. The soldier piles (W12×53 steel sections) are spaced 8 feet on center. At a depth of 12 feet, the lateral earth pressure is 720 psf. What is the maximum bending moment in each soldier pile between two levels of bracing that are 6 feet apart vertically?
(a) 51,840 lb-ft
(b) 69,120 lb-ft
(c) 77,760 lb-ft
(d) 86,400 lb-ft

Question 10

A temporary tower crane foundation consists of a concrete pad measuring 15 ft × 15 ft × 3 ft thick. The crane exerts a maximum vertical load of 180 kips at the center of the pad. The soil bearing capacity is 4,000 psf. Concrete weighs 150 pcf. What is the maximum bearing pressure on the soil?
(a) 3,200 psf
(b) 3,650 psf
(c) 4,000 psf
(d) 4,350 psf

Question 11

A temporary bridge uses timber stringers (Southern Pine, No. 2 grade) with dimensions 6 inches × 16 inches spanning 20 feet. The allowable bending stress is 1,350 psi and the modulus of elasticity is 1.6 × 10⁶ psi. A concentrated load of 12,000 lb is applied at midspan. What is the maximum deflection at midspan?
(a) 0.42 inches
(b) 0.56 inches
(c) 0.70 inches
(d) 0.84 inches

Question 12

A construction superintendent plans the removal sequence for formwork supporting a 14-inch thick concrete slab. The concrete was placed 5 days ago and has achieved a compressive strength of 2,500 psi. The design strength is 4,000 psi. According to ACI 318, what minimum percentage of design strength must be achieved before removing the forms if the slab is not supporting any construction loads?
(a) 50%
(b) 70%
(c) 85%
(d) 100%

Question 13

A tieback anchor system is designed for a 25-foot deep excavation. Each tieback is inclined at 30° below horizontal and must resist a horizontal force of 45 kips. The unbonded length is 15 feet and the bonded length is 25 feet in soil with an ultimate bond strength of 3,000 psf. If the tieback diameter is 6 inches, what is the factor of safety against pullout?
(a) 1.8
(b) 2.2
(c) 2.6
(d) 3.0

Question 14

A project uses adjustable steel shores (Ellis-type) to support formwork for a beam. Each shore has a maximum safe working load of 10,000 lb. The beam formwork creates a tributary load of 1,200 lb/ft along its 18-foot length. Shores are spaced uniformly along the beam length. What is the minimum number of shores required?
(a) 2 shores
(b) 3 shores
(c) 4 shores
(d) 5 shores

Question 15

A cofferdamn is constructed using double-wall steel sheet piling with a granular fill between the walls. The cofferdam must retain water to a depth of 18 feet on the outside while the inside is dewatered. The water unit weight is 62.4 pcf. What is the total hydrostatic force per linear foot acting on the outer sheet pile wall?
(a) 8,640 lb/ft
(b) 10,108 lb/ft
(c) 11,340 lb/ft
(d) 12,960 lb/ft

Question 16

A temporary access platform is constructed with 3/4-inch thick plywood sheathing supported by joists at 24 inches on center. The plywood has an allowable bending stress of 1,400 psi and section modulus of 0.108 in³/ft width. The platform must support a live load of 100 psf plus the plywood self-weight of 2.2 psf. What is the maximum bending stress in the plywood?
(a) 904 psi
(b) 1,134 psi
(c) 1,267 psi
(d) 1,418 psi

Question 17

A braced excavation uses cross-lot bracing with steel pipe struts (8-inch diameter, 0.5-inch wall thickness, 40-foot length). The strut must resist a compressive load of 85 kips. The steel has a yield strength of 36 ksi and E = 29,000 ksi. Using an effective length factor K = 1.0 for pinned ends, what is the critical buckling load for the strut?
(a) 122 kips
(b) 147 kips
(c) 168 kips
(d) 192 kips

Question 18

A concrete pour for a 24-foot tall wall will be completed in 4 hours at a temperature of 60°F. The concrete unit weight is 150 pcf and the slump is 6 inches. Using the ACI 347 formula for concrete pressure on formwork where the rate of placement R = H/t, and P = 150 + 9,000R/T with a maximum of 2,000 psf or 150h (whichever is less), what is the maximum lateral pressure on the formwork?
(a) 1,050 psf
(b) 2,000 psf
(c) 2,850 psf
(d) 3,600 psf

Question 19

A suspended scaffold platform is 20 feet long and 5 feet wide, constructed with aluminum planks weighing 3 psf. The platform must accommodate two workers (175 lb each), tools and materials (50 psf), and provide a safety factor per OSHA requirements. The suspension cables have a working load limit of 3,000 lb each. How many suspension cables are required if a 5:1 safety factor is applied?
(a) 2 cables
(b) 3 cables
(c) 4 cables
(d) 5 cables

Question 20

An engineer designs a temporary crane mat using timber mats to distribute crane outrigger loads. Each outrigger applies a maximum load of 120 kips over a 24-inch × 24-inch pad. The soil bearing capacity is 2,500 psf. What minimum area of timber mat is required under each outrigger to safely distribute the load?
(a) 32 ft²
(b) 40 ft²
(c) 48 ft²
(d) 56 ft²

The document Practice Problems: Temporary Structures is a part of the PE Exam Course Civil Engineering (PE Civil).
All you need of PE Exam at this link: PE Exam
Explore Courses for PE Exam exam
Get EduRev Notes directly in your Google search
Related Searches
practice quizzes, Objective type Questions, video lectures, Extra Questions, Exam, past year papers, ppt, Important questions, Practice Problems: Temporary Structures, Semester Notes, Viva Questions, Free, shortcuts and tricks, Summary, mock tests for examination, Practice Problems: Temporary Structures, pdf , Previous Year Questions with Solutions, study material, Practice Problems: Temporary Structures, MCQs, Sample Paper;