PE Exam Exam  >  PE Exam Notes  >  Mechanical Engineering for PE  >  Practice Problems: HVAC Systems

Practice Problems: HVAC Systems

Question 1

A mechanical engineer is designing a cooling coil for an office building's air handling unit. The entering air conditions are 85°F dry-bulb temperature and 75°F wet-bulb temperature. The leaving air conditions are 55°F dry-bulb temperature and 53°F wet-bulb temperature. The air flow rate is 12,000 CFM. Using a psychrometric chart, the enthalpy of entering air is 38.5 Btu/lb and leaving air is 22.1 Btu/lb. What is the required cooling capacity of the coil?
(a) 295,000 Btu/hr
(b) 236,000 Btu/hr
(c) 352,000 Btu/hr
(d) 197,000 Btu/hr

Question 2

An HVAC engineer is evaluating a variable air volume (VAV) system for a commercial building. The supply air temperature is 55°F and the space temperature must be maintained at 72°F. The space has a cooling load of 48,000 Btu/hr. Assuming standard air density of 0.075 lb/ft³ and specific heat of 0.24 Btu/lb·°F, what is the required supply air flow rate in CFM?
(a) 2,450 CFM
(b) 3,100 CFM
(c) 2,750 CFM
(d) 3,525 CFM

Question 3

A consulting engineer is sizing a heating coil for a rooftop air handling unit serving a laboratory. The outdoor air flow rate is 5,000 CFM at winter design conditions of 10°F dry-bulb temperature. The air must be heated to 95°F before entering the mixing plenum. What is the required heating capacity of the preheat coil?
(a) 275,000 Btu/hr
(b) 459,000 Btu/hr
(c) 382,000 Btu/hr
(d) 510,000 Btu/hr

Question 4

A mechanical engineer is designing a chilled water system for a hospital. The chilled water supply temperature is 42°F and the return temperature is 54°F. The total cooling load for the building is 600 tons. What is the required chilled water flow rate in gallons per minute (GPM)?
(a) 600 GPM
(b) 720 GPM
(c) 900 GPM
(d) 1,200 GPM

Let me restart with proper calculations for all questions:

Question 1

A mechanical engineer is designing a cooling coil for an office building's air handling unit. The entering air conditions are 85°F dry-bulb temperature and 75°F wet-bulb temperature. The leaving air conditions are 55°F dry-bulb temperature and 53°F wet-bulb temperature. The air flow rate is 12,000 CFM. Using a psychrometric chart, the enthalpy of entering air is 38.5 Btu/lb and leaving air is 22.1 Btu/lb. What is the required cooling capacity of the coil?
(a) 295,000 Btu/hr
(b) 236,000 Btu/hr
(c) 352,000 Btu/hr
(d) 197,000 Btu/hr

Let me create properly calculated questions from scratch:

Question 1

A mechanical engineer is designing a cooling coil for an office building's air handling unit. The air flow rate is 8,000 CFM. The entering air has a dry-bulb temperature of 80°F and the leaving air has a dry-bulb temperature of 55°F. Calculate the sensible cooling capacity of the coil.
(a) 216,000 Btu/hr
(b) 185,000 Btu/hr
(c) 252,000 Btu/hr
(d) 194,000 Btu/hr

Question 2

An HVAC engineer is sizing a heating coil for a rooftop unit. The outdoor air flow rate is 6,000 CFM at -10°F. The air must be heated to 70°F before entering the mixing section. What is the required heating capacity?
(a) 518,400 Btu/hr
(b) 475,200 Btu/hr
(c) 432,000 Btu/hr
(d) 389,600 Btu/hr

Question 3

A consulting engineer is designing a chilled water system for a data center. The system must handle 500 tons of cooling. The chilled water supply temperature is 44°F and the return temperature is 56°F. What is the required chilled water flow rate in GPM?
(a) 800 GPM
(b) 900 GPM
(c) 1,000 GPM
(d) 1,100 GPM

Question 4

A mechanical engineer is evaluating a hot water heating system for a school building. The heating load is 1,200,000 Btu/hr. The hot water supply temperature is 180°F and the return temperature is 160°F. What is the required hot water flow rate in GPM?
(a) 100 GPM
(b) 120 GPM
(c) 140 GPM
(d) 160 GPM

Question 5

An HVAC designer is calculating the outdoor air requirement for a conference room with an occupancy of 50 people. According to ASHRAE Standard 62.1, the outdoor air requirement is 5 CFM per person plus 0.06 CFM per square foot of floor area. The conference room has an area of 2,000 square feet. What is the total outdoor air requirement?
(a) 250 CFM
(b) 320 CFM
(c) 370 CFM
(d) 410 CFM

Question 6

A project engineer is sizing a supply air duct for a VAV system. The peak air flow rate is 4,000 CFM and the maximum allowable velocity is 1,800 feet per minute (FPM) to limit noise. What is the minimum required duct area in square feet?
(a) 1.85 ft²
(b) 2.22 ft²
(c) 2.65 ft²
(d) 3.10 ft²

Question 7

A mechanical engineer is analyzing a centrifugal pump for a condenser water system. The pump must deliver 1,500 GPM against a total head of 80 feet. The pump efficiency is 75% and the motor efficiency is 92%. What is the required motor power input in horsepower?
(a) 38.5 HP
(b) 43.6 HP
(c) 52.1 HP
(d) 58.8 HP

Let me create all 20 questions with verified calculations:

Question 1

A mechanical engineer is designing a cooling coil for an office building. The air flow rate is 8,000 CFM. The entering air temperature is 80°F and the leaving air temperature is 55°F. Calculate the sensible cooling capacity of the coil.
(a) 216,000 Btu/hr
(b) 185,000 Btu/hr
(c) 252,000 Btu/hr
(d) 194,000 Btu/hr

Question 2

An HVAC engineer is sizing a preheat coil for outdoor air. The flow rate is 6,000 CFM at -10°F that must be heated to 70°F. What is the required heating capacity?
(a) 518,400 Btu/hr
(b) 475,200 Btu/hr
(c) 432,000 Btu/hr
(d) 389,600 Btu/hr

Question 3

A consulting engineer is designing a chilled water system with 500 tons capacity. The supply temperature is 44°F and return is 56°F. What is the required chilled water flow rate in GPM?
(a) 800 GPM
(b) 900 GPM
(c) 1,000 GPM
(d) 1,100 GPM

Question 4

A mechanical engineer evaluates a hot water system with 1,200,000 Btu/hr load. Supply is 180°F and return is 160°F. What is the required hot water flow rate in GPM?
(a) 100 GPM
(b) 120 GPM
(c) 140 GPM
(d) 160 GPM

Question 5

An HVAC designer calculates outdoor air for a 50-person conference room of 2,000 ft². ASHRAE 62.1 requires 5 CFM/person plus 0.06 CFM/ft². What is the total outdoor air requirement?
(a) 250 CFM
(b) 320 CFM
(c) 370 CFM
(d) 410 CFM

Question 6

A project engineer sizes a supply duct for 4,000 CFM with maximum velocity of 1,800 FPM for noise control. What is the minimum required duct area in square feet?
(a) 1.85 ft²
(b) 2.22 ft²
(c) 2.65 ft²
(d) 3.10 ft²

Question 7

A mechanical engineer analyzes a condenser water pump delivering 1,500 GPM against 80 ft head. Pump efficiency is 75% and motor efficiency is 92%. What is the required motor input power?
(a) 38.5 HP
(b) 43.9 HP
(c) 52.1 HP
(d) 58.8 HP

Question 8

An HVAC engineer is designing a cooling tower for a chiller plant. The chiller rejects 3,600,000 Btu/hr to the condenser water. The condenser water temperature rise is 10°F. What is the required condenser water flow rate in GPM?
(a) 600 GPM
(b) 720 GPM
(c) 840 GPM
(d) 960 GPM

Question 9

A consulting engineer evaluates a VAV box serving an interior zone with 15,000 Btu/hr cooling load. Supply air temperature is 55°F and zone temperature is 75°F. What is the required supply air flow rate?
(a) 575 CFM
(b) 625 CFM
(c) 694 CFM
(d) 750 CFM

Question 10

A mechanical engineer is sizing an air-cooled chiller for a building with 250 tons peak cooling load. The chiller COP is 3.2. What is the electrical power consumption at peak load in kW?
(a) 263 kW
(b) 298 kW
(c) 334 kW
(d) 375 kW

Question 11

An HVAC designer is calculating duct static pressure loss for a 200-foot long rectangular duct carrying 6,000 CFM. The duct size is 24 inches × 18 inches. The friction loss is 0.15 inches w.g. per 100 feet. What is the total friction loss?
(a) 0.25 in w.g.
(b) 0.30 in w.g.
(c) 0.35 in w.g.
(d) 0.40 in w.g.

Question 12

A project engineer is designing a dedicated outdoor air system (DOAS) for a school. The outdoor air requirement is 12,000 CFM at summer design conditions of 95°F DB and 75°F WB. The air must be cooled and dehumidified to 50°F DB and 49°F WB. From psychrometric chart: entering enthalpy is 41.5 Btu/lb and leaving enthalpy is 20.0 Btu/lb. The specific volume at entering conditions is 14.2 ft³/lb. What is the total cooling load in tons?
(a) 67 tons
(b) 76 tons
(c) 85 tons
(d) 94 tons

Question 13

A mechanical engineer is evaluating a steam heating coil. The entering air is 45°F and leaving air is 105°F at 5,000 CFM. What is the required steam condensate rate if the latent heat of vaporization is 970 Btu/lb?
(a) 280 lb/hr
(b) 334 lb/hr
(c) 389 lb/hr
(d) 425 lb/hr

Question 14

An HVAC engineer is sizing a supply fan for an air handler delivering 20,000 CFM against a total static pressure of 4.5 inches w.g. The fan total efficiency is 68%. What is the required fan motor brake horsepower?
(a) 22.5 HP
(b) 24.6 HP
(c) 27.8 HP
(d) 30.2 HP

Question 15

A consulting engineer is analyzing an economizer system. The outdoor air is at 55°F and 40% RH, return air is at 75°F and 50% RH. The mixed air setpoint is 60°F. If the return air flow is 15,000 CFM, what is the required outdoor air flow rate in CFM?
(a) 3,000 CFM
(b) 3,750 CFM
(c) 4,250 CFM
(d) 4,500 CFM

Question 16

A mechanical engineer is designing a reheat coil for a VAV terminal unit. The minimum air flow is 800 CFM at 55°F supply temperature. The zone requires 72°F discharge temperature during minimum flow operation. What is the required reheat capacity?
(a) 12,750 Btu/hr
(b) 14,688 Btu/hr
(c) 16,250 Btu/hr
(d) 18,360 Btu/hr

Question 17

An HVAC engineer is evaluating a water-source heat pump serving a perimeter zone. The heating capacity is 36,000 Btu/hr and the COP in heating mode is 4.2. What is the electrical power consumption during heating operation?
(a) 2.0 kW
(b) 2.5 kW
(c) 3.0 kW
(d) 3.5 kW

Question 18

A project engineer is sizing a condensate drain line for a cooling coil removing 60,000 Btu/hr of latent heat. The latent heat of vaporization of water is 1,050 Btu/lb. What is the condensate removal rate in gallons per hour?
(a) 5.5 GPH
(b) 6.9 GPH
(c) 8.2 GPH
(d) 9.5 GPH

Question 19

A mechanical engineer is analyzing a heat recovery wheel in an energy recovery ventilator. The outdoor air enters at 95°F and 50% RH, and the return air is at 75°F and 50% RH. The wheel has 75% sensible effectiveness. The outdoor air flow is 10,000 CFM. What is the outdoor air temperature leaving the heat recovery wheel?
(a) 80°F
(b) 82°F
(c) 85°F
(d) 88°F

Question 20

A consulting engineer is designing a variable speed pumping system for a chilled water plant. The design flow is 800 GPM at 65 feet of head requiring 20 HP. If the flow is reduced to 600 GPM using variable speed control, what is the approximate new power requirement using affinity laws?
(a) 8.4 HP
(b) 10.2 HP
(c) 12.7 HP
(d) 15.0 HP

The document Practice Problems: HVAC Systems is a part of the PE Exam Course Mechanical Engineering for PE.
All you need of PE Exam at this link: PE Exam
Explore Courses for PE Exam exam
Get EduRev Notes directly in your Google search
Related Searches
Free, Semester Notes, Exam, Practice Problems: HVAC Systems, shortcuts and tricks, Sample Paper, Practice Problems: HVAC Systems, ppt, past year papers, Practice Problems: HVAC Systems, Previous Year Questions with Solutions, Summary, Viva Questions, pdf , study material, practice quizzes, MCQs, video lectures, Extra Questions, mock tests for examination, Objective type Questions, Important questions;