You can prepare effectively for Civil Engineering (CE) SSC JE Civil Engineering 2026 Mock Test Series with this dedicated MCQ Practice Test (available with solutions) on the important topic of "Test: Irrigation Engineering- 1 ". These 20 questions have been designed by the experts with the latest curriculum of Civil Engineering (CE) 2026, to help you master the concept.
Test Highlights:
Sign up on EduRev for free to attempt this test and track your preparation progress.
Wetted perimeter of a regime channel for discharge of 144 cumec as per Lacey’s theory will be:
Detailed Solution: Question 1
If the electrical conductivity of water is in between 750 to 2250 micro mhos/cm at 25oC, then it is classified as:
Detailed Solution: Question 2
A canal which is aligned at right angles to the contour is called
Detailed Solution: Question 3
The discharge passing over an ogee spillway is given by _______, Where, L is an effective length of spillway crest and H is the total head over the spillway crest including velocity head.
Detailed Solution: Question 4
The sodium carbonate lining in canal consist of at least
Detailed Solution: Question 5
Detailed Solution: Question 6
Critical velocity of flow (Vo) given by Kennedy is
Where, m = critical velocity ratio, D = Depth of water over the bed portion of a channel in meters
Detailed Solution: Question 7
Which of the following are the main causes of water logging:
Detailed Solution: Question 8
A field of 500 hectares is to be irrigated for a particular crop having 100 days base period. The total depth of water required by the crop is 100 cm. Calculate the duty of the water (in hectares per cubic metre).
Detailed Solution: Question 9
For smooth entry, the regulators are aligned at an angle of “x” to the water. The value of “x” is:
Detailed Solution: Question 10
The relation for discharge over a rectangular crest of a sarda fall is
Where, L = Length of crest in meters
B = top width of the crest in meters
H = depth of water in meters
Detailed Solution: Question 11
Detailed Solution: Question 12
Detailed Solution: Question 13
Detailed Solution: Question 14
The structure build at the head of the watercourse so as to connect it with a minor or a distributor channel is known as:
Detailed Solution: Question 16
If D is the depth of scour below original bed, then the width of launching apron is generally taken as:
Detailed Solution: Question 17
Detailed Solution: Question 18
Which one of the following is the purpose of providing the downstream sheet pile in a barrage?
Detailed Solution: Question 19
Which of the following spillway gates cannot be seen from a distance, when lowered?