Civil Engineering (CE) Exam  >  Civil Engineering (CE) Test  >  GATE 2027 Mock Test Series  >  Test: Docks, Harbours & Tunnel Engineering - 1 - Civil Engineering (CE) MCQ

GATE Civil Engineering (CE) 2027 Test: Docks, Harbours & Tunnel - 1 Free


MCQ Practice Test & Solutions: Test: Docks, Harbours & Tunnel Engineering - 1 (10 Questions)

You can prepare effectively for Civil Engineering (CE) GATE Civil Engineering (CE) 2027 Mock Test Series with this dedicated MCQ Practice Test (available with solutions) on the important topic of "Test: Docks, Harbours & Tunnel Engineering - 1". These 10 questions have been designed by the experts with the latest curriculum of Civil Engineering (CE) 2026, to help you master the concept.

Test Highlights:

  • - Format: Multiple Choice Questions (MCQ)
  • - Duration: 30 minutes
  • - Number of Questions: 10

Sign up on EduRev for free to attempt this test and track your preparation progress.

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 1

When a ship floats at its designed water line, the vertical distance from water line to the bottom of the ship is known as

Detailed Solution: Question 1

Beam is the width of the midship section at water line. Free board is equal to difference between depth and draft.

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 2

The maximum harbour depth below lowest low water is generally equal to

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 3

The minimum diameter of turning basin, where ships turn by going ahead and without tug assistance should be 

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 4

In "full face" method of constructing tunnel, the first operation relates to

Detailed Solution: Question 4

Excavation of small sized heading (drift) is done centrally at top or bottom of the face in the drift method.
In heading and benching method the top portion is driven in advance of the bottom portion, in full face method the whole section is excavated once for all, It is suitable for tunnels of small cross- sections area say up to 3 m diameter.

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 5

Which one of the following is considered to be an advantage of the heading and benching method of tunnel construction?

Detailed Solution: Question 5

Heading and benching method is used when the tunnel section is very large and quality of rock is not very satisfactory i.e., the rock is unstable. In self supporting rocks, the top heading advance are round ahead of the bottom heading. In unstable (broken or non self supporting rocks), the bench provides platform for timber Supports to the heading.

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 6

Consider the following statements in regard to Beaufort scale for wind speeds.
1. The Beaufort number ranges from 1 to 12
2. Higher Beaufort number indicates higher speed of wind
3. Beaufort number for calm is smalls and for hurricane is highest

Which of these statements are correct?

Detailed Solution: Question 6

The Beaufort number ranges from 0 to 12. The Beaufort number for calm is 0 with 1.6 km/hr velocity and for hurricane, the Beaufort number is 12 with velocity greater than 120 km/hr.

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 7

At a given port, the fetch is 400 nautical miles, the maximum height of storm wave will be

Detailed Solution: Question 7

It is given by,

where F is in nautical miles and h is in feet.

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 8

In a two lane channel, bottom width of channel is given by

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 9

Minimum width of ship clearance shall be where “B" is beam of the design vessel

Test: Docks, Harbours & Tunnel Engineering - 1 - Question 10

Littoral draft as bed load is proportional to
Where V = Velocity, G = Specific gravity of transported material,