Test: CPM & PERT - 1 - Mechanical Engineering MCQ


Test Description

10 Questions MCQ Test - Test: CPM & PERT - 1

Test: CPM & PERT - 1 for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Test: CPM & PERT - 1 questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: CPM & PERT - 1 MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: CPM & PERT - 1 below.
Solutions of Test: CPM & PERT - 1 questions in English are available as part of our course for Mechanical Engineering & Test: CPM & PERT - 1 solutions in Hindi for Mechanical Engineering course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Test: CPM & PERT - 1 | 10 questions in 30 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study for Mechanical Engineering Exam | Download free PDF with solutions
Test: CPM & PERT - 1 - Question 1

In the network diagram shown below:

The critical path is along

Detailed Solution for Test: CPM & PERT - 1 - Question 1


The critical path is along 1 -2-3-5-6-7-8-9 as it has maximum duration.

Test: CPM & PERT - 1 - Question 2

Refer to the network shown in the figure given below

The probability of completion of the project in 24 days is

Detailed Solution for Test: CPM & PERT - 1 - Question 2

The critical path is 1-2-3-4-6.
Ts - Scheduled time
= 24 days
Te - Expected time = 20 days

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: CPM & PERT - 1 - Question 3

The activities for which total float is equal to zero are known as

Test: CPM & PERT - 1 - Question 4

The time by which as activity can be delayed without affecting the earliest start time of any other activity in a project is called

Test: CPM & PERT - 1 - Question 5

The slack on various events at critical path on a PERT/ CPM chart

Test: CPM & PERT - 1 - Question 6

Which one of the following is assumed for timing the activities in PERT network?

Test: CPM & PERT - 1 - Question 7

The area under β-distribution curve is divided into two equal halves by a vertical oridnate through

Detailed Solution for Test: CPM & PERT - 1 - Question 7

Correct option is C. Expected time

Test: CPM & PERT - 1 - Question 8

Negative slack occurs when

Test: CPM & PERT - 1 - Question 9

Which of the following is not a logical error in network construction?

Test: CPM & PERT - 1 - Question 10

The performance of a specific task in CPM is known as

Information about Test: CPM & PERT - 1 Page
In this test you can find the Exam questions for Test: CPM & PERT - 1 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: CPM & PERT - 1, EduRev gives you an ample number of Online tests for practice

Top Courses for Mechanical Engineering

Download as PDF

Top Courses for Mechanical Engineering