Test: CPM & PERT - 2 - Mechanical Engineering MCQ


Test Description

10 Questions MCQ Test - Test: CPM & PERT - 2

Test: CPM & PERT - 2 for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Test: CPM & PERT - 2 questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: CPM & PERT - 2 MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: CPM & PERT - 2 below.
Solutions of Test: CPM & PERT - 2 questions in English are available as part of our course for Mechanical Engineering & Test: CPM & PERT - 2 solutions in Hindi for Mechanical Engineering course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Test: CPM & PERT - 2 | 10 questions in 30 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study for Mechanical Engineering Exam | Download free PDF with solutions
Test: CPM & PERT - 2 - Question 1

In CPM network critical path denotes the

Test: CPM & PERT - 2 - Question 2

In PERT, the distribution of activity times is assumed to be

Detailed Solution for Test: CPM & PERT - 2 - Question 2

In PERT the activity times follow Beta distribution.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: CPM & PERT - 2 - Question 3

In PERT analysis a critical activity has

Test: CPM & PERT - 2 - Question 4

The expected time (te) of a PERT activity in term s of optimistic time (to), pessimistic time (tp) and most likely time (tm) is given by

Detailed Solution for Test: CPM & PERT - 2 - Question 4

The expected time (te) of PERT activity in terms of optimistic time (to), pessimistic-time (tp) and most likely time (tm ) is given by,

Test: CPM & PERT - 2 - Question 5

The critical path of a network is the path that

Test: CPM & PERT - 2 - Question 6

In PERT the span of time between the optimistic and pessimistic time estimates of an activity is

Test: CPM & PERT - 2 - Question 7

In an activity has zero slack, it implies that

Test: CPM & PERT - 2 - Question 8

Activity-on-Arrow (AOA) diagram is preferred over Activity-on-Node (AON) diagram because

Test: CPM & PERT - 2 - Question 9

The most likely time (m) is ’mode’ of the

Test: CPM & PERT - 2 - Question 10

The variance of the completion time for a project is the sum of variance of

Information about Test: CPM & PERT - 2 Page
In this test you can find the Exam questions for Test: CPM & PERT - 2 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: CPM & PERT - 2, EduRev gives you an ample number of Online tests for practice