The resected position of plane-table station from three known position is unreliable if the station lies
Which of the following methods of plane tabling also known as “graphic triangulation”
1 Crore+ students have signed up on EduRev. Have you? Download the App |
The quick and most accurate method to solve three point problem in resection type of plane tabling is
The ‘fix’ of a plane table with three known points is good if the instrument station lies
Consider the following steps
1. Using Lehmann's rule, an improved position of station point is obtained
2. Procedure is repeated till the triangle of error is reduced to a point
3. Triangle of error is obtained
4. The plane table is levelled over the station point
5. Three resection tines are drawn from three well defined station points
The correct sequence of "Lehman’s Procedure" for solving the three point problem is
Consider the following statements regarding Plane Table surveying
1. It is less accurate than chain surveying
2. It is not necessary to do accurate centering of plane table for small scale surveys
3. Compass rule may be made use of for adjusting the plane table traverse
4. From the instrument station, resectors are drawn to plot the position of objects in the field
Which of these statements is/are correct?
Consider the following statements pertaining to plane table survey
1. Two-point problem is solved by mechanical method.
2. Three-point problem is solved by Bessel’s method
3. In two-point problem, auxiliary station is required
Which of these statements is/are correct?
Which one of the following instruments is used in plane table surveying for the measurement of horizontal and vertical distances directly?
Which of the following is NOT the error due to manipulation and sighting in
plane table survey?
Which one of the following methods estimates best the area of an irregular and curved boundary?