You can prepare effectively for Civil Engineering (CE) GATE Civil Engineering (CE) 2027 Mock Test Series with this dedicated MCQ Practice Test (available with solutions) on the important topic of "Test: Airport Engineering -2". These 10 questions have been designed by the experts with the latest curriculum of Civil Engineering (CE) 2026, to help you master the concept.
Test Highlights:
Sign up on EduRev for free to attempt this test and track your preparation progress.
As the elevation increases, the runway length has to be changed at what rate?
Consider the corrections to be applied to the basic length of the runway
1. Elevation correction
2. Gradient correction
3. Temperature correction
The correct order of applying the corrections to obtain runway length is
Detailed Solution: Question 2
The orientation of runway is decided by which factors?
1. Maximum wind coverage and least cross winds
2. Landing characteristics of aircrafts
3. Scope for future expansion
4. Obstruction-free approaches
Select the correct answer using the codes given below:
AVOR radio transmitter which emits beam in a vertical plane and gives an indication to the pilot whether he is to the left or right of the correct alignment for approach to the runway is known as
Detailed Solution: Question 4
The size of hangar in airport is guided by which of the following?
Wind Rose diagram Type-lI used for the orientation of runway shows
Detailed Solution: Question 6
Match List-l (Component) with List-II (Design feature) and select the correct answer using the codes given below the lists:
List-I
A. Taxiways
B. Control tower
C. Hangar
D. Apron
List-II
1. Large span structures
2. Visibility allround and soundproof
3. Turning radius
4. Waiting capacity for aircraft
Codes:
A B C D
(a) 1 4 3 2
(b) 3 2 1 4
(c) 1 2 3 4
(d) 3 4 1 2
A1 type of international airport is the indicative term for
Detailed Solution: Question 8
For the design of runways, if, the standard atmospheric temperature at sea level is 15°C, then the standard temperature at an altitude of 800 m will be
Detailed Solution: Question 9
Where the aircraft is standing (parking), the facility for loading and unloading operation in front of terminal building is known as