Test: CPM & PERT - 3 for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Test: CPM & PERT - 3 questions and answers have been prepared according to the Civil Engineering (CE) exam syllabus.The Test: CPM & PERT - 3 MCQs are made for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: CPM & PERT - 3 below.
Solutions of Test: CPM & PERT - 3 questions in English are available as part of our course for Civil Engineering (CE) & Test: CPM & PERT - 3 solutions in Hindi for Civil Engineering (CE) course. Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free. Attempt Test: CPM & PERT - 3 | 20 questions in 60 minutes | Mock test for Civil Engineering (CE) preparation | Free important questions MCQ to study for Civil Engineering (CE) Exam | Download free PDF with solutions
Test: CPM & PERT - 3 - Question 1

If the scheduled completion time for a particular project is 18 weeks and its earliest expected time is 20 weeks, then the slack time for the project is

Detailed Solution for Test: CPM & PERT - 3 - Question 1

Slack = 18 - 20 = -2 weeks

Test: CPM & PERT - 3 - Question 2

Slack time in PERT analysis

Detailed Solution for Test: CPM & PERT - 3 - Question 2

When slack is zero for one path and negative for other, then path with minimum slack is more critical.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: CPM & PERT - 3 - Question 3

If the optimistic time, most likely time and pessimistic times for activity A are 8,12 and 16 respectively and for activity B are 10,11 and 18 respectively, then

Detailed Solution for Test: CPM & PERT - 3 - Question 3

te(for A) =
te(for B) =

Test: CPM & PERT - 3 - Question 4

Free float is mainly used to

Detailed Solution for Test: CPM & PERT - 3 - Question 4

The free float for activity i - j is the difference between its earliest finish time and the earliest finish time for its success or activity.

Test: CPM & PERT - 3 - Question 5

If the value of variance is more

Test: CPM & PERT - 3 - Question 6

CPM analysis presumes that

Detailed Solution for Test: CPM & PERT - 3 - Question 6

Test: CPM & PERT - 3 - Question 7

Latest start of an activity is always

Test: CPM & PERT - 3 - Question 8

In the network showrr in the figure the activity 4-5 can be started only when

Test: CPM & PERT - 3 - Question 9

According to Fulkerson’s rule, what are the correct event numbers corresponding to events A, B, C, D,E, Fand G respectively of the network shown in the figure below?

Test: CPM & PERT - 3 - Question 10

The given figure shows the arrow diagram for a particular project. The arrow A is known as

Detailed Solution for Test: CPM & PERT - 3 - Question 10

Activity (1) - (2) is subcritical
Activity (2) - (3) is dummy

Test: CPM & PERT - 3 - Question 11

A ‘merge event’ is represented by

Test: CPM & PERT - 3 - Question 12

Consider the following statements:
The critical path in a network plane of a project
1. help in planning efficient time schedule
2. indicates the shortest path in time
3. helps in crashing the project judiciously 
4. helps in encouraging discipline in execution
Which of these statements are correct?

Detailed Solution for Test: CPM & PERT - 3 - Question 12

A critical path is one which connects the events having zero or minimum slack times. All the events along the critical path are considered to be critical in the sense that any delay in their occurrence will result in the delay in the scheduled completion of the project.

Test: CPM & PERT - 3 - Question 13

Match List-1 (Description of activity floats) with List-11 (Names of the floats) and select the correct answer using the codes given below the lists:
List-I
A. Earliest start time of its successor activity minus earliest finish time' of the activity in question minus the duration
B. Time available for an activity performance minus the duration of the activity
C. Excess of minimum available time over the required activity duration
D. Difference between total float and free float of an activity
List-II
1. Total
2. Free
3. Interfering
4. Independent
Codes: A, B, C, D 

Test: CPM & PERT - 3 - Question 14

Match List-I (Activity types) with List-II (Property of activity) and select the correct answer using the codes given below the lists:
List-I
A. Critical activity to be crashed first to reduce project duration
B. Critical activity
C. Dummy activity
D. Subcritical activity
List II
1. It has float
2. It has least cost slope
3. It maintains logic of network
4. It has no float
Codes: A, B, C, D

Test: CPM & PERT - 3 - Question 15

For an activity i-j, the early event times at i and j, respectively are 5, 24, 9 and 29. (EST = 5, LST = 9, EFT = 24, LFT = 29. The activity duration is 6. Match List-I (Float) with List-ll (Duration) and select the correct answer using the codes given below the lists:
List-I                        List-ll
A. Free                    1. 5
B. Total                    2. 9
C. Interfering           3. 13
D. Independent       4. 18
Codes: A, B, C, D

Test: CPM & PERT - 3 - Question 16

Consider the following statements:
CPM network helps an engineer to
1. Concentrate his attention on critical activities
2. Divert the resources from non-critical advanced activities to critical activities
3. Be cautious in avoiding any delay in the critical activities in order to avoid delay of the whole project
Which of these statements are correct?

Test: CPM & PERT - 3 - Question 17

Consider the following features/factors:
1. Projects are of. the non-repetitive type.
2. Time required .need not be known.
3. Time required is known precisely.
4. Emphasis is,giyen to activities of project.
5. Events have been established for planning.
For which of these features/factors PERT is preferred for planning ?

Test: CPM & PERT - 3 - Question 18

The flow net of activities of a project is given in the following figure. The duration of activities are indicated along the arrows. The critical path of the activities is along

Detailed Solution for Test: CPM & PERT - 3 - Question 18

Path 1-2-4-7-9 = 6 + 9 + 14 + 12 = 41
Path 1-3-5-7-9 = 8 + 9 + 14 + 12 = 43
Path 1-3-6-8-9 = 8 + 10 + 13 + 15 = 46
Path 1-3-5-6-8-9 = 8 + 9 + 10 + 13 + 15 = 45

Test: CPM & PERT - 3 - Question 19

For the network shown in the below figure (the number on each arrow denotes the time duration of activity in days), the earliest start time, in days for activity 5-6 is

Detailed Solution for Test: CPM & PERT - 3 - Question 19


The earliest start time of each activity in days is calculated as shown in the squares on the Network Diagram of various activities.
Therefore from network diagram the earliest start time in days for activity 5-6 is 9 days.

Test: CPM & PERT - 3 - Question 20

The time estimates obtained from four contractors P, Q, R and S for executing a particular job are as under

Which one of these contractors is more certain about completing the job in time?

Detailed Solution for Test: CPM & PERT - 3 - Question 20

Certainity is known by calculating the standard deviatio n,



∴ Q is more certain about completing the job in time.

Information about Test: CPM & PERT - 3 Page
In this test you can find the Exam questions for Test: CPM & PERT - 3 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: CPM & PERT - 3, EduRev gives you an ample number of Online tests for practice