Mechanical Engineering Exam  >  Mechanical Engineering Tests  >  Past Year Questions: PERT And CPM - Mechanical Engineering MCQ

Past Year Questions: PERT And CPM - Mechanical Engineering MCQ


Test Description

20 Questions MCQ Test - Past Year Questions: PERT And CPM

Past Year Questions: PERT And CPM for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Past Year Questions: PERT And CPM questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Past Year Questions: PERT And CPM MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Past Year Questions: PERT And CPM below.
Solutions of Past Year Questions: PERT And CPM questions in English are available as part of our course for Mechanical Engineering & Past Year Questions: PERT And CPM solutions in Hindi for Mechanical Engineering course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Past Year Questions: PERT And CPM | 20 questions in 20 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study for Mechanical Engineering Exam | Download free PDF with solutions
Past Year Questions: PERT And CPM - Question 1

 In PERT, the distribution of activity times is assumed to be

[1995]

Past Year Questions: PERT And CPM - Question 2

A dummy activity is used in PERT network to describe

Detailed Solution for Past Year Questions: PERT And CPM - Question 2

Dummy activities often have a zero completion time & are used to represents precendence relationship.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Past Year Questions: PERT And CPM - Question 3

 In PERT analysis a critical activity has

[2004]

Detailed Solution for Past Year Questions: PERT And CPM - Question 3

Past Year Questions: PERT And CPM - Question 4

Consider a PERT network for a project involving six tasks (a to f)

The expected completion time of the project is

[2006]

Detailed Solution for Past Year Questions: PERT And CPM - Question 4

⇒ a – c – e – f
⇒ 30 + 60 + 45 + 20 = 155 days

Past Year Questions: PERT And CPM - Question 5

The standard deviation of the critical path of the project is

[2006]

Detailed Solution for Past Year Questions: PERT And CPM - Question 5

Past Year Questions: PERT And CPM - Question 6

The expected time (te) of a PERT activity in terms of optimistic time (t0), pessimistic time (tp) and most likely time (tl) is given by

[2006]

Past Year Questions: PERT And CPM - Question 7

Consider the following PERT network:

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:The critical path duration of the network (in days) is

[2009]

Detailed Solution for Past Year Questions: PERT And CPM - Question 7

EST = Earliest start time LFT = Latest Finish Time \ Path along which EST & LFT is equal are called critical path Critical path duration is 18 days.

Past Year Questions: PERT And CPM - Question 8

The standard deviation of the critical path is

[2009]

Detailed Solution for Past Year Questions: PERT And CPM - Question 8

Past Year Questions: PERT And CPM - Question 9

In PERT chart, the activity time distribution is

[2016]

Detailed Solution for Past Year Questions: PERT And CPM - Question 9

Beta distribution extended to the Maximum & Minimum & gives strict definition for the mean & variance

Past Year Questions: PERT And CPM - Question 10

In the construction of networks , dummy activities are introduced in order to

[1990]

Past Year Questions: PERT And CPM - Question 11

The symbol used for Transport in work study is

[2003]

Past Year Questions: PERT And CPM - Question 12

 A project consists of activities A to M shown in the net in the following figure with the duration of the activities marked in daysThe project can be completed

[2003]

Detailed Solution for Past Year Questions: PERT And CPM - Question 12

Project completed = Activity C + Activity F + Activity K + Activity M
⇒ 4 + 9 + 3 + 8 = 24

Past Year Questions: PERT And CPM - Question 13

An assembly activity is represented on an Operation Process Chart by the symbol

[2005]

Past Year Questions: PERT And CPM - Question 14

A project has six activities (A t o F ) w it h respective activity durations 7,5,6,6,8,4 days.The network has three path A-B, C-D and EF. All the activities can be crashed with the same crash cost per day.The number of activities that need to be crashed to reduce the project duration by 1 day is

[2005]

Past Year Questions: PERT And CPM - Question 15

 For the network below, the objective is to find the length of the shortest path from node P to node G. Let dij be the length of directed arc from node i to node j.Let sj, be the length of the shortest path from P to node j. Which of the following equations can be used to find SG?

[2008]

Detailed Solution for Past Year Questions: PERT And CPM - Question 15

The only way to reach G is th en by r eading Q and then QG or reaching R and then RG.
therefore, SG = Min [SQ + dQG ,.SR + dRG

Past Year Questions: PERT And CPM - Question 16

The  project activities, precedence relationships and durations are described in the table. The critical path of the project is

[2010]

Detailed Solution for Past Year Questions: PERT And CPM - Question 16

Path QSUW = Q + S + U + W = 4 + 5 + 5 +10 = 24 days.

Past Year Questions: PERT And CPM - Question 17

 The critical path for the project is

[2012]

Detailed Solution for Past Year Questions: PERT And CPM - Question 17

Various path are A B E G H – 17 days A C G H – 16 days A D F H – 18 days; Hence A D F H is critical path

Past Year Questions: PERT And CPM - Question 18

If duration of activity f is changed to 10 days, then the critical path for the project is

[2012]

Detailed Solution for Past Year Questions: PERT And CPM - Question 18

If duration of activity F has changed to 10 days, critical path remains the same and project duration will increase to 19 days.

Past Year Questions: PERT And CPM - Question 19

Consider the given project network, where numbers along various activities represent normal time. The free float on activity 4-6 and the project duration, respectively, are

[2014]

Detailed Solution for Past Year Questions: PERT And CPM - Question 19

For 4 – 6 Free float = (Ej – Ei) – dij = (8 – 2) – 4
= 6 – 4 = 2
Project duration , E = 13
therefore, (2, 13)

Past Year Questions: PERT And CPM - Question 20

The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are

[2014]

Detailed Solution for Past Year Questions: PERT And CPM - Question 20

= (E, L)
TF = LFT – EFT = LST – EST
(TF)F ⇒ 7 - 4 -2 = 1
(TF)F ⇒ 12 - 4 - 4 = 4

Information about Past Year Questions: PERT And CPM Page
In this test you can find the Exam questions for Past Year Questions: PERT And CPM solved & explained in the simplest way possible. Besides giving Questions and answers for Past Year Questions: PERT And CPM, EduRev gives you an ample number of Online tests for practice

Top Courses for Mechanical Engineering

Download as PDF

Top Courses for Mechanical Engineering