Electrical Engineering (EE) Exam  >  Electrical Engineering (EE) Tests  >  Test: Long Transmission Line - Electrical Engineering (EE) MCQ

Test: Long Transmission Line - Electrical Engineering (EE) MCQ


Test Description

5 Questions MCQ Test - Test: Long Transmission Line

Test: Long Transmission Line for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Test: Long Transmission Line questions and answers have been prepared according to the Electrical Engineering (EE) exam syllabus.The Test: Long Transmission Line MCQs are made for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Long Transmission Line below.
Solutions of Test: Long Transmission Line questions in English are available as part of our course for Electrical Engineering (EE) & Test: Long Transmission Line solutions in Hindi for Electrical Engineering (EE) course. Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free. Attempt Test: Long Transmission Line | 5 questions in 15 minutes | Mock test for Electrical Engineering (EE) preparation | Free important questions MCQ to study for Electrical Engineering (EE) Exam | Download free PDF with solutions
Test: Long Transmission Line - Question 1

Length of long transmission line is more than ___________

Detailed Solution for Test: Long Transmission Line - Question 1

Transmission lines having length more than 200 kilometres are categorised as long transmission lines. Transmission lines having length less than 200 kilometres are medium transmission lines.

Test: Long Transmission Line - Question 2

Range of surge impedance for an overhead transmission line is ____________

Detailed Solution for Test: Long Transmission Line - Question 2

Surge impedance is the characteristic impedance of a loss free transmission line. It is the square root of ratio of line impedance(Z) and shunt admittance (Y). Its value varies between 400 Ω and 600 Ω.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Long Transmission Line - Question 3

Synchronous phase modifiers are installed at which of the following position of the transmission line?

Detailed Solution for Test: Long Transmission Line - Question 3

For constant voltage transmission, specially designed synchronous motors, called synchronous phase modifiers. Synchronous phase modifiers are installed at receiving end to maintain the voltage drop along the line constant.

Test: Long Transmission Line - Question 4

The leakage current through the shunt admittance is __________

Detailed Solution for Test: Long Transmission Line - Question 4

The leakage current through the shunt admittance is maximum at the sending end of the transmission line. This current decreases continuously as it move towards the receiving end of the line and becomes zero at the receiving end.

Test: Long Transmission Line - Question 5

In long transmission lines Resistance and Capacitance parameters of lines are connected in __________

Detailed Solution for Test: Long Transmission Line - Question 5

The resistance and inductance parameters are series elements of long transmission line. Capacitive susceptance and conductance parameters are shunt elements of transmission lines.

Information about Test: Long Transmission Line Page
In this test you can find the Exam questions for Test: Long Transmission Line solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Long Transmission Line, EduRev gives you an ample number of Online tests for practice

Top Courses for Electrical Engineering (EE)

Download as PDF

Top Courses for Electrical Engineering (EE)