In the cubical contents method, the cost of a structure is computed by the multiplication of total cubic contents and _______
As per IS 3861-1966, which of the following areas should not be included while calculating the plinth area of a building?
1 Crore+ students have signed up on EduRev. Have you? Download the App |
Which of the following is not a method used for preparing approximate estimates?
While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per _____
Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the execution of the work.
For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.
In the plinth area method, the cost of construction is computed by the multiplication of ________
In the case of works which require some special types of equipment, an amount of ______ percent of the estimated cost is given.
The process of working out the cost per unit of each item is known as ______
Which of the following data is not required to prepare an estimate?