You can prepare effectively for RPSC RAS (Rajasthan) RAS RPSC Prelims Preparation - Notes, Study Material & Tests with this dedicated MCQ Practice Test (available with solutions) on the important topic of "CHAIN RULE - MCQ Test (1)". These 16 questions have been designed by the experts with the latest curriculum of RPSC RAS (Rajasthan) 2026, to help you master the concept.
Test Highlights:
Sign up on EduRev for free to attempt this test and track your preparation progress.
If the cost of x metres of wire is d rupees, then what is the cost of y metres of wire at the samerate?
Detailed Solution: Question 1
In a camp, there is a meal for 120 men or 200 children. If 150 children have taken the meal, howmany men will be catered to with remaining meal?
Detailed Solution: Question 2
36 men can complete a piece of work in 18 days. In how many days will 27 men complete thesame work?
Detailed Solution: Question 3
A wheel that has 6 cogs is meshed with a larger wheel of 14 cogs. If the smaller wheel has made21 revolutions, what will be the number of revolutions made by the larger wheel?
Detailed Solution: Question 4
3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day should 4pumps work in order to empty the tank in 1 day?
Detailed Solution: Question 5
39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons,working 6 hours a day, complete the work?
Detailed Solution: Question 6
A certain industrial loom weaves 0.128 meters of cloth every second. Approximately how manyseconds will it take for the loom to weave 25 meters of cloth?
Detailed Solution: Question 7
21 goats eat as much as 15 cows. How many goats each as much as 35 cows?
Detailed Solution: Question 8
In a dairy farm, 40 cows eat 40 bags of husk in 40 days. In how many days one cow will eat onebag of husk?
Detailed Solution: Question 9
. If a quarter kg of potato costs 60 paise, how many paise does 200 gm cost?
Detailed Solution: Question 10
A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After30 days, 2/5 of the work is completed. How many additional persons should be deployed so that thework will be completed in the scheduled time, each person’s now working 9 hours a day.
Detailed Solution: Question 11
x men working x hours per day can do x units of a work in x days. How much work can becompleted by y men working y hours per day in y days?
Detailed Solution: Question 12
A flagstaff 17.5 m high casts a shadow of length 40.25 m. What will be the height of a building,which casts a shadow of length 28.75 m under similar conditions?
Detailed Solution: Question 13
If the price of 357 apples is Rs.1517.25, what will be the approximate price of 49 dozens of suchapples?
Detailed Solution: Question 14
9 engines consume 24 metric tonnes of coal, when each is working 8 hours day. How much coal isrequired for 8 engines, each running 13 hours a day, if 3 engines of former type consume as much as4 engines of latter type?
Detailed Solution: Question 15
In a camp, food was was sufficient for 2000 people for 54 days. After 15 days, more people cameand the food last only for 20 more days. How many people came?
Detailed Solution: Question 16