You can prepare effectively for Mechanical Engineering GATE Mechanical (ME) Mock Test Series 2027 with this dedicated MCQ Practice Test (available with solutions) on the important topic of "Industrial Engineering - 1". These 15 questions have been designed by the experts with the latest curriculum of Mechanical Engineering 2026, to help you master the concept.
Test Highlights:
Sign up on EduRev for free to attempt this test and track your preparation progress.
A work centre operates 6 days per week on a two-shift-per-day basis (8 hours per shift) and has four machines with the same capability. If the machines are utilized 75% of the time at a system efficiency of 90%, what s the rated output in standard hours per week?
Detailed Solution: Question 1
Detailed Solution: Question 2
The product variety is height in the following production system
Detailed Solution: Question 3
Consider the project shown in the figure below form the possible sequence of start to the finish. Find the critical path.
Detailed Solution: Question 4
In the linear programming model, the objective and the constraint coefficients are deterministic implies that all the constraints are know. This is the property of
Detailed Solution: Question 5
Detailed Solution: Question 6
Detailed Solution: Question 7
Buyers products company distributes an item known as a tie bar, which is a U-bolt used on truck equipment. The following data have been collected for this item held in inventory.
Monthly demand forecast, d = 11,107 units
Standard error of forecast = 3,099 units
Replenishment lead time, LT = 1.5 months
Item value, C = $ 0.11/unit
Cost for processing vendor order, S = $ 10/order
Carrying cost, I = 20%/year
In-stock probability during lead time,
P = 75% Find the reorder level
Maximize z = 3x1 + 9x2
Subject to:
Which of the following is true for above problem?
A small maintenance project consists of the following 10 jobs, whose precedence, relationships are identified by their node numbers:
Q.
What is the earliest and latest start and finish times for job F?
A small maintenance project consists of the following 10 jobs, whose precedence, relationships are identified by their node numbers:
Q.
Find the critical path of the network
In the manufacturing firm the operators re-assigned with each one of the machine. The cost for assigning each machine is depicted in the following table.
Q.
What is the optimal schedule?
Detailed Solution: Question 12
In the manufacturing firm the operators re-assigned with each one of the machine. The cost for assigning each machine is depicted in the following table.
Q.
The optimum cost that we can assign is
The moving-average forecast and the actual demand for a hospital drug are shown in table. Then find the tracking signal using this
Detailed Solution: Question 14
Project planners have sought the judgment of various knowledgeable engineers, foreman, and vendors and have developed the time estimate shown below in network diagram. (Time estimates are in months). What is the probability at the project will be finished within 4 years?
Detailed Solution: Question 15
30 docs|220 tests |