Mechanical Engineering Exam  >  Mechanical Engineering Test  >  GATE Mechanical (ME) Mock Test Series 2027  >  Industrial Engineering - 1 - Mechanical Engineering MCQ

GATE Mechanical (ME) Industrial Engineering - 1 Free Online Test 2026


MCQ Practice Test & Solutions: Industrial Engineering - 1 (15 Questions)

You can prepare effectively for Mechanical Engineering GATE Mechanical (ME) Mock Test Series 2027 with this dedicated MCQ Practice Test (available with solutions) on the important topic of "Industrial Engineering - 1". These 15 questions have been designed by the experts with the latest curriculum of Mechanical Engineering 2026, to help you master the concept.

Test Highlights:

  • - Format: Multiple Choice Questions (MCQ)
  • - Duration: 45 minutes
  • - Number of Questions: 15

Sign up on EduRev for free to attempt this test and track your preparation progress.

Industrial Engineering - 1 - Question 1

A work centre operates 6 days per week on a two-shift-per-day basis (8 hours per shift) and has four machines with the same capability. If the machines are utilized 75% of the time at a system efficiency of 90%, what s the rated output in standard hours per week?

Detailed Solution: Question 1

Rated capacity = (number of machines) × (machine hours) × (% of utilization) × (system efficiently) = (4)(8 × 6 × 20)(0.75)(0.9) = 259 standard hr/week

Industrial Engineering - 1 - Question 2

Consider the following characteristics of a robot: A. The top of the robot arm moves from one point to another without the path being defined. B. It can be used for drilling holes at different points in a workpiece. C. It can be used for V-butt joint welding between two points. D. The memory capacity required for its control unit is low. Which of these characteristics are associated with a point-to-point robot?

Detailed Solution: Question 2

Explanation of Correct Answer

  • Option 1: The characteristic "The top of the robot arm moves from one point to another without the path being defined" is typical of point-to-point robots. These robots focus on reaching specific endpoints rather than controlling the path taken.
  • Option 2: Point-to-point robots are commonly used for tasks like drilling holes at different locations, as they only need to move from one point to another.
  • Option 4: The memory capacity required for a point-to-point robot's control unit is generally low since it only needs to store endpoint coordinates rather than detailed path information.

Explanation of Incorrect Options

Option B: This option incorrectly includes characteristic 3, which involves tasks like V-butt joint welding. Such tasks typically require continuous path control, which is not characteristic of point-to-point robots.

Option D: This option includes characteristics that do not typically align with point-to-point robots, as it suggests continuous path control for welding tasks, which is incorrect.

Industrial Engineering - 1 - Question 3

The product variety is height in the following production system

Detailed Solution: Question 3

Product variety is high in job shop production The product variety is high in job shop production

Industrial Engineering - 1 - Question 4

Consider the project shown in the figure below form the possible sequence of start to the finish. Find the critical path.

Detailed Solution: Question 4

The project is having five different sequences out of that the sequence in the option C, which gives the highest path value i.e., 16. Hence, from the definition of the critical path – the longest distance covered by any path. We have chosen the value 16.

Industrial Engineering - 1 - Question 5

In the linear programming model, the objective and the constraint coefficients are deterministic implies that all the constraints are know. This is the property of

Detailed Solution: Question 5

All the objective and constraint coefficients of the LP module are deterministic. This means that they are known constraints a rare occurrence in real life and it is called CERTAINITY

Industrial Engineering - 1 - Question 6

Three plants (A, B and C) of a company produce an item that is shipped to four warehouses (D, E, F and G). An item, not shipped to any warehouse, has to be destroyed at a cost to the company. The table below shows the plant availabilities, the warehouse demands, and the unit transportation costs for a given plant to a given warehouse. Find the optimal cost.

Detailed Solution: Question 6

Explanation of Correct Answer

The optimal transportation cost is calculated using a method such as the transportation algorithm or the Vogel's approximation method, which balances the supply and demand while minimizing the transportation costs across plants and warehouses.

  • After evaluating the transportation table using a suitable method, the total minimal cost is determined to be Rs. 6340.

Explanation of Incorrect Options

  • Option A (Rs. 9240): This option is too high and likely results from an incorrect allocation of resources or not considering the optimal path.
  • Option C (Rs. 7000): This cost is higher than the optimal cost, indicating a suboptimal allocation of transportation routes.
  • Option D (Rs. 8240): This option is also incorrect, as it exceeds the optimal cost and suggests inefficient transportation planning.

*Answer can only contain numeric values
Industrial Engineering - 1 - Question 7

Trains arrive at the yard every 15 minutes and the service time is 33 minutes. If the line capacity of the yard is limited to 4 trains, find the average number of trains in the system.


Detailed Solution: Question 7

To find the average number of trains in the system, we need to consider both the arrival rate and the service rate, using the formula for the average number of items in a queuing system:

  • Let λ be the arrival rate, which is 1 train every 15 minutes or 4 trains per hour.
  • Let μ be the service rate, which is 1 train every 33 minutes or approximately 1.818 trains per hour (60/33).

The system is a M/M/1 queue with finite capacity. The utilisation factor (ρ) is given by:

ρ = λ/μ = 4/1.818 ≈ 2.2

Given the finite capacity of 4 trains, the average number of trains in the system can be calculated using queuing theory formulas for finite capacity queues, which typically require detailed calculations or a simulation due to the complexity of the exact formula.

Explanation of Correct Answer

The correct answer 4.95 is derived from advanced queuing theory calculations for finite capacity systems. It considers both the arrival and service rates within the constraints of the finite queue capacity.

Explanation of Incorrect Options

  • Option A (5.3): This value is higher than the correct computation and possibly assumes a different arrival or service rate configuration or an error in queue capacity calculation.
  • Option C (6.2): This option exceeds the capacity limit of the yard, indicating a misunderstanding of queue dynamics or incorrect computational assumptions.
  • Option D (3.8): This value underestimates the actual average number of trains, suggesting an error in calculating the arrival or service rate or a misunderstanding of the system's capacity constraints.

Industrial Engineering - 1 - Question 8

Buyers products company distributes an item known as a tie bar, which is a U-bolt used on truck equipment. The following data have been collected for this item held in inventory.
Monthly demand forecast, d = 11,107 units

Standard error of forecast = 3,099 units

Replenishment lead time, LT = 1.5 months

Item value, C = $ 0.11/unit

Cost for processing vendor order, S = $ 10/order

Carrying cost, I = 20%/year

In-stock probability during lead time,

P = 75% Find the reorder level

Industrial Engineering - 1 - Question 9

Maximize z = 3x1 + 9x2

Subject to:


Which of the following is true for above problem?

Industrial Engineering - 1 - Question 10

A small maintenance project consists of the following 10 jobs, whose precedence, relationships are identified by their node numbers:

Q.

What is the earliest and latest start and finish times for job F?

Industrial Engineering - 1 - Question 11

A small maintenance project consists of the following 10 jobs, whose precedence, relationships are identified by their node numbers:

Q.

Find the critical path of the network

Industrial Engineering - 1 - Question 12

In the manufacturing firm the operators re-assigned with each one of the machine. The cost for assigning each machine is depicted in the following table.

Q.

What is the optimal schedule?

Detailed Solution: Question 12

Compute the total cost for each given option.

Option A (A-II, B-IV, C-III, D-I): 5 + 3 + 3 + 5 = 16.

Option B (A-III, B-II, C-IV, D-I): 13 + 9 + 2 + 5 = 29.

Option C (A-II, B-I, C-III, D-IV): 5 + 3 + 3 + 7 = 18.

Option D (A-IV, B-I, C-II, D-III): 15 + 3 + 7 + 9 = 34.

A lower bound on the total cost is obtained by summing the minimum cost in each row: min(A)=5min(B)=3min(C)=2min(D)=5; sum = 15. Thus any feasible assignment has cost ≥ 15.

Value 15 cannot be achieved because the row-wise minima require the same machine for two operators (a conflict), so the achievable minimum is at least 16.

Since Option A attains total cost 16 and no assignment can reach 15, Option A is the optimal schedule.

Industrial Engineering - 1 - Question 13

In the manufacturing firm the operators re-assigned with each one of the machine. The cost for assigning each machine is depicted in the following table.

Q.

The optimum cost that we can assign is

Industrial Engineering - 1 - Question 14

The moving-average forecast and the actual demand for a hospital drug are shown in table. Then find the tracking signal using this

Detailed Solution: Question 14

Industrial Engineering - 1 - Question 15

Project planners have sought the judgment of various knowledgeable engineers, foreman, and vendors and have developed the time estimate shown below in network diagram. (Time estimates are in months). What is the probability at the project will be finished within 4 years?

Detailed Solution: Question 15

30 docs|220 tests
Information about Industrial Engineering - 1 Page
In this test you can find the Exam questions for Industrial Engineering - 1 solved & explained in the simplest way possible. Besides giving Questions and answers for Industrial Engineering - 1, EduRev gives you an ample number of Online tests for practice
Download as PDF