Test: CPM, PERT & Inventory Control - 2 - Mechanical Engineering MCQ


Test Description

30 Questions MCQ Test - Test: CPM, PERT & Inventory Control - 2

Test: CPM, PERT & Inventory Control - 2 for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Test: CPM, PERT & Inventory Control - 2 questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: CPM, PERT & Inventory Control - 2 MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: CPM, PERT & Inventory Control - 2 below.
Solutions of Test: CPM, PERT & Inventory Control - 2 questions in English are available as part of our course for Mechanical Engineering & Test: CPM, PERT & Inventory Control - 2 solutions in Hindi for Mechanical Engineering course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Test: CPM, PERT & Inventory Control - 2 | 30 questions in 90 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study for Mechanical Engineering Exam | Download free PDF with solutions
Test: CPM, PERT & Inventory Control - 2 - Question 1

The project activities, precedence relationships and durations are described in the table. The critical path of the project is: 

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 1

Q – S – V – W is haring maximum duration = 24 days so it is the critical path. 

Test: CPM, PERT & Inventory Control - 2 - Question 2

In a machine shop, pins of 15 mm diameter are produced at a rate of 1000 per month and the same is consumed at a rate of 500 per month. The production and consumption continue simultaneously till the maximum inventory is reached. Then inventory is allowed to reduce to zero due to consumption. The lot size of production is 1000. If backlog is not allowed, the maximum inventory level is:  

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 2

MAXIMUM INVENTORY 

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: CPM, PERT & Inventory Control - 2 - Question 3

A project has six activities (A to F) with respective activity durations 7, 5, 6, 6, 8, 4 days. The network has three paths A-B, C-D and E-F. All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by 1 day is: 

Test: CPM, PERT & Inventory Control - 2 - Question 4

Consider the following data for an item. 

Annual demand: 2500  units per year Ordering cost: Rs. 100 per order Inventory holding rate: 25% of unit price.

The optimum order quantity ?  

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 4

D = 2500 units/years
Co = Rs. 100/order
Ch = (0.25) Unit + Price

⇒23562.5
Since Total cost minimum at Q = 500 units
∴ the optimal order quality is Q = 500 units

Test: CPM, PERT & Inventory Control - 2 - Question 5

Consider the following statements:

PERT considers the following time estimates
1. Optimistic time
2. Pessimistic time
3. Most likely time

Which of the statements given above are correct?  

Test: CPM, PERT & Inventory Control - 2 - Question 6

In computing Wilson's economic lot size for an item, by mistake the demand rate estimate used was 40% higher than the tree demand rate. Due to this error in the lot size computation, the total cost of setups plus inventory holding per unit time. Would rise above the true optimum by approximately 

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 6


Test: CPM, PERT & Inventory Control - 2 - Question 7

Consider the following statements with respect to PERT

1. It consists of activities with uncertain time phases
2. This is evolved from Gantt chart 
3. Total slack along the critical path is not zero
4. There can be more than one critical path in PERT network
5. It is similar to electrical network

Which of the statements given above are correct?  

Test: CPM, PERT & Inventory Control - 2 - Question 8

One of the following statements about PRS (Periodic Reordering System) is not true. Identify 

Test: CPM, PERT & Inventory Control - 2 - Question 9

Dummy activities are used in a network to: 

Test: CPM, PERT & Inventory Control - 2 - Question 10

The net requirements of an item over 5 consecutive weeks are 50-015-20-20. The inventory carrying costs are Re. 1 per item per week and Rs. 100 per order respectively. Starting inventory is zero. Use “Least Unit Const Technique” for developing the plan. The const of the plan (in Rs.) is: 

Test: CPM, PERT & Inventory Control - 2 - Question 11

A PERT activity has an optimistic time estimate of 3 days, a pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?  

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 11

Test: CPM, PERT & Inventory Control - 2 - Question 12

Which of the following are the benefits of inventory control? 

1. Improvement in customers relationship.
2. Economy in purchasing.
3. Elimination of the possibility of duplicate ordering.

 Select the correct answer using the code given below:  

Test: CPM, PERT & Inventory Control - 2 - Question 13

Which one of the following statements is not correct? 

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 13

(a) PERT → Event oriented
CPM → Activity oriented
(b) PERT → 3 tim e esti mates are made 

CPM → on ly one ti me estimate
(c) In PERT slack is calculated, CPM floats calculated
(d) Both PERT and CPM are used for project situation. 

Test: CPM, PERT & Inventory Control - 2 - Question 14

In ABC analysis, A items require: 

Test: CPM, PERT & Inventory Control - 2 - Question 15

If the earliest starting time for an activity is 8 weeks, the latest finish time is 37 weeks and the duration time of the activity is 11 weeks, then the total float is equal to: 

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 15

T.F. = LSi− ESij − tij = 37 − 8 − 11 = 18

Test: CPM, PERT & Inventory Control - 2 - Question 16

Classifying items in A, B and C categories for selective control in inventory management is done by arranging items in the decreasing order of: 

Test: CPM, PERT & Inventory Control - 2 - Question 17

The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' I' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks. If the activity time is 11 weeks, then the total float will be: 

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 17

Total float = 37 – 8 – 11 = 18 days. 

Test: CPM, PERT & Inventory Control - 2 - Question 18

Assertion (A): Selective control manages time more effectively.

Reason (R): ABC analysis is based on Pareto distribution. 

Test: CPM, PERT & Inventory Control - 2 - Question 19

Which of the following are the guidelines for the construction of a network diagram?

1. Each activity is represented by one and only one arrow in the network.
2. Two activities can be identified by the same beginning and end events.
3. Dangling must be avoided in a network diagram.
4. Dummy activity consumes no time or resource.

Select the correct answer using the codes given below:  

Test: CPM, PERT & Inventory Control - 2 - Question 20

ABC analysis in materials management is a method of classifying the inventories based on 

Test: CPM, PERT & Inventory Control - 2 - Question 21

Earliest finish time can be regarded as 

Test: CPM, PERT & Inventory Control - 2 - Question 22

Consider the following statements:

1. ABC analysis is based on Pareto's principle 
2. FIFO and LIFO policies can be used for material valuation in materials management.
3. Simulation can be Used for inventory control.
4. EOQ (Economic Order Quantity) formula ignores variations in demand pattern.

Of these statem ents:   

Test: CPM, PERT & Inventory Control - 2 - Question 23

Consider an activity having a duration time of Tij. E is the earliest occurrence time and L the latest occurrence time (see figure given). 

Consider the following statements in this regard:

1. Total float = Lj - Ei - Tij
2. Free float = Ej - Ei - Tij
3. Slack of the tail event = Lj- Ei

Of these statem ents:   

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 23

 

Test: CPM, PERT & Inventory Control - 2 - Question 24

Out of the following item listed below, which two items you would consider under category (c) under ABC analysis:

Test: CPM, PERT & Inventory Control - 2 - Question 25

What is the additional time available for the performance of an activity in PERT and CPM calculated on the basis that all activities will start at their earliest start time, called? 

Test: CPM, PERT & Inventory Control - 2 - Question 26

In the ABC method of inventory control, Group A constitutes costly items. What is the usual percentage of such items of the total items? 

Test: CPM, PERT & Inventory Control - 2 - Question 27

Which one of the following networks is correctly drawn? 

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 27

Diagram (a) is correct as in (b) & (c) diagrams backward arrows are seen which is not correct. In (d) both activity is dummy it is also not correct. 

Test: CPM, PERT & Inventory Control - 2 - Question 28

Which one of the following is correct? 
In the basic EOQ model, if lead time increases from 5 to 10 days, the EOQ will:   

Test: CPM, PERT & Inventory Control - 2 - Question 29

The essential condition for the decompression of an activity is:   

Test: CPM, PERT & Inventory Control - 2 - Question 30

In the EOQ model, if the unit ordering cost is doubled, the EOQ   

Detailed Solution for Test: CPM, PERT & Inventory Control - 2 - Question 30

Information about Test: CPM, PERT & Inventory Control - 2 Page
In this test you can find the Exam questions for Test: CPM, PERT & Inventory Control - 2 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: CPM, PERT & Inventory Control - 2, EduRev gives you an ample number of Online tests for practice