Mechanical Engineering Exam  >  Mechanical Engineering Tests  >  Test: MRP Work Study & Work Measurement - 2 - Mechanical Engineering MCQ

Test: MRP Work Study & Work Measurement - 2 - Mechanical Engineering MCQ


Test Description

30 Questions MCQ Test - Test: MRP Work Study & Work Measurement - 2

Test: MRP Work Study & Work Measurement - 2 for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Test: MRP Work Study & Work Measurement - 2 questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: MRP Work Study & Work Measurement - 2 MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: MRP Work Study & Work Measurement - 2 below.
Solutions of Test: MRP Work Study & Work Measurement - 2 questions in English are available as part of our course for Mechanical Engineering & Test: MRP Work Study & Work Measurement - 2 solutions in Hindi for Mechanical Engineering course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Test: MRP Work Study & Work Measurement - 2 | 30 questions in 90 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study for Mechanical Engineering Exam | Download free PDF with solutions
Test: MRP Work Study & Work Measurement - 2 - Question 1

A process of discovering and identifying the pertinent information relating to the nature of a specific job is called 

Test: MRP Work Study & Work Measurement - 2 - Question 2

Which of the following hand-motion belongs to 'Therblig' in motion study')

1. Unavoidable delay
2. Pre-position  
3. Select
4. Reach

Select the correct answer from the codes given below: 

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: MRP Work Study & Work Measurement - 2 - Question 3

Assertion (A): Job enrichment increases the job satisfaction of the employee.

Reason (R): The jobs of wireman and lineman doing indoor and outdoor works respectively can be integrated for better results.  

Test: MRP Work Study & Work Measurement - 2 - Question 4

Match List-I (Charts) with List-II (Details) and select the correct answer using the codes given below the lists:


Test: MRP Work Study & Work Measurement - 2 - Question 5

Procedure of modifying work content to give more meaning and enjoyment to the job by involving employees in planning, organization and control of their work, is termed as 

Test: MRP Work Study & Work Measurement - 2 - Question 6

Assertion (A): SIMO chart reveals the deficiencies in the motion pattern of the process chart.

Reason (R): SIMO chart and operator processes chart yield the same results.  

Test: MRP Work Study & Work Measurement - 2 - Question 7

A systematic job improvement sequence will consist of: 

(i) Motion Study
(ii) Time Study
(iii) Job Enrichment
(iv) Job Enlargement  

An optimal sequence would consist of:  

Test: MRP Work Study & Work Measurement - 2 - Question 8

Match List-I (Study) with List-II (Related factors) and select the correct answer using the codes given below the lists:


Test: MRP Work Study & Work Measurement - 2 - Question 9

Which one of the following statements is correct?

Standard time is obtained from normal time by adding the policy allowance and  

Detailed Solution for Test: MRP Work Study & Work Measurement - 2 - Question 9

Standard time = Normal time + PDA Allowances 

Test: MRP Work Study & Work Measurement - 2 - Question 10

Repetitive fast speed activities can be effectively analyzed by taking photograph at 

Test: MRP Work Study & Work Measurement - 2 - Question 11

A time standard for a data entry clerk is to be set. A job is rated at 120 percent, it takes 30 seconds to enter each record and the allowances are 15%. What is the normal time? 

Test: MRP Work Study & Work Measurement - 2 - Question 12

Determination of standard time in complex job system is best done through 

Test: MRP Work Study & Work Measurement - 2 - Question 13

If in a time study, the observed time is 0.75 min, rating factor = 110% and allowances are 20% of normal time, then what is the standard time? 

Detailed Solution for Test: MRP Work Study & Work Measurement - 2 - Question 13

Normal time = Observed Time × Rating Factor = 0.75 ×1.1 = 0.825 min  
Standard time = Normal Time × (1 + % age allowance)
= 0.825 × (1 + 0.20) = 0.99 minutes 

Test: MRP Work Study & Work Measurement - 2 - Question 14

Standard time is: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 2 - Question 14

Normal time = Actual time × Rating factor
Standard time = Normal time + Allowances

Test: MRP Work Study & Work Measurement - 2 - Question 15

In time study, the rating factor is applied to determine 

Detailed Solution for Test: MRP Work Study & Work Measurement - 2 - Question 15

In time study, the rating factor is applied to determine merit rating of the worker. 

Test: MRP Work Study & Work Measurement - 2 - Question 16

The standard time of an operation has been calculated as 10 min. The worker was rated at 80%. If the relaxation and other allowances were 25%, then the observed time would be: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 2 - Question 16

Observed time = (Standard time + Allowances) × Rating of worker
= 10 × (1 + 0.25) × 0.8 = 10 

Test: MRP Work Study & Work Measurement - 2 - Question 17

Match List-I (Charts) with List-II (Operations/Information) using the codes given below the lists:


Test: MRP Work Study & Work Measurement - 2 - Question 18

Consider the following objectives:

1. To train the individual regarding motion economy.
2. To assist in research projects in the field of work study.
3. To help in the collection of Motion Time data. 

Detailed Solution for Test: MRP Work Study & Work Measurement - 2 - Question 18

Objectives 1 and 3 are true for Micromotion study. 

Test: MRP Work Study & Work Measurement - 2 - Question 19

MTM is a work measurement technique by: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 2 - Question 19

MTM (Methods-time measurement) is based on use of standard time for work elements that have been predetermined from long periods of observation and analysis.

Test: MRP Work Study & Work Measurement - 2 - Question 20

Which one of the following is NOT a work measurement technique? 

Test: MRP Work Study & Work Measurement - 2 - Question 21

Which one of the following is not a technique under Predetermined Motion Time System (PMTS)? 

Test: MRP Work Study & Work Measurement - 2 - Question 22

Consider the following steps:

1. Method time measurement
2. Work sampling
3. Work factor system.

PMTS (Predetermined motion time systems) in work study would include:  

Test: MRP Work Study & Work Measurement - 2 - Question 23

Which one of the following statements is not correct? 

Test: MRP Work Study & Work Measurement - 2 - Question 24

Match List-I with List-II and select the correct answer using the codes given below the lists:


Test: MRP Work Study & Work Measurement - 2 - Question 25

Work study involves 

Test: MRP Work Study & Work Measurement - 2 - Question 26

Motions of limbs are through

1. Elbow
2. Finger
3. Hip  
4. Shoulder
5. Wrist

What is the correct sequence in descending order of motion in terms of time of fatigue involved?  

Test: MRP Work Study & Work Measurement - 2 - Question 27

A SIMO chart should be used with 

Test: MRP Work Study & Work Measurement - 2 - Question 28

Match List-I (Type of Chart) with List-II (Definition) and select the correct answer using the codes given below the lists:


Test: MRP Work Study & Work Measurement - 2 - Question 29

A graphical representation of the coordinated activities (i.e., fundamental motions) of an operator's body members, on a common time scale is known as 

Test: MRP Work Study & Work Measurement - 2 - Question 30

Consider the following statements:

Method study is carried out to achieve
1. The most effective use of plant and equipment.
2. The most effective use of human efforts.
3. Evaluation of human work.

Which of the statements given above are correct? 

Information about Test: MRP Work Study & Work Measurement - 2 Page
In this test you can find the Exam questions for Test: MRP Work Study & Work Measurement - 2 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: MRP Work Study & Work Measurement - 2, EduRev gives you an ample number of Online tests for practice

Top Courses for Mechanical Engineering

Download as PDF

Top Courses for Mechanical Engineering