All Exams  >   SSC CGL  >   Quantitative Aptitude for SSC CGL  >   All Questions

All questions of Time and Work for SSC CGL Exam

A and B together can do a piece of work in 24 days, which B and C together can do it in 32 days. After A has been working at it for 10 days and B for 14 days, C finishes it in 26 days. In how many days C alone will do the work?
  • a)
    32
  • b)
    36
  • c)
    44
  • d)
    48
  • e)
    None of these
Correct answer is option 'D'. Can you explain this answer?

Anaya Patel answered
Correct Answer :- d
Explanation : Work done by (A+B)'s in 1 day = 24
work done by (B+C)'s in 1 day = 32
Let C does a work in x days
Then work done by C in a day = 1/x
According to the question
A's 10 day's work + B's 14 day's work + C's 26 day's work = 1
10A + 14B + 26C = 1 ;
10A + 10B + 4B + 4C + 22C = 1 ;
10(A + B ) + 4( B + C ) + 22C = 1 ;
10( 1/24 ) + 4( 1/32 ) + 22C = 1 ;
10/24 + 4/32 + 22C = 1 ;
13/24 + 22C = 1 ;
22C = 1 - 13/24 ;
22C = 11/24 ;
2C = 1/24 ;
C = 1/48 ;
Therefore , C alone takes 48 days to finish the job.

Sekar, Pradeep and Sandeep can do a piece of work in 15 days. After all the three worked for 2 days, sekar left. Pradeep and Sandeep worked for 10 more days and Pradeep left. Sandeep worked for another 40 days and completed the work. In how many days can sekar alone complete the work if sandeep can complete it in 75 days?
  • a)
    25 days
  • b)
    20 days
  • c)
    30 days
  • d)
    35 days
  • e)
    15 days
Correct answer is option 'C'. Can you explain this answer?

Assume the total work to be 600 units. (LCM of all the numbers) Then Sandeep’s 1 day work = 8 units.
All three’s 1 day work = 40 units.All work together in the first 2 days
Work done in the first 2 days = 40 × 2 = 80 units
Sandeep alone works during the last 40 days
Work done in the last 40 days = 40 × 8 = 320 units
Remaining work = 600 – (320 + 80) = 200 units
This work is done by pradeep and sandeep in 10 days.
Pradeep and Sandeep together’s 1 day work = 20 units
Sekar’s 1 day work = All three 1 day work – Pradeep and Sandeep together’s 1 day
work = 40 units – 20 units = 20 units
Sekar can do the work of 600 units in 30 days.

Arun can do a certain work in the same time in which Bipasha and Rahul together can do it. If Arun and Bipasha together could do it in 10 days and Rahul alone in 50 days, then Bipasha alone could do it in:
  • a)
    15 days
  • b)
    20 days
  • c)
    25 days
  • d)
    30 days
  • e)
    35 days
Correct answer is option 'C'. Can you explain this answer?

Kavya Saxena answered
Arun, Bipasha and rahul’s 1 day work = 1/10 + 1/50 = 6/50 = 3/25
Arun’s 1 day work = Bipasha + Rahul ‘s 1 day work
2*(Arun’s 1 day work) = 3/25
Arun’s 1 day work = 3/50
Bipasha’s 1 day work = 1/10 – 3/50 = 2/50 = 1/25

Efficiency of A is 25% more then B and B takes 25 days to complete a piece of work. A started a work alone and then B joined her 5 days before actual completion of the work. For how many days A worked alone?
  • a)
    9
  • b)
    11
  • c)
    10
  • d)
    25
  • e)
    12
Correct answer is option 'B'. Can you explain this answer?

Efficiency (A : B) = 5 : 4
Number of days(A : B) = 4x : 5x = 4x : 25
∴ Number of days required by A to finish the work alone = 4x
= 4 x 5 = 20.
A and B work together for last 5 days = 5 x 9 = 45%
Efficiency of A = 5% and B’s efficiency = 4%
∴ No. of days taken by A to complete 55% work = 55/5 = 11days

If P can do 1/3 of the work in 5 days and Q can do 1/4 of the work in 6 days, then how much money will Q get if they were paid a total of 390 rupee?
  • a)
    120
  • b)
    150
  • c)
    170
  • d)
    190
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?

sol = P can alone complete the whole work in 15 days and Q can complete the same work alone in 24 days. So ratio of work done by them 1/15: 1/24 i.e. 8: 5
Q get = (5/13)*390 = 150

Angel can do a piece of work in 10 days, Balu in 15 days. They work together for 5 days, the rest of the work is finished by Chitra in two more days. If they get Rs. 6000 as wages for the whole work, what are the daily wages of Angel, Bala and Chitra respectively?
  • a)
    200, 250, 300
  • b)
    300, 200, 250
  • c)
    600, 400, 200
  • d)
    600, 400, 500
  • e)
    None of these
Correct answer is option 'D'. Can you explain this answer?

Angel’s 5 days work = 50%
Balu’s 5 days work = 33.33%
Chitra’s 2 days work = 16.66%
[100- (50+33.33)]
Ratio of work of Angel, Balu and Chitra = 3: 2: 1
Angel’s total share = Rs. 3000
Balu’s total share = Rs. 2000
Chitra’s total share = Rs. 1000
Angel’s one day’s wage = Rs.600
Balu’s one day’s wage = Rs.400
Chitra’s one day’s wage = Rs.500

Ravi can do a piece of work in 16 days. Rakesh can do the same work in 64/5 days, while Geeta can do it in 32 days. All of them started to work together but Ravi leaves after 4 days. Rakesh leaves the job 3 days before the completion of the work. How long would the work last?
  • a)
    6 days
  • b)
    9 days
  • c)
    18 days
  • d)
    5 days
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?

Kavya Saxena answered
Let the work lasted for x days,
Ravi’s 4 day’s work + Rakesh (x – 3) day’s work + Geeta’s x day’s work = 1
⇒ (4/16) + (x – 3) / (64/5) + x/32 = 1
⇒ 5(x – 3)/64 + x/32 = 1 – 1/4
⇒ [5(x – 3) + 2x] / 64 = 3/4
⇒ 7x – 15 = 48
∴ x = (48 + 15)/7 = 63/7 = 9 days

A does half as much work as B does in one sixth of the time. If together they take 20 days to complete the work, then what is the time taken by A to complete the work independently.
  • a)
    80/3 days
  • b)
    100/3 days
  • c)
    60/3 days
  • d)
    140/3 days
  • e)
    None of these
Correct answer is option 'A'. Can you explain this answer?

Faizan Khan answered
Let B complete the work in X days so in one day work done by B is 1/x
as A do half work in one-sixth of the time so A will complete work in 2*x/6 = x/3 days
One day work of A and B i.e. 3/x + 1/x = 1/20. So we get x = 80
So time taken by A alone = 80/3 days

(x-2) person can do a work in x days and (x+7) person can do 75% of the same work in (x-10)days. Then in how many days can (x+10) person finish the work?
  • a)
    27 days
  • b)
    12 days
  • c)
    25 days
  • d)
    18 days
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?

Aarav Sharma answered
Given:
(x-2) person can do a work in x days
(x+7) person can do 75% of the same work in (x-10) days

To find:
In how many days can (x+10) person finish the work?

Solution:
Let us assume that the work done is 1 unit.
So, (x-2) persons can do 1 unit of work in x days.
Hence, the work done by 1 person in 1 day = 1/(x(x-2))

(x+7) persons can do 75% of the same work in (x-10) days.
So, the work done by (x+7) persons in 1 day = 0.75/ (x-10)

Let the number of days required for (x+10) persons to complete the work be d.
So, the work done by (x+10) persons in 1 day = 1/d

Now, we know that the work done is the same in all the cases.
Hence, we can equate the work done by (x-2) persons to the work done by (x+7) persons and (x+10) persons.

(x-2)/x = 0.75/(x-10) = (x+10)/d

Solving for d, we get d = 12 days.

Hence, (x+10) persons can finish the work in 12 days.

Answer: Option B) 12 days

Ramu, Hari and Sanjay are three typists, who working simultaneously, can type 228 pages in four hours. In one hour, Sanjay can type as many pages more than Hari as Hari can type more than Ramu. During a period of five hours, Sanjay can type as many passages as Ramu can, during seven hours. How many pages does each of them type per hour?
  • a)
    16, 18, 22
  • b)
    14, 17, 20
  • c)
    15, 17, 22
  • d)
    15, 18, 21
  • e)
    16, 19, 22
Correct answer is option 'E'. Can you explain this answer?

Let Rohit, Harsh and Sanjeev can type x, y and z pages respectively in 1 h. Therefore, they together can type 4(x + y + z) pages in 4 h
∴ 4(x + y + z) = 228
⇒ x + y + z = 57 …..(i)
Also, z – y = y – x
i.e., 2y = x + z ……(ii)
5z = 7x ……(iii)
From Eqs. (i) and (ii), we get
3y = 57
⇒ y = 19
From Eq. (ii), x + z = 38
x = 16 and z = 22

Madhavan can finish a work in 5 hours. He invites Manohar and Manjima who can work 3/4th as fast as he can to join him. He also invites Mani and Mohan who can work only 1/5th as fast as he can to join him. If the five person team works the same job and they start together, how long will it take for them to finish the job?
  • a)
    50/97 days
  • b)
    87 days
  • c)
    50/29 days
  • d)
    78 days
  • e)
    62 days
Correct answer is option 'C'. Can you explain this answer?

Anaya Patel answered
Let the work be 100 units.
Madhavan’s 1 hour work = 100/5 = 20 units
Manohar and Manjima’s 1 day work = 3/4 × 20 = 15 units.
Mohan and Mani’s 1 day work = 1/5 × 20 = 4 units.
In one day all five of them can do = 20 + 15 + 15 + 4 + 4 = 58 units of work. Hence they can complete the work in 100/58 days.

Sruthi, Swetha and Swati together can cut 216 Apples of the same size in 3 hours. Number of Apples cut by Sruthi in 9 hours is same as the number of Apples cut by Swati in 7 hours. In one hour, Swati can cut as many Apples more than Swetha as Swetha can cut more than Sruthi.Then the number of Apples cut by Swetha in one hour?
  • a)
    21
  • b)
    24
  • c)
    27
  • d)
    29
  • e)
    None
Correct answer is option 'B'. Can you explain this answer?

Aruna Singh answered
 
Let's denote:
  • Sruthi's efficiency as 'S' apples/hour
  • Swetha's efficiency as 'W' apples/hour
  • Swati's efficiency as 'T' apples/hour
Given information:
  1. S * 9 = T * 7 => S = (7/9)T
  2. T - W = W - S => T = 2W - S
Total work done in 3 hours:
  • (S + W + T) * 3 = 216
  • S + W + T = 72
Substituting S and T in terms of W:
  • (7/9)T + W + 2W - (7/9)T = 72
  • 3W = 72
  • W = 24
Therefore, Swetha can cut 24 apples in one hour.
So, the correct answer is option B: 24.

When Ashok and Karthik are working alone, they can complete a piece of work in 25 days and 30 days respectively. On day 1, Karthik started the work and Ashok joined B from day 3 on-wards. Find approximately after how many days will the work be completed?
  • a)
    20 days
  • b)
    10 days
  • c)
    15 days
  • d)
    25 days
  • e)
    30 days
Correct answer is option 'C'. Can you explain this answer?

Aisha Gupta answered
Fraction of work completed by Karthik on day 1 and day 2 = 2* 1/30 = 1/15
Fraction of work left after 2 days = 14/15
Fraction of work completed by Both = 1/25 + 1/30 = 11/150
Number of days after day 2 to complete work = 14*150/15*11 = 13 days
So after 2+13 = 15 days works will be completed

A can do a piece of work in 20 days and B can do the same work in 30 days. In how many days can both finish the whole work working together?
  • a)
    10
  • b)
    12
  • c)
    15 
  • d)
    18
Correct answer is option 'B'. Can you explain this answer?

Pranab Goyal answered
Working together to finish a piece of work:
To determine how many days it will take for A and B to finish the work together, we need to calculate their combined work rate.

Work rate of A and B:
- A can finish the work in 20 days, so A's work rate = 1/20.
- B can finish the work in 30 days, so B's work rate = 1/30.

Combined work rate:
When A and B work together, their combined work rate is the sum of their individual work rates. Therefore, their combined work rate = 1/20 + 1/30 = 3/60 + 2/60 = 5/60 = 1/12.

Calculating the number of days to finish the work together:
To find out how many days it will take for A and B to finish the work together, we use the formula:
Number of days = Total work / Combined work rate
Since the total work is 1, and the combined work rate is 1/12, we have:
Number of days = 1 / (1/12) = 12 days.
Therefore, A and B will finish the whole work working together in 12 days, which corresponds to option B.

Sarthak can destroy a work in 90 days and Deepak can destroy the same work in 60 days. In how many days can both of them together destroy the work?
  • a)
    30
  • b)
    36
  • c)
    40
  • d)
    42
Correct answer is option 'B'. Can you explain this answer?

Malavika Rane answered
Understanding Individual Work Rates
Sarthak and Deepak have different work rates based on how many days they take to complete the same task.
- Sarthak's Work Rate:
- He can complete the work in 90 days.
- Work rate = 1/90 (work done per day)
- Deepak's Work Rate:
- He can complete the work in 60 days.
- Work rate = 1/60 (work done per day)
Combined Work Rate Calculation
To find out how quickly they can complete the work together, we add their individual work rates.
- Combined Work Rate:
- Combined work rate = Sarthak's rate + Deepak's rate
- Combined work rate = 1/90 + 1/60
Finding a Common Denominator
To add these fractions, we find a common denominator.
- Common Denominator of 90 and 60:
- The least common multiple (LCM) of 90 and 60 is 180.
- Converting Fractions:
- Sarthak's rate: (1/90) = 2/180
- Deepak's rate: (1/60) = 3/180
Final Calculation
Now we can add the two rates:
- Combined Rate:
- Combined work rate = 2/180 + 3/180 = 5/180
- Simplifying gives us 1/36.
Time to Complete Work Together
To find out how long it takes both of them to complete the work, we take the reciprocal of their combined work rate.
- Time Taken Together:
- Time = 1 / (1/36) = 36 days.
Thus, Sarthak and Deepak together can destroy the work in 36 days. Therefore, the correct answer is option 'B'.

Diya can complete a work in 80 days. In how many days can she complete it with 80% of her efficiency?
  • a)
    60
  • b)
    70
  • c)
    80
  • d)
    100
Correct answer is option 'D'. Can you explain this answer?

Ishaan Roy answered
Understanding Diya's Work Efficiency
Diya can complete a task in 80 days at her full efficiency. To determine how long it will take her to complete the same task at 80% of her efficiency, we need to understand the impact of efficiency on time taken.
Calculating Diya's Work Rate
- At full efficiency, Diya completes 1/80 of the work in a day.
- This means she completes 1 unit of work in 80 days.
Adjusting for 80% Efficiency
- 80% of her efficiency means she is now completing only 80% of her usual daily work.
- Thus, her new work rate will be:
- (1/80) * 80% = 1/100 per day.
Finding the New Time Required
- If Diya completes 1/100 of the work in a day, we can determine how many days it will take her to complete the entire work:
- Total work = 1 unit.
- Days required = Total work / New daily work rate = 1 / (1/100) = 100 days.
Conclusion
- Therefore, at 80% efficiency, Diya will take 100 days to complete the work.
The correct answer is option D: 100 days.

A, B and C together can complete a work in 8 days. If A is 50% more efficient than B and B is 50% less efficient than C, then B alone will complete the same work in:
  • a)
    16 days
  • b)
    24 days
  • c)
    48 days
  • d)
    36 days
  • e)
    None of these
Correct answer is option 'D'. Can you explain this answer?

Mihir Chawla answered
Solution:

Let's assume that C can complete the work in x days.

Efficiency of B compared to C:
B is 50% less efficient than C. This means B can complete only half the work that C can complete in the same time. So, B can complete the work in 2x days.

Efficiency of A compared to B:
A is 50% more efficient than B. This means A can complete 1.5 times the work that B can complete in the same time. So, A can complete the work in (2x/1.5) days.

Efficiency of A, B, and C together:
Given that A, B, and C together can complete the work in 8 days. So, their combined efficiency is 1/8 of the work per day.

Let's calculate their combined efficiency:
1/A + 1/B + 1/C = 1/8

Substituting the values of A, B, and C:
1/(2x/1.5) + 1/2x + 1/x = 1/8

Taking the LCM and simplifying the equation:
[(1.5 + 3 + 4)/2x] = 1/8
8/2x = 1/8
2x = 64
x = 32

So, C alone can complete the work in 32 days.

Now, let's find out how many days B alone will take to complete the work:
B can complete the work in 2x days.
Substituting the value of x:
B can complete the work in 2(32) = 64 days.

Therefore, the correct answer is option D) 36 days.

Manoj can complete 75% of a work in 90 days. In how many days can he complete 80% of that work with his full efficiency?
  • a)
    60
  • b)
    72
  • c)
    80
  • d)
    96
Correct answer is option 'D'. Can you explain this answer?

Pranab Goyal answered
Understanding the Problem
Manoj can complete 75% of a work in 90 days. We need to calculate how many days he would take to complete 80% of the same work.
Calculating Work Rate
- If 75% of the work takes 90 days, we can find the total amount of work in days.
- The full work (100%) would take:
- (90 days / 75%) = 90 days * (100/75) = 120 days.
Daily Work Output
- Manoj’s work rate can be computed as follows:
- Total work = 1 (100% of the work).
- Daily work output = 1 work / 120 days = 1/120 work per day.
Calculating Time for 80% of Work
- To find the time taken to complete 80% of the work:
- Work to be done = 80% of the total work = 0.8.
- Time required = Work to be done / Daily work output = 0.8 / (1/120) = 0.8 * 120 = 96 days.
Final Answer
- Therefore, Manoj can complete 80% of the work in 96 days.
The correct option is D) 96.

Chapter doubts & questions for Time and Work - Quantitative Aptitude for SSC CGL 2026 is part of SSC CGL exam preparation. The chapters have been prepared according to the SSC CGL exam syllabus. The Chapter doubts & questions, notes, tests & MCQs are made for SSC CGL 2026 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests here.

Chapter doubts & questions of Time and Work - Quantitative Aptitude for SSC CGL in English & Hindi are available as part of SSC CGL exam. Download more important topics, notes, lectures and mock test series for SSC CGL Exam by signing up for free.

Top Courses SSC CGL