GATE Architecture and Planning Exam  >  GATE Architecture and Planning Tests  >  GATE Architecture and Planning 2025 Mock Test Series  >  GATE Architecture and Planning Mock Test - 1 - GATE Architecture and Planning MCQ

GATE Architecture and Planning Mock Test - 1 - GATE Architecture and Planning MCQ


Test Description

30 Questions MCQ Test GATE Architecture and Planning 2025 Mock Test Series - GATE Architecture and Planning Mock Test - 1

GATE Architecture and Planning Mock Test - 1 for GATE Architecture and Planning 2024 is part of GATE Architecture and Planning 2025 Mock Test Series preparation. The GATE Architecture and Planning Mock Test - 1 questions and answers have been prepared according to the GATE Architecture and Planning exam syllabus.The GATE Architecture and Planning Mock Test - 1 MCQs are made for GATE Architecture and Planning 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for GATE Architecture and Planning Mock Test - 1 below.
Solutions of GATE Architecture and Planning Mock Test - 1 questions in English are available as part of our GATE Architecture and Planning 2025 Mock Test Series for GATE Architecture and Planning & GATE Architecture and Planning Mock Test - 1 solutions in Hindi for GATE Architecture and Planning 2025 Mock Test Series course. Download more important topics, notes, lectures and mock test series for GATE Architecture and Planning Exam by signing up for free. Attempt GATE Architecture and Planning Mock Test - 1 | 65 questions in 180 minutes | Mock test for GATE Architecture and Planning preparation | Free important questions MCQ to study GATE Architecture and Planning 2025 Mock Test Series for GATE Architecture and Planning Exam | Download free PDF with solutions
GATE Architecture and Planning Mock Test - 1 - Question 1

The second figure in the first part of the problem figures bears certain relationship to the first figure. Similarly, one of the figures of answer figures bear the same relationship to the first figure of the second part. You have to select a figure from the set of answer figures which would replace the question mark (?)

Problem Figures

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 1

All elements are moving 90° angle towards clockwise in first pair of problem figure. Same kind of rule will be followed in second problem figures pair.

GATE Architecture and Planning Mock Test - 1 - Question 2

The value of is,

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 2

Given Expression =  

1 Crore+ students have signed up on EduRev. Have you? Download the App
GATE Architecture and Planning Mock Test - 1 - Question 3

The symbols Ο, ✱, △, and □ are to be filled, one in each box, as shown below. The rules for filling in the four symbols are as follows.  

  1. Every row and every column must contain each of the four symbols.  
  2. Every 2×2 square delineated by bold lines must contain each of the four symbols.  

Which symbol will occupy the box marked with ‘?’ in the partially filled figure?

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 3

In the first 2×2 square (left-most top) delineated by bold lines, the two boxes highlighted below are not suitable for ✱ 

So, the suitable box for ✱ will be❓
The solved puzzle will be as follows: 

GATE Architecture and Planning Mock Test - 1 - Question 4

Planting : Seed : : Raising : _____ (By word meaning)

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 4

Planting a seed is analogous to ‘raising a child’

GATE Architecture and Planning Mock Test - 1 - Question 5

Consider the following inequalities:  
p2 - 4q < 4
3p + 2q < 6
Where p and q are positive integers.
The value of (p + q) is ______ 

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 5

It is mentioned that p and q are positive integers. The least positive integer is 1. The second inequality holds true only if both p and q are 1. So, the value of (p + q) is 2 

GATE Architecture and Planning Mock Test - 1 - Question 6

An opaque pyramid (shown below), with a square base and isosceles faces, is suspended in the path of a parallel beam of light, such that its shadow is cast on a screen oriented perpendicular to the direction of the light beam. The pyramid can be reoriented in any direction within the light beam. Under these conditions, which one of the shadows P, Q, R, and S is NOT possible? 

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 6

Q is not a possible shadow as the pyramid tip doesn’t connect to all four corners of the base.

GATE Architecture and Planning Mock Test - 1 - Question 7

Which one of the sentence sequences in the given options creates a coherent narrative?
(i) I could not bring myself to knock.  
(ii) There was a murmur of unfamiliar voices coming from the big drawing room and the door was firmly shut.  
(iii) The passage was dark for a bit, but then it suddenly opened into a bright kitchen.  
(iv) I decided I would rather wander down the passage.

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 7

As point (iv) uses the word ‘rather wander down the passage’ it can be inferred that it comes after point (i) which states an alternative option – which is ‘knocking the door’. As point (iv) mentions the decision to walk down the passage, point (iii) should be the next point as it describes the passage.

GATE Architecture and Planning Mock Test - 1 - Question 8

As per National building code, the height of a kitchen shall not be less than ____

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 8

As per National building code the height of a kitchen shall not be less than 2.75 m.Size: kitchen with separate dining area shall not be less than 5 m2, with minimum width of 1.8m. kitchen with dining area shall not be less than 7.5 m2, with minimum width of 2.1 m.

GATE Architecture and Planning Mock Test - 1 - Question 9

As per the Burra Charter (2013) ‘Cultural Significance’ means __________ for past, present or future generations.  

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 9

Some important definitions from Article 1 of Burra Charter are listed below:

  • Place means a geographically defined area. It may include elements, objects, spaces and views. Place may have tangible and intangible dimensions.
  • Cultural significance means aesthetic, historic, scientific, social or spiritual value for past, present or future generations. Cultural significance is embodied in the place itself, its fabric, setting, use, associations, meanings, records, related places and related objects.
  • Fabric means all the physical material of the place including elements, fixtures, contents and objects. Conservation means all the processes of looking after a place so as to retain its cultural significance.
  • Maintenance means the continuous protective care of a place, and its setting. Maintenance is to be distinguished from repair which involves restoration or reconstruction.
  • Preservation means maintaining a place in its existing state and retarding deterioration.
  • Restoration means returning a place to a known earlier state by removing accretions or by reassembling existing elements without the introduction of new material.
  • Reconstruction means returning a place to a known earlier state and is distinguished from restoration by the introduction of new material.
  • Adaptation means changing a place to suit the existing use or a proposed use.  
GATE Architecture and Planning Mock Test - 1 - Question 10

In eighteenth century English gardens, __________was used to eliminate visual boundaries between the garden and the landscape.  

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 10

The sunken fence, fosse, or ha-ha, is an English invention, used in separating that portion of the lawn near the house, from the part grazed by deer or cattle, and is only a ditch sufficiently wide and deep to render communication difficult on opposite sides. When the ground slopes from the house, such a sunk fence is invisible to a person near the latter and answers the purpose of a barrier without being in the least obtrusive. 

GATE Architecture and Planning Mock Test - 1 - Question 11

Select the option(s) which is/are NOT considered as primary air pollutant(s).  

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 11

AQI will consider eight pollutants (PM10, PM2.5, NO2, SO2, CO, O3, NH3, and Pb) for which short-term (up to 24-hourly averaging period) National Ambient Air Quality Standards are prescribed. VOCs in air pollution are also a concern because they contribute to the formation of groundlevel ozone when they react with nitrogen oxides in the air. 

GATE Architecture and Planning Mock Test - 1 - Question 12

The figure below shows the spatial arrangement of rooms in a building with access from the exterior, marked as ‘entry’. Identify the appropriate diagram showing the access to rooms starting from the entry.

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 12

By observation, there should be continuous link from Entry to ‘A’ and then to ‘B’. Link from A to B can be seen only in Option B and the remaining options can be directly eliminated.

GATE Architecture and Planning Mock Test - 1 - Question 13

Select the Act which stipulates prohibited area of 100 m around centrally protected monuments in India.  

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 13

National Monuments Authority has been established under the provisions of ‘The Ancient Monuments and Archaeological Sites and Remains (Amendment and Validation) Act, 2010'. The minimum prohibited area in respect of centrally protected monuments and protected areas is 100m, in all directions beginning at the limit of the protected area of the centrally protected monument or site. The minimum limit of regulated area of centrally protected monuments and protected areas is 200m which will begin from the limit of the prohibited area. These limits area extendable as per the classification of the centrally protected monuments and protected areas on the recommendation of the National Monuments Authority. 

*Answer can only contain numeric values
GATE Architecture and Planning Mock Test - 1 - Question 14

Full sunlight is falling on a 18% efficiency solar cell of area 3 m² at an angle of incidence of 60 degrees to the normal to the cell. What is the output power (in Watts) of the cell?


Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 14

The projected area of the cell normal to the direction of the sunlight is 3 x cos 60 = 1.5 m². The cell's efficiency is 18% and full sunlight has an intensity of 1000 W/m2, so the output power is 0.18 x 1000 x 1.5 = 270 W.

*Answer can only contain numeric values
GATE Architecture and Planning Mock Test - 1 - Question 15

Calculate the quantity of air required (in cum per minute) to remove 400 p.p.m of B.O.D from 10 million litres of sewage per day.


Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 15

With respect to the B.OD. removal, the usual rate adopted is 30 m³ of air per million litres for each Op.p.m of B.O.D. to be removed.

Quantity of air required = 30 x 10 x 400 = 120,000 cum per day = 83.33 cum per minute.

*Answer can only contain numeric values
GATE Architecture and Planning Mock Test - 1 - Question 16

The normal duration and normal cost of activity are 28 days and Rs. 55,000 respectively. The activity crash duration is 24 days and the indirect cost is Rs. 1,000 per day. If the cost slope is Rs. 1,500 per day, then the total cost of the activity (in rupees) after the crashing will be ______.


Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 16

Indirect project Cost:

Indirect project cost are those expenditures which cannot be clearly allocated to the individual activities of the project, but are assessed as a whole.

The indirect cost rises with an increase in duration. 

Direct Project Cost: 

These include labour cost, material cost, equipment cost, etc.

Direct cost decreases with an increase in duration.

Cost slope:

The cost slope is the slope of the direct cost curve, approximated as straight line. It is defined as follows:

cost slope=Crash cost−Normal cost / (Normal time−Crash time)

Cs = Cc − Cn/(tn − tc) = ΔC/Δt

Where, Cs = Cost slope, ΔC = Increase in cost, Δt = Decrease in time

Calculation

Given data,

Normal activity duration = 28 days

Crash activity duration = 24 days

Cost slope = 1500/- , Indirect cost = 1000/- per day

Normal cost of activity = 55,000 /-

No. of days crashed = 28 - 24 = 4 days. 

The increase in direct cost for 4 days crashing = Cost Slope × 4 = 1500×4 = 6000 rupees

The decrease in indirect cost for 4 days = 1000×4 = 4000 rupees

Total project cost = Direct cost + Indirect cost

The total cost of the activities after crashing

= 55000 + 6000 – 4000 = 57000 rupees

∴ Total cost = 57,000 /-

GATE Architecture and Planning Mock Test - 1 - Question 17

In a construction project, generally 50% of total project cost is attributed to

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 17

The rate analysis is the determination of the rate of a particular item of construction per unit. The various factors affecting the rate analysis are:

1. Materials required for Rate Analysis:

Almost 50 % of the total cost of any work is due to the materials themselves.  

The quantity of the materials either more or less, both affects the rate analysis. Hence one should maintain the proper quantity of materials on the site.

2. Manpower requirement:

About 30 % of the total cost of the work is due to the cost of manpower.

 The selection of the workforce should be done according to their categories like skilled, semi-skilled, and unskilled and their wages should also be decided according to their class.

3. Item specification:

The specification of the items indicates the proportion of materials, the process, and the work method.  

4. Tools and Plants:

They are decided on various factors such as duration of work, labor requirement, the budget of work, type of work, etc.    

5. Overhead Charges:

Overhead charges include expenses of office, labour welfare, material testing, water supply, electrification, depreciation amount etc.

This is usually considered as 2-5 % of the total cost of the work.

6. Contractor’s Profit:

Typically 10 to 15 % of the overall cost of the work is considered to be the contractor’s profit.

GATE Architecture and Planning Mock Test - 1 - Question 18

In a colour wheel, Orange and Violet colours are

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 18

GATE Architecture and Planning Mock Test - 1 - Question 19

Promoted by the UN, Sustainable Development Goal 10 Focuses on:

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 19

 

*Multiple options can be correct
GATE Architecture and Planning Mock Test - 1 - Question 20

Which of the following are a part of the four principles of Ekistics?

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 20

Ekistics is the science of human settlements including regional, city, community planning and dwelling design. Its major incentive was the emergence of increasingly large and complex conurbations, tending even to a worldwide city.

Doxiadis defines 4 principles of Ekistics for solving the problems of human settlements:

(1) Unity of Purpose

(2) Hierarchy of functions (All functions should belong to a pyramid set in a hierarchical way)

(3) Four-dimensional synthesis

(4) Many masters creating many scales

*Multiple options can be correct
GATE Architecture and Planning Mock Test - 1 - Question 21

Which of the following is part of the Ekistics Logarithmic Scale (ELS)

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 21
  • A classification of settlements according to their size, presented on the basis of a logarithmic scale, running from Anthropos (ekistic unit 1), as the smallest unit of measurement, to the whole earth (ekistic unit 15).
  • Ecumenopolis: Term coined by C.A. Doxiadis from the Greek words ecumene, that is, the total inhabited area of the world, and polis, or city, in the broadest sense of the word. It means the coming city that will - together with the corresponding open land, which is indispensable for Anthropos - cover the entire earth as a continuous system forming a universal settlement.
  • House and house group: These terms replace "dwelling" and "dwelling group," which corresponded to ekistic units 3 and 4, with a population of four and 40 people respectively.
*Answer can only contain numeric values
GATE Architecture and Planning Mock Test - 1 - Question 22

The annual precipitation recorded in a town is 400 mm. Rainwater is being collected from the flat roof of a building, and then treated to potable standards, and stored. Water loss due to evaporation, transmission and treatment is 40 percent of the total harvested volume. The roof area is 500 sq.m. There are 3 occupants, with average daily water demand as 200 lpcd. The stored rainwater will be adequate for the household’s daily use for ________ days [in integer]. 


Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 22

Loss of water = 40%. So run-off coefficient = 0.6
Volume of stored water from runoff = C*i*A = 0.6 * 0.4 m * 500 sqm = 120 cu.m  
Daily water demand of the household = 3*200 = 600 liters = 0.6 cu.m
No. of days the stored water will be adequate for = 120/0.6 = 200 days 

*Answer can only contain numeric values
GATE Architecture and Planning Mock Test - 1 - Question 23

A residential housing project is designed in a plot measuring 1 hectare. The car parking area is equally distributed between the ground floor and the basement. Considering the data given below, the number of cars accommodated in the basement will be______________ [in integer].  
Data:  
FAR consumed = 2.0  
Car parking area is exempted from built up area for FAR calculations.  
One car parking to be given for each 100 sq.m of built-up area.  
Area required for accommodating each car in ground floor = 15 sq.m  
Area required for accommodating each car in basement = 25 sq.m 


Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 23

Total built-up area = Plot area * FAR = 10,000 sqm * 2 = 20,000 sqm
Number of car parking required = 20,000/100 = 200 cars
Let parking area on ground floor = ‘x’ and parking area on basement level = ‘y’. Given, x = y
Number of cars on ground floor = x/15 and Number of cars on basement level
= y/25  (x/15) + (y/25) = 200
⇒ (5y + 3y)/75 = 200
⇒ 8y = 200*75
⇒ Area of parking on basement level, y = 1875 sqm 
Number of cars that can be accommodated on basement level = 1875/25 = 75 

*Answer can only contain numeric values
GATE Architecture and Planning Mock Test - 1 - Question 24

If the excavation of earth is done manually then it costs Rs. 120 per cum. A machine can excavate at a fixed cost of Rs. 40,000 plus a variable cost Rs. 20 per cum. The quantity of the earth (in cum) for which the cost of excavation by machine will be equal to the cost by manual excavation is _________.


Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 24

Let the total quantity for excavation is x cum

Cost of excavation of earth if done manually = Rs. 120 per cum

The total cost of excavation of ‘A’ cum earth if done manually, Ch = Rs. 120 × A cum

Cost of excavation by Machine, Cm = Fixed cost + variable cost                     

Cm = 40000 + 20 × A

It is given that cost of excavation by machine will be equal to the cost of manual excavation is

i.e. Ch = Cm

120 × A= 40000 + 20 × A

On solving, we get A = 400 cum

The total quantity for excavation is 400 cum

GATE Architecture and Planning Mock Test - 1 - Question 25

What is the other name for the typical Rose window, i.e. a circular window, especially used for those found in Gothic cathedrals and churches?

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 25

The rose (rosette) window is the shape of the openwork bay in the wall, while rose is the name of stained glass. A large circle of glass piercing a wall supporting tons of stone is characteristically Gothic architectural feat. It is accomplished by crisscrossing the opening with a visually delicate but structurally strong web of stone, which breaks the glass into smaller shapes in a symmetrical way, distributing weight equally across the circle.

GATE Architecture and Planning Mock Test - 1 - Question 26

The proportion of the sides of a traditional Japanese tatami mat is _______.  

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 26

A tatami is a type of mat used as a flooring material in traditional Japanese-style rooms. Tatamis are made in standard sizes, twice as long as wide, about 0.9 m by 1.8 m depending on the region. 

*Answer can only contain numeric values
GATE Architecture and Planning Mock Test - 1 - Question 27

For a beam of cross-section, width = 230 mm and effective depth = 450 mm, the number of rebars of 12 mm diameter required to satisfy minimum tension reinforcement requirement specified by IS: 456 - 2000 (assuming grade of steel reinforcement as Fe500) is


Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 27

Minimum tension reinforcement:

Ast min/(b × d)=0.85/fy

Where,

Ast min = Minimum tension reinforcement, b = width of the beam, d = depth of the beam, fy = yield strength of the steel

Calculation:

Given, b = 230 mm, d = 500 mm, Dia of bars = 12 mm, fy = 500 N/mm2

Ast min/(b × d) = 0.85/fy

Ast min = (0.85 × b × d)/fy

Ast min = (0.85 × 230 × 450)/500

Ast min = 175.95 mm2

Number of rebars = 175.95/(π(122/4)) = 175.95/113.0973

Number of rebars = 1.5557 = 2

GATE Architecture and Planning Mock Test - 1 - Question 28

A white, powdery deposit that forms on an exposed masonry or concrete surface, caused by leaching and crystallization of soluble salts from within the material is

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 28

Efflorescence is a deposit of salts, usually white, formed on a surface, the substance having emerged in solution from within either concrete or masonry and subsequently precipitated by evaporation. It occurs most readily in porous concrete near the surface.

GATE Architecture and Planning Mock Test - 1 - Question 29

Which of the instrument that measures the volume and the density of solid objects in a non-destructive manner

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 29

A pycnometer is a common science equipment found in laboratories. It is used to measure the density or rather volume of solids. It uses an inert gas such as helium or nitrogen. Hence, sometimes it is also known as helium pycnometer. A pycnometer can measure solids that are porous/non-porous, regularly shaped, granular, powdered, monolithic and even comminuted.
This laboratory equipment is based on Boyle’s Law which determines the volume-pressure relationship.

GATE Architecture and Planning Mock Test - 1 - Question 30

An excess amount of which of these components in clay may cause the bricks to shrink, warp or crack on drying and burning?

Detailed Solution for GATE Architecture and Planning Mock Test - 1 - Question 30

Alumina is the main constituent of clay. It acts as a cementing material in raw brick. Brick clay is plastic due to the presence of alumina. This plasticity ensures that bricks can be molded. An excess amount of alumina in clay may cause the bricks to shrink, warp or crack on drying and burning as any other cementing material.
brick composition: -
1) silica- silica is about 50 to 60% of dry weight of bricks
2) Alumina is about 20 to 30% of dry weight of bricks
3) lime is about 10 to 12% dry weight of bricks
4) ferric oxide is about less than 7% of dry weight of bricks
5) magnesia is about less than 1% of dry weight of bricks
6) Alkalies is about less than 10% of dry weight of bricks.

View more questions
10 tests
Information about GATE Architecture and Planning Mock Test - 1 Page
In this test you can find the Exam questions for GATE Architecture and Planning Mock Test - 1 solved & explained in the simplest way possible. Besides giving Questions and answers for GATE Architecture and Planning Mock Test - 1, EduRev gives you an ample number of Online tests for practice
Download as PDF