Earliest Date = 20 weeks
Latest Date = 40 weeks
Activity E is connecting both the events and its duration is 10 weeks. The independent float of the activity is
The network rules are common to ail activity on- arrow networking systems. The use of computers for making computations may impose certain rules. Which of the following basic rules of network logic are correct?
1. Before an activity may beg in, all the activities preceding it must be complete.
2. Any two events may be directly connected by not more than one activity.
3. Event numbers must not be duplicated in a network.
Select the correct answer using the codes given below:
1 Crore+ students have signed up on EduRev. Have you? Download the App |
Match List-I (Item) and with List-ll (Characteristic) and select the correct answer using the codes given below the lists:
Codes:
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and some times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be
Consider the following statements:
1. A dummy activity is artificially introduced in a network when necessary,
2. A dummy activity consumes some time.
3. A dummy activity is represented by a dotted arrow.
4. A dummy activity must necessarily be introduced in every network.
Which of the above statements are correct?
Match List-I (Activity type) with List-ll (Representation by) and select the correct answer using the codes given below the lists:
Codes:
With reference to the network shown in figure, which statement is incorrect?
Figure shows the network for a particular project which consists of four activities.
Normal duration time and crash time for each activity are given below:
The minimum time required for the completion of project is
Consider the following statements:
1. Tests on cement paste to determine initial and final setting times are done at normal consistency condition.
2. Low heat cement has a high percentage of tricalcium aluminate.
3. High early strength Portland cement contains a larger percentage of tricafcium silicate and a lower percentage of dicalcium silicate.
Which of these statements are correct?