Civil Engineering (CE) Exam  >  Civil Engineering (CE) Tests  >  Environmental Engineering  >  Test: Design Of Activated Sludge Plant - Civil Engineering (CE) MCQ

Test: Design Of Activated Sludge Plant - Civil Engineering (CE) MCQ


Test Description

10 Questions MCQ Test Environmental Engineering - Test: Design Of Activated Sludge Plant

Test: Design Of Activated Sludge Plant for Civil Engineering (CE) 2024 is part of Environmental Engineering preparation. The Test: Design Of Activated Sludge Plant questions and answers have been prepared according to the Civil Engineering (CE) exam syllabus.The Test: Design Of Activated Sludge Plant MCQs are made for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Design Of Activated Sludge Plant below.
Solutions of Test: Design Of Activated Sludge Plant questions in English are available as part of our Environmental Engineering for Civil Engineering (CE) & Test: Design Of Activated Sludge Plant solutions in Hindi for Environmental Engineering course. Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free. Attempt Test: Design Of Activated Sludge Plant | 10 questions in 25 minutes | Mock test for Civil Engineering (CE) preparation | Free important questions MCQ to study Environmental Engineering for Civil Engineering (CE) Exam | Download free PDF with solutions
Test: Design Of Activated Sludge Plant - Question 1

Which of the following is the correct expression of the aeration period in hours?

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 1

Explanation: Aeration period = 24V/Q where, V is the volume of the tank and Q is the quantity of sewage. It is measured in hours.

Test: Design Of Activated Sludge Plant - Question 2

 Which of the following activated sludge process has minimum food to microorganism ratio?

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 2

Explanation: Extended aeration process has minimum food to microorganism ratio of 0.5 which means it has the maximum BOD removal efficiency.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Design Of Activated Sludge Plant - Question 3

The maximum aeration period for a conventional activated sludge system is

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 3

Explanation: The detention period for a conventional activated sludge system is between 4 to 6 hours.

Test: Design Of Activated Sludge Plant - Question 4

 The organic loading in an activated sludge plant is defined as

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 4

Explanation: The organic loading in an activated sludge plant is defined as the mass of BOD to the aeration tank in grams per unit volume of aeration tank in m3.

Test: Design Of Activated Sludge Plant - Question 5

_________ is defined as a volume in ml occupied by 1gram of solid in the mixed liquor after 30 minutes of settling.

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 5

Explanation: Sludge volume index is used to indicate the settling behavior of sludge. It is measured in ml/gm.

Test: Design Of Activated Sludge Plant - Question 6

 The design value of food to microorganism ratio in the tapered aeration sludge process is

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 6

Explanation: The design value of food to microorganism ratio is 0.3-0.4 for a tapered aeration sludge process.

Test: Design Of Activated Sludge Plant - Question 7

Which of the following sludge process has maximum aeration period?

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 7

Explanation: Extended process has the maximum aeration period of 12 to 24 hours.

Test: Design Of Activated Sludge Plant - Question 8

The maximum BOD removal efficiency of the Step aeration process of the activated sludge system is

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 8

Explanation: The BOD removal efficiency of the step aeration process of the activated sludge system is between 85% to 92%.

Test: Design Of Activated Sludge Plant - Question 9

 _________ is the time at which sewage is detained in the aeration tank.

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 9

Explanation: Aeration period decides the loading rate at which sewage is introduced in the aeration tank.

Test: Design Of Activated Sludge Plant - Question 10

Which of the following has minimum hydraulic retention time?

Detailed Solution for Test: Design Of Activated Sludge Plant - Question 10

Explanation: Modified aeration process has a minimum hydraulic retention time with an aeration period of 1.5 hours.

14 videos|99 docs|98 tests
Information about Test: Design Of Activated Sludge Plant Page
In this test you can find the Exam questions for Test: Design Of Activated Sludge Plant solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Design Of Activated Sludge Plant, EduRev gives you an ample number of Online tests for practice

Top Courses for Civil Engineering (CE)