Civil Engineering (CE) Exam  >  Civil Engineering (CE) Tests  >  Civil Engineering SSC JE (Technical)  >  Test: Estimation and Costing - Civil Engineering (CE) MCQ

Test: Estimation and Costing - Civil Engineering (CE) MCQ


Test Description

10 Questions MCQ Test Civil Engineering SSC JE (Technical) - Test: Estimation and Costing

Test: Estimation and Costing for Civil Engineering (CE) 2024 is part of Civil Engineering SSC JE (Technical) preparation. The Test: Estimation and Costing questions and answers have been prepared according to the Civil Engineering (CE) exam syllabus.The Test: Estimation and Costing MCQs are made for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Estimation and Costing below.
Solutions of Test: Estimation and Costing questions in English are available as part of our Civil Engineering SSC JE (Technical) for Civil Engineering (CE) & Test: Estimation and Costing solutions in Hindi for Civil Engineering SSC JE (Technical) course. Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free. Attempt Test: Estimation and Costing | 10 questions in 30 minutes | Mock test for Civil Engineering (CE) preparation | Free important questions MCQ to study Civil Engineering SSC JE (Technical) for Civil Engineering (CE) Exam | Download free PDF with solutions
Test: Estimation and Costing - Question 1

In the cubical contents method, the cost of a structure is computed by the multiplication of total cubic contents and _______

Detailed Solution for Test: Estimation and Costing - Question 1

The cost of a structure in the cubical contents method is determined by the multiplication of total cubic contents with the local cubic rate. Therefore, the cost of the building is calculated by multiplying the volume of buildings with the rate per unit volume.

Test: Estimation and Costing - Question 2

As per IS 3861-1966, which of the following areas should not be included while calculating the plinth area of a building?

Detailed Solution for Test: Estimation and Costing - Question 2

As per IS 3861-1966, the areas which should be included while calculating the plinth area of a building are porches of non-cantilever type, area of barsati at terrace level, area of walls at floor level, etc. However, the area of lofts should not be included.

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Estimation and Costing - Question 3

Which of the following is not a method used for preparing approximate estimates?

Detailed Solution for Test: Estimation and Costing - Question 3

There are various methods used for preparing approximate estimates. These are the plinth area method, unit base method and cubical contents method. An approximate estimate is needed for studying various aspects of the work of the project.

Test: Estimation and Costing - Question 4

While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per _____

Detailed Solution for Test: Estimation and Costing - Question 4

While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per the Standard Data Book. However, the rates of labour and materials are obtained from the current standard scheduled of rates.

Test: Estimation and Costing - Question 5

Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the execution of the work.

Detailed Solution for Test: Estimation and Costing - Question 5

Estimating is the process of calculating the various quantities and their cost in the building construction. It is needed for controlling the expenditure during the execution of the work.

Test: Estimation and Costing - Question 6

For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.

Detailed Solution for Test: Estimation and Costing - Question 6

For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method. Cubical contents method is usually used for multi-storeyed buildings.

Test: Estimation and Costing - Question 7

In the plinth area method, the cost of construction is computed by the multiplication of ________

Detailed Solution for Test: Estimation and Costing - Question 7

In the plinth area method, the cost of construction is computed by the multiplication of plinth area and plinth area rate. This area is calculated by multiplying the length and the breadth.

Test: Estimation and Costing - Question 8

In the case of works which require some special types of equipment, an amount of ______ percent of the estimated cost is given.

Detailed Solution for Test: Estimation and Costing - Question 8

In the case of works that require some special types of equipment, an amount of 1-2 percent of the estimated cost is given. While preparing a detailed estimate, it is also important to select a suitable site of work to reduce damage during the loading and unloading of materials.

Test: Estimation and Costing - Question 9

The process of working out the cost per unit of each item is known as ______

Detailed Solution for Test: Estimation and Costing - Question 9

The preparation of a detailed estimate comprises of working out quantities of different items of work and then determining the cost of each item. The process of working out the cost per unit of each item is known as data.

Test: Estimation and Costing - Question 10

Which of the following data is not required to prepare an estimate?

Detailed Solution for Test: Estimation and Costing - Question 10

For preparing an estimate, data such as drawings, detailed specifications, rates, etc. is required. The drawings needed to prepare the estimate include plans, sections, elevations, etc.

2 videos|122 docs|55 tests
Information about Test: Estimation and Costing Page
In this test you can find the Exam questions for Test: Estimation and Costing solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Estimation and Costing, EduRev gives you an ample number of Online tests for practice

Top Courses for Civil Engineering (CE)

Download as PDF

Top Courses for Civil Engineering (CE)