Test: MRP Work Study & Work Measurement - 1 - Mechanical Engineering MCQ


Test Description

20 Questions MCQ Test GATE Mechanical (ME) Mock Test Series 2025 - Test: MRP Work Study & Work Measurement - 1

Test: MRP Work Study & Work Measurement - 1 for Mechanical Engineering 2024 is part of GATE Mechanical (ME) Mock Test Series 2025 preparation. The Test: MRP Work Study & Work Measurement - 1 questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: MRP Work Study & Work Measurement - 1 MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: MRP Work Study & Work Measurement - 1 below.
Solutions of Test: MRP Work Study & Work Measurement - 1 questions in English are available as part of our GATE Mechanical (ME) Mock Test Series 2025 for Mechanical Engineering & Test: MRP Work Study & Work Measurement - 1 solutions in Hindi for GATE Mechanical (ME) Mock Test Series 2025 course. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free. Attempt Test: MRP Work Study & Work Measurement - 1 | 20 questions in 60 minutes | Mock test for Mechanical Engineering preparation | Free important questions MCQ to study GATE Mechanical (ME) Mock Test Series 2025 for Mechanical Engineering Exam | Download free PDF with solutions
Test: MRP Work Study & Work Measurement - 1 - Question 1

In an MRP system, component demand is: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 1 - Question 1

In a MRP system, component demand is calculated by the MRP system from the Master Production Schedule. 

Test: MRP Work Study & Work Measurement - 1 - Question 2

The principles of motion economy are mostly used while conducting   

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: MRP Work Study & Work Measurement - 1 - Question 3

The proper sequence of activities for material requirement planning is:  

Test: MRP Work Study & Work Measurement - 1 - Question 4

The individual human variability in time studies to determine the production standards is taken care of by: 

Test: MRP Work Study & Work Measurement - 1 - Question 5

Match List-I (Files in MRP) with List-II (Inputs required) and select the correct answer:


Test: MRP Work Study & Work Measurement - 1 - Question 6

A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are allowed for this operation, the expected standard production rate of the weld-joint (in units per 8 hour day) is: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 1 - Question 6

Normal time = 1.2 × 8 = 9.6 minute 

Test: MRP Work Study & Work Measurement - 1 - Question 7

Which one of the following is not a necessary information input to Material Requirements Planning? 

Test: MRP Work Study & Work Measurement - 1 - Question 8

The standard time of an operation while conducting a time study is:   

Detailed Solution for Test: MRP Work Study & Work Measurement - 1 - Question 8

Correct Answer :- c

Explanation : Thus, Standard time = Average Time × Rating factor + Other allowances. 

Standard Time: It is the time, which is taken by a normal worker for a specific task or job, working under moderate conditions and includes other allowances such as fatigue, setting of tool and job, repairing of tool, checking of job etc.

Test: MRP Work Study & Work Measurement - 1 - Question 9

Assertion (A): Master production schedule drives the whole of production and inventory control system in a manufacturing organization.

Reason (R): Master production schedule is a list of daily and weekly work released by PPC to production.  

Test: MRP Work Study & Work Measurement - 1 - Question 10

Fifty observations of a production operation revealed a mean cycle time of 10 min. The worker was evaluated to be performing at 90% efficiency. Assuming the allowances to be 10% of, the normal time, the standard time (in seconds) for the job is: 

Test: MRP Work Study & Work Measurement - 1 - Question 11

Which of the following input data are needed for MRP?

1. Master production schedule
2. Inventory position
3. Machine capacity
4. Bill of materials  

Select the correct answer using the codes given below:  

Test: MRP Work Study & Work Measurement - 1 - Question 12

In a time study exercise, the time observed for an activity was 54 seconds. The operator had a performance rating of 120. A personal time allowance of 10% is given. The standard time for the activity, in seconds, is: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 1 - Question 12


Test: MRP Work Study & Work Measurement - 1 - Question 13

Consider the fo llow ing:

1. A master production schedule
2. An inventory status file
3. Bill of material    

Which of the above are the inputs to MRP systems?  

Test: MRP Work Study & Work Measurement - 1 - Question 14

A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 1 - Question 14

Standard time of the operation = Basic time + Allowances 

Standard time of the operation = 2.4 + 0.24 = 2.64 minutes. 

Test: MRP Work Study & Work Measurement - 1 - Question 15

Match List -I (Pro duction con trol function) with List-II (Explanation) and select the correct answer using the code given below the lists:

Detailed Solution for Test: MRP Work Study & Work Measurement - 1 - Question 15
  • A. Bill of Materials (BOM)

    • This corresponds to: 4. The part numbers & quantity required per assembly.
  • B. Capacity Resource Planning (CRP)

    • This corresponds to: 2. A technique for determining personnel and equipment capacities needed to meet the production objective.
  • C. Material Requirement Planning (MRP)

    • This corresponds to: 1. A technique for determining the quantity and timing of dependent demand items.
  • D. Master Production Schedule (MPS)

    • This corresponds to: 3. Specifies what end items are to be produced and when.

So, the correct matching is:

A - 4
B - 2
C - 1
D - 3

From the given codes, the correct answer is: C

Test: MRP Work Study & Work Measurement - 1 - Question 16

The actual observed time for an operation was 1 minute per piece. If the performance rating of the operator was 120 and a 5 per cent personal time is to be provided, the standard time in minute per piece is: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 1 - Question 16


Test: MRP Work Study & Work Measurement - 1 - Question 17

Which of the following are needed as the input data for materials requirement planning?

1. Weekly production schedule
2. Bill of material
3. Supplier lead time
4. Market forecast  

Test: MRP Work Study & Work Measurement - 1 - Question 18

A soldering operation was work-sampled over two days (16 hours) during which an employee soldered 108 joints. Actual working time was 90% of the total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would be: 

Detailed Solution for Test: MRP Work Study & Work Measurement - 1 - Question 18


Test: MRP Work Study & Work Measurement - 1 - Question 19

Assertion (A): In job design, instead of each job consisting of a single task, a large group of tasks are clustered for a job holder. 

Reason (R): A single job should encompass not only production tasks but also the set up, scheduling and control tasks related to the operation. 

Test: MRP Work Study & Work Measurement - 1 - Question 20

Work study is mainly aimed at 

29 docs|220 tests
Information about Test: MRP Work Study & Work Measurement - 1 Page