Test: CPM & PERT - 4 - Civil Engineering (CE) MCQ


Test Description

10 Questions MCQ Test Topicwise Question Bank for Civil Engineering - Test: CPM & PERT - 4

Test: CPM & PERT - 4 for Civil Engineering (CE) 2024 is part of Topicwise Question Bank for Civil Engineering preparation. The Test: CPM & PERT - 4 questions and answers have been prepared according to the Civil Engineering (CE) exam syllabus.The Test: CPM & PERT - 4 MCQs are made for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: CPM & PERT - 4 below.
Solutions of Test: CPM & PERT - 4 questions in English are available as part of our Topicwise Question Bank for Civil Engineering for Civil Engineering (CE) & Test: CPM & PERT - 4 solutions in Hindi for Topicwise Question Bank for Civil Engineering course. Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free. Attempt Test: CPM & PERT - 4 | 10 questions in 30 minutes | Mock test for Civil Engineering (CE) preparation | Free important questions MCQ to study Topicwise Question Bank for Civil Engineering for Civil Engineering (CE) Exam | Download free PDF with solutions
Test: CPM & PERT - 4 - Question 1

Earliest Date = 20 weeks 
Latest Date = 40 weeks


Activity E is connecting both the events and its duration is 10 weeks. The independent float of the activity is

Detailed Solution for Test: CPM & PERT - 4 - Question 1

Independent float

Test: CPM & PERT - 4 - Question 2

The network rules are common to ail activity on- arrow networking systems. The use of computers for making computations may impose certain rules. Which of the following basic rules of network logic are correct?
1. Before an activity may beg in, all the activities preceding it must be complete.
2. Any two events may be directly connected by not more than one activity.
3. Event numbers must not be duplicated in a network.
Select the correct answer using the codes given below:

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: CPM & PERT - 4 - Question 3

Match List-I (Item) and with List-ll (Characteristic) and select the correct answer using the codes given below the lists:

Codes:

Test: CPM & PERT - 4 - Question 4

A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and some times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

Detailed Solution for Test: CPM & PERT - 4 - Question 4


∴ 
= 21 minutes

Test: CPM & PERT - 4 - Question 5

Consider the following statements:
1. A dummy activity is artificially introduced in a network when necessary,
2. A dummy activity consumes some time.
3. A dummy activity is represented by a dotted arrow.
4. A dummy activity must necessarily be introduced in every network.
Which of the above statements are correct?

Detailed Solution for Test: CPM & PERT - 4 - Question 5

A dummy is introduced artificially and it is shown by a dotted arrow. It does not consume any time. It is not necessary to introduce a dummy always. Thus statements 1 and 3 are correct.

Test: CPM & PERT - 4 - Question 6

Match List-I (Activity type) with List-ll (Representation by) and select the correct answer using the codes given below the lists:

Codes:

Detailed Solution for Test: CPM & PERT - 4 - Question 6

A-4, B-1.C-2, D-3
Artifically introduced activity is dummy and it is shown by a dotted arrow.
Critical activity is represented by a single thick arrow.
Non-critical activity is represented by a single arrow. Dangler does not enter into any event.

Test: CPM & PERT - 4 - Question 7

With reference to the network shown in figure, which statement is incorrect?

Detailed Solution for Test: CPM & PERT - 4 - Question 7

Because dummy activity between events 3 and 7 imposes a restriction on the occurrence of event 7 unless event 3 also occurs.

Test: CPM & PERT - 4 - Question 8

Figure shows the network for a particular project which consists of four activities.

Normal duration time and crash time for each activity are given below:

The minimum time required for the completion of project is

Detailed Solution for Test: CPM & PERT - 4 - Question 8

This is the sum of crash times along the critical path.

Test: CPM & PERT - 4 - Question 9

In PERT analysis, event means

Test: CPM & PERT - 4 - Question 10

Consider the following statements:
1. Tests on cement paste to determine initial and final setting times are done at normal consistency condition.
2. Low heat cement has a high percentage of tricalcium aluminate.
3. High early strength Portland cement contains a larger percentage of tricafcium silicate and a lower percentage of dicalcium silicate.
Which of these statements are correct?

237 tests
Information about Test: CPM & PERT - 4 Page
In this test you can find the Exam questions for Test: CPM & PERT - 4 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: CPM & PERT - 4, EduRev gives you an ample number of Online tests for practice

Top Courses for Civil Engineering (CE)

Download as PDF

Top Courses for Civil Engineering (CE)