In an MRP system, component demand is:
The principles of motion economy are mostly used while conducting
1 Crore+ students have signed up on EduRev. Have you? Download the App |
The proper sequence of activities for material requirement planning is:
The individual human variability in time studies to determine the production standards is taken care of by:
Match List-I (Files in MRP) with List-II (Inputs required) and select the correct answer:
A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are allowed for this operation, the expected standard production rate of the weld-joint (in units per 8 hour day) is:
Which one of the following is not a necessary information input to Material Requirements Planning?
The standard time of an operation while conducting a time study is:
Assertion (A): Master production schedule drives the whole of production and inventory control system in a manufacturing organization.
Reason (R): Master production schedule is a list of daily and weekly work released by PPC to production.
Fifty observations of a production operation revealed a mean cycle time of 10 min. The worker was evaluated to be performing at 90% efficiency. Assuming the allowances to be 10% of, the normal time, the standard time (in seconds) for the job is:
Which of the following input data are needed for MRP?
1. Master production schedule
2. Inventory position
3. Machine capacity
4. Bill of materials
Select the correct answer using the codes given below:
In a time study exercise, the time observed for an activity was 54 seconds. The operator had a performance rating of 120. A personal time allowance of 10% is given. The standard time for the activity, in seconds, is:
Consider the fo llow ing:
1. A master production schedule
2. An inventory status file
3. Bill of material
Which of the above are the inputs to MRP systems?
A stop watch time study on an operator with a performance rating of 120 yielded a time of 2 minute. If allowances of 10% of the total available time are to be given, the standard time of the operation is:
Match List -I (Pro duction con trol function) with List-II (Explanation) and select the correct answer using the code given below the lists:
The actual observed time for an operation was 1 minute per piece. If the performance rating of the operator was 120 and a 5 per cent personal time is to be provided, the standard time in minute per piece is:
Which of the following are needed as the input data for materials requirement planning?
1. Weekly production schedule
2. Bill of material
3. Supplier lead time
4. Market forecast
A soldering operation was work-sampled over two days (16 hours) during which an employee soldered 108 joints. Actual working time was 90% of the total time and the performance rating was estimated to be 120 percent. If the contract provides allowance of 20 percent of the total time available, the standard time for the operation would be:
Assertion (A): In job design, instead of each job consisting of a single task, a large group of tasks are clustered for a job holder.
Reason (R): A single job should encompass not only production tasks but also the set up, scheduling and control tasks related to the operation.
29 docs|220 tests
|