Civil Engineering (CE) Exam  >  Civil Engineering (CE) Tests  >  GATE Civil Engineering (CE) 2025 Mock Test Series  >  Test: Runoff - 1 - Civil Engineering (CE) MCQ

Test: Runoff - 1 - Civil Engineering (CE) MCQ


Test Description

10 Questions MCQ Test GATE Civil Engineering (CE) 2025 Mock Test Series - Test: Runoff - 1

Test: Runoff - 1 for Civil Engineering (CE) 2024 is part of GATE Civil Engineering (CE) 2025 Mock Test Series preparation. The Test: Runoff - 1 questions and answers have been prepared according to the Civil Engineering (CE) exam syllabus.The Test: Runoff - 1 MCQs are made for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test: Runoff - 1 below.
Solutions of Test: Runoff - 1 questions in English are available as part of our GATE Civil Engineering (CE) 2025 Mock Test Series for Civil Engineering (CE) & Test: Runoff - 1 solutions in Hindi for GATE Civil Engineering (CE) 2025 Mock Test Series course. Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free. Attempt Test: Runoff - 1 | 10 questions in 30 minutes | Mock test for Civil Engineering (CE) preparation | Free important questions MCQ to study GATE Civil Engineering (CE) 2025 Mock Test Series for Civil Engineering (CE) Exam | Download free PDF with solutions
Test: Runoff - 1 - Question 1

Direct runoff is made up of

Detailed Solution for Test: Runoff - 1 - Question 1

Direct runoff is that part of runoff which enters the stream immediately after the precipitation. It includes surface runoff, prompt interflow and precipitation on the channel surface.

Test: Runoff - 1 - Question 2

A hydrograph is a plot of

1 Crore+ students have signed up on EduRev. Have you? Download the App
Test: Runoff - 1 - Question 3

The term base flow denotes

Detailed Solution for Test: Runoff - 1 - Question 3

The delayed flow that reaches a stream essentially as groundwater flow is called base flow.

Test: Runoff - 1 - Question 4

Virgin flow is

Detailed Solution for Test: Runoff - 1 - Question 4

A stream flow unaffected by works of man, such as structures for storage and diversion on a stream is called virgin flow.

Test: Runoff - 1 - Question 5

An ephemeral stream

Test: Runoff - 1 - Question 6

An intermittent stream

Detailed Solution for Test: Runoff - 1 - Question 6

An intermittent stream has limited contribution from the groundwater. During the wet season the water table is above the stream bed and there is a contribution of the base flow to the stream flow.

Test: Runoff - 1 - Question 7

The flow-duration curve is a plot of

Detailed Solution for Test: Runoff - 1 - Question 7

A flow-duration curve of a stream is a plot of discharge against the per cent of time the flow was equalled or exceeded. This curve is also known as discharge frequency curve.

Test: Runoff - 1 - Question 8

In a flow-mass curve study the demand line drawn from a ridge in the curve did not interest the mass curve again. This represents that

Test: Runoff - 1 - Question 9

If in a flow-mass curve, a demand line drawn tangent to the lowest point in a valley of the cure does not intersect the mass curve at an earlier time period, it represents that

Test: Runoff - 1 - Question 10

The flow-mass curve is an integral curve of

Detailed Solution for Test: Runoff - 1 - Question 10

The flow mass curve is a plot of the cumulative discharge volume against time plotted in chronological order. The ordinate of the mass curve, V at any time t is,

Since the hydrograph is a plot of Q vs t, it is easy that the flow mass curve is an integral curve of the hydrograph.

31 docs|280 tests
Information about Test: Runoff - 1 Page
In this test you can find the Exam questions for Test: Runoff - 1 solved & explained in the simplest way possible. Besides giving Questions and answers for Test: Runoff - 1, EduRev gives you an ample number of Online tests for practice

Up next

Download as PDF

Up next