The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance?
Most Upvoted Answer
The standard cost of a chemical mixture is as under 8 tons of material...
Materials Variance Calculation

The standard cost of the chemical mixture is based on the following:


  • 8 tons of material A at Rs. 40 per ton

  • 12 tons of material B at Rs. 60 per ton

  • Standard yield is 90% of input


The actual cost for a period is as follows:


  • 10 tons of material A at Rs. 30 per ton

  • 20 tons of material B at Rs. 68 per ton

  • Actual yield is 26.5 tons



Step 1: Calculate Standard Cost

The standard cost of the chemical mixture can be calculated as follows:


  • Material A cost = 8 tons x Rs. 40 per ton = Rs. 320

  • Material B cost = 12 tons x Rs. 60 per ton = Rs. 720

  • Total standard cost = Rs. 320 + Rs. 720 = Rs. 1040



Step 2: Calculate Actual Cost

The actual cost of the chemical mixture can be calculated as follows:


  • Material A cost = 10 tons x Rs. 30 per ton = Rs. 300

  • Material B cost = 20 tons x Rs. 68 per ton = Rs. 1360

  • Total actual cost = Rs. 300 + Rs. 1360 = Rs. 1660



Step 3: Calculate Materials Price Variance

The materials price variance can be calculated as follows:


  • Material A price variance = (10 tons x Rs. 30 per ton) - (10 tons x Rs. 40 per ton) = -Rs. 100

  • Material B price variance = (20 tons x Rs. 68 per ton) - (20 tons x Rs. 60 per ton) = Rs. 160

  • Total materials price variance = -Rs. 100 + Rs. 160 = Rs. 60 (Favorable)



Step 4: Calculate Materials Usage Variance

The materials usage variance can be calculated as follows:


  • Standard input = 8 tons + 12 tons = 20 tons

  • Actual input = 10 tons + 20 tons = 30 tons

  • Standard cost per unit = Rs. 1040 / 20 tons = Rs. 52 per ton

  • Materials usage variance = (20 tons x 90%) - 26.5 tons x Rs. 52 per ton = -Rs. 286 (Unfavorable)



Step 5: Interpretation of Results

The materials variance analysis shows that the total materials variance is Rs. 226 (Favorable). The favorable variance is mainly due to the materials price variance. The unfavorable variance in the materials usage variance is due to the actual yield being lower than the
Community Answer
The standard cost of a chemical mixture is as under 8 tons of material...
,7778
Explore Courses for B Com exam
The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance?
Question Description
The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance? for B Com 2024 is part of B Com preparation. The Question and answers have been prepared according to the B Com exam syllabus. Information about The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance? covers all topics & solutions for B Com 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance?.
Solutions for The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance? in English & in Hindi are available as part of our courses for B Com. Download more important topics, notes, lectures and mock test series for B Com Exam by signing up for free.
Here you can find the meaning of The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance? defined & explained in the simplest way possible. Besides giving the explanation of The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance?, a detailed solution for The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance? has been provided alongside types of The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance? theory, EduRev gives you an ample number of questions to practice The standard cost of a chemical mixture is as under 8 tons of material A at Rs. 40 per ton 12 tons of material B at Rs. 60 per ton Standard yield is 90% of input Actual cost for a period is as under: 10 tons of material A at Rs. 30 per ton 20 tons of material B at Rs. 68 per ton Actual yield is 26.5 tons Compute all materials variance? tests, examples and also practice B Com tests.
Explore Courses for B Com exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev