Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  When actual cost of construction plus certain... Start Learning for Free
When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:
  • a)
    Unscheduled contract
  • b)
    Nominated contract
  • c)
    Cost plus percentage contract
  • d)
    Work order
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
When actual cost of construction plus certain profit is paid to the co...
Work order: This is a contract and specifies the approximate quantities of different items of work, detailed specifications of each item of work, time for completion of the whole work, penalty etc. Small work up to Rs. 2,000 may be carried out by work order.
Cost plus percentage contract: In this type of contract, contractor is given certain percentage over the actual cost of the construction as his profit. Contractor arranges materials and labour at his cost and keeps proper account and he is paid by the department or owner the whole cost together with certain percentage, say 10% as his profit as agreed upon beforehand.
View all questions of this test
Most Upvoted Answer
When actual cost of construction plus certain profit is paid to the co...
Cost Plus Percentage Contract

A cost plus percentage contract is a type of construction contract in which the contractor is paid for the actual cost of construction plus a certain percentage of profit. In this type of contract, the contractor is reimbursed for all expenses incurred during the construction process, including labor, materials, equipment, and subcontractor fees. Additionally, the contractor is paid a percentage of the total cost of construction as profit.

Advantages

1. Transparency: Cost plus percentage contracts are highly transparent, as all costs and expenses are clearly documented and accounted for.

2. Flexibility: This type of contract allows for greater flexibility in terms of changes to the project scope, as the contractor is reimbursed for actual costs and can adjust the project as needed.

3. Incentivizes efficient work: The contractor has an incentive to work efficiently and minimize costs, as their profit is based on a percentage of the total cost of construction.

Disadvantages

1. No fixed cost: Since the total cost of construction is not fixed, it can be difficult for the owner to budget and plan for the project.

2. Risk of overcharging: There is a risk that the contractor may overcharge for expenses or inflate costs in order to increase their profit margin.

3. Lack of predictability: Since the final cost of the project is uncertain, it can be difficult to predict the final outcome of the project in terms of time and cost.

Conclusion

Overall, cost plus percentage contracts can be a beneficial option for construction projects in which there is a high degree of uncertainty or flexibility in the project scope. However, it is important for owners to carefully monitor costs and ensure that the contractor is working efficiently and transparently.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer?
Question Description
When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer?.
Solutions for When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice When actual cost of construction plus certain profit is paid to the contractor then such a contract is known as:a)Unscheduled contractb)Nominated contractc)Cost plus percentage contractd)Work orderCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev