Four jobs are to be processed on a machine as per data listed in the table.
Using the Shortest Processing Time (SPT) rule, total tardiness is
  • a)
    0
  • b)
    2
  • c)
    6
  • d)
    8
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Four jobs are to be processed on a machine as per data listed in the t...
Since, negative tardiness is not considered as delay i.e. considered as 0 tardiness.
So, Total tardiness =  0 + 0 + 4 + 4 = 8
View all questions of this test
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer?
Question Description
Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer?.
Solutions for Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Four jobs are to be processed on a machine as per data listed in the table.Using the Shortest Processing Time (SPT) rule, total tardiness isa)0b)2c)6d)8Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam
Signup to solve all Doubts
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev