Teaching Exam  >  Teaching Questions  >  A can complete a project in 20 days and B can... Start Learning for Free
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed? 
  • a)
    16 days 
  • b)
    27 days 
  • c)
    26.67 days 
  • d)
    18 days 
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
A can complete a project in 20 days and B can complete the same projec...
View all questions of this test
Most Upvoted Answer
A can complete a project in 20 days and B can complete the same projec...
Given:
A can complete the project in 20 days
B can complete the project in 30 days

To find:
In how many days will the project be completed if A quits 10 days before it is completed?

Approach:
To solve this problem, we can calculate the rate at which A and B work individually and then find their combined rate when working together. Using their combined rate, we can determine the number of days required to complete the project.

Let's start by calculating the work rate of A and B separately.

Calculating the work rate of A:
A can complete the project in 20 days, which means that A completes 1/20th of the project in a day.
So, the work rate of A is 1/20.

Calculating the work rate of B:
B can complete the project in 30 days, which means that B completes 1/30th of the project in a day.
So, the work rate of B is 1/30.

Now, let's calculate their combined work rate when working together.

Calculating the combined work rate:
When A and B work together, their work rates are added.
Combined work rate = 1/20 + 1/30
Combining the fractions, we get 3/60 + 2/60 = 5/60.
So, the combined work rate is 5/60.

Now, let's determine the number of days required to complete the project.

Calculating the number of days:
Let the number of days required to complete the project when A quits be x.
Since A quits 10 days before the project is completed, A works for (x-10) days.
B works for x days.

Using the work rate formula (Work = Rate * Time), we can write the equation:

1 = (5/60) * (x-10) + (1/30) * x

Simplifying the equation:
Multiplying through by 60 to eliminate fractions, we get:

60 = 5(x-10) + 2x

60 = 5x - 50 + 2x

Combining like terms, we get:

60 = 7x - 50

Adding 50 to both sides, we get:

110 = 7x

Dividing by 7, we get:

x = 110/7

x ≈ 15.71

Therefore, the project will be completed in approximately 15.71 days, which can be rounded to 16 days.

Hence, the correct answer is option D) 16 days.
Explore Courses for Teaching exam
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer?
Question Description
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer? for Teaching 2024 is part of Teaching preparation. The Question and answers have been prepared according to the Teaching exam syllabus. Information about A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Teaching 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer?.
Solutions for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Teaching. Download more important topics, notes, lectures and mock test series for Teaching Exam by signing up for free.
Here you can find the meaning of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed in how many days will the project be completed?a)16 daysb)27 daysc)26.67 daysd)18 daysCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Teaching tests.
Explore Courses for Teaching exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev