Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).

 
    Correct answer is '(6.33)'. Can you explain this answer?
    Verified Answer
    Processing times (including step times) and due dates for six jobs wai...
    By SPT Rule

    Total tardiness = 38
    Average tardiness per job
    View all questions of this test
    Explore Courses for Mechanical Engineering exam

    Similar Mechanical Engineering Doubts

    Top Courses for Mechanical Engineering

    Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer?
    Question Description
    Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer?.
    Solutions for Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
    Here you can find the meaning of Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer?, a detailed solution for Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer? has been provided alongside types of Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is _________(correct to two decimal places).Correct answer is '(6.33)'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev