The following document contains detailed description of all items of work excluding their quantities, along with the current rates:
  • a)
    Analysis of rates
  • b)
    Tender document
  • c)
    Abstract estimate
  • d)
    Schedule of rates
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
The following document contains detailed description of all items of w...
Tender is an offer to execute some specified work or to supply some specified article at certain rates. While inviting tender the bill of quantities, detailed specifications, conditions of contract and plans and drawings are supplied.
Schedule of rates is a list of rates of various items of works to facilitate the preparation of estimates and to serve as a guide in setting rates in connection with contract agreement. 
View all questions of this test
Most Upvoted Answer
The following document contains detailed description of all items of w...
Explanation:

The correct answer is option 'D' - Schedule of rates. Let's understand why the other options are not the correct answer:

a) Analysis of rates: Analysis of rates refers to the detailed breakdown of the cost of each item of work. It includes the quantities, rates, and costs of all the materials, labor, and equipment required for the completion of a specific project. However, the question specifically states that the document excludes the quantities of work.

b) Tender document: A tender document is a set of documents that provides information about a project, including the scope of work, specifications, terms and conditions, and other relevant details. While a tender document may contain the rates for each item of work, it also includes the quantities, which are excluded in this case.

c) Abstract estimate: An abstract estimate is a summary of the estimated cost of a construction project. It includes the total cost of various items of work, but it does not provide detailed descriptions of each item or their rates. Therefore, it does not align with the description given in the question.

d) Schedule of rates: A schedule of rates is a document that provides detailed descriptions of all the items of work, along with their rates. It does not include the quantities of work, which matches the description given in the question. The schedule of rates is typically prepared by the relevant authorities or organizations and is used as a reference for estimating the cost of construction projects. It is an essential document for contractors and project managers to determine the cost of individual items of work.

In summary, the document that contains detailed descriptions of all items of work excluding their quantities, along with the current rates, is the schedule of rates. This document is crucial for estimating the cost of construction projects and is commonly used in the civil engineering field.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer?
Question Description
The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer?.
Solutions for The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The following document contains detailed description of all items of work excluding their quantities, along with the current rates:a)Analysis of ratesb)Tender documentc)Abstract estimated)Schedule of ratesCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev