A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
The minimum project completion time (in days) is ______
    Correct answer is '30'. Can you explain this answer?
    Verified Answer
    A project starts with activity A and ends with activity F. The precede...
    ∴ Minimum project completion Time = Length of longest path = 4+3+14+9=30 Days.
    View all questions of this test
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer?
    Question Description
    A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer?.
    Solutions for A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
    Here you can find the meaning of A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer?, a detailed solution for A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer? has been provided alongside types of A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:The minimum project completion time (in days) is ______Correct answer is '30'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev